Public Service Commission v. City of Annapolis

526 A.2d 975, 71 Md. App. 593, 1987 Md. App. LEXIS 339
CourtCourt of Special Appeals of Maryland
DecidedJune 11, 1987
DocketNo. 1483
StatusPublished
Cited by3 cases

This text of 526 A.2d 975 (Public Service Commission v. City of Annapolis) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Commission v. City of Annapolis, 526 A.2d 975, 71 Md. App. 593, 1987 Md. App. LEXIS 339 (Md. Ct. App. 1987).

Opinion

WILNER, Judge.

In 1974, the General Assembly enacted a new § 8.14.1 to the Zoning and Planning article of the Code (Md.Code Ann. art. 66B). The law authorized the counties and municipal [595]*595corporations of the State to enact ordinances requiring utilities with overhead lines in historic districts to relocate those lines underground; it directly required the utilities having overhead lines in the historic districts of Annapolis and Frederick to place them underground.

Although there is little in the way of officially recorded legislative history with respect to that law, it seems evident from amendments put on during the legislative process that the principal focus of the Legislature was not so much on the desirability of burying the overhead lines as on who was to bear the cost of the work. That is the issue before us in this appeal.

There appear to be three categories of cost involved: (1) digging up the streets or sidewalks, removing the existing overhead wires and facilities, and placing them underground; (2) repaving the streets and sidewalks; and (3) reconnecting the affected customers to the underground lines. The law makes clear that the third category of cost is to be borne by the affected customers, although it authorizes the county or city to advance the reconnection costs and recover them through a special benefit assessment against property in the historic district. We are not directly concerned with that category in this case.

Initially, the bill would have required the utilities to advance the other capital costs of the relocation and to recover those costs through their general rate structure. In that regard, it proposed to enact a new § 72A to the Public Service Commission Law (Md.Code Ann. art. 78) stating:

“The Public Service Commission shall, at the time of setting rates for an affected utility, permit the inclusion in the general rate base of capital costs associated with the relocation underground of utility lines and facilities in connection with projects required by Section 8.14.1 of Article 66B of the code.”

See, 1974 Md.Laws, ch. 651 (Sen.Bill 805).

That approach would have had the dual effect of spreading the cost among all customers of the utilities — not just [596]*596thosé living in the historic districts — and of possibly allowing the utilities to recover more than their actual cost,1 and it was discarded. In its place, the Legislature recrafted proposed § 72A; as enacted, it reads as follows:

“With respect to the net capital costs associated with the relocation underground of utility lines and facilities in connection with projects required by § 8.14.1 of Article 66B of the Code, the Public Service Commission shall prescribe the amount of the monthly surcharge required to support the said costs and determine which customers of the applicable utility are subject to the surcharge, or shall include in the rate base the related net capital costs, or shall adopt any other method to appropriately apportion the costs. However, in no event shall the utility be required to pay more than 50 percent of the net capital costs. The county, municipal corporation, or Baltimore City is authorized to make appropriations for such relocation projects from any appropriate federal, State, and local funds it receives for this purpose.”

It is evident from this statute that the Legislature did not intend for the utilities or their customers to bear more than 50% of the “related net capital costs” of the relocation, and that it expected any part of the cost not allocated to the utilities to come from public funds. The question is whether the Public Service Commission was authorized to direct that the entire cost of the relocation be paid from public funds, in particular whether, under its authority to “adopt any other method to appropriately apportion the costs,” the Commission could require that the full cost of relocating the overhead lines and facilities in the historic district of Annapolis be paid by the City of Annapolis. That is what the [597]*597Commission did; the Circuit Court for Anne Arundel County held that the Commission had no authority to do so. We disagree with the Circuit Court but shall affirm for other reasons.

Annapolis was not the first municipality to require the undergrounding of utility lines. A number of subdivisions, through zoning ordinances or regulations, have historically required service to new developments to be provided through underground lines. That, of course, does not involve the relocation of existing lines, but it does increase the cost of installing the new lines. In that regard, as far back as 1966, the Commission had established a general policy, reflected in Order No. 56351 in Case No. 6016, that, whenever an electric utility is required to construct its lines underground at a cost substantially higher than the cost to construct the same lines overhead, absent unusual circumstances the annual fixed cost necessary to support the excess investment “shall be imposed on all of the utility’s customers receiving service in the geographic area and/or the local subdivision to which the regulation or ordinance is applicable as a whole.” (Emphasis in original).

Frederick was apparently the first city to take advantage of the 1974 law and require the undergrounding of existing overhead utility lines in its historic district. In that case, the Commission directed that the city pay half the relocation cost and that the other half be advanced by the utilities, to be recovered by a one-time surcharge on their customers in the city. See Matter of the Application of the Potomac Edison Co., 66 P.S.C.Rep. 181, Order No. 61252 (1975).

The case now before us originated with a letter-petition from the Baltimore Gas and Electric Co. (BG & E) on April 22, 1985. The company informed the Commission that the City of Annapolis had “approached” it regarding the power lines in the historic district of the City, that the first phase of the work, near the Governor’s Mansion, would cost about $175,000, and that the total project would take five years or more to complete and would cost “several million dollars.” The company read the law as requiring the City to pay 50% [598]*598of the cost “with the remaining 50% to be handled either as a surcharge to customers within the Municipality, or as a rate base item.” It asked the Commission to approve “rate base treatment,” contending that that approach was “consistent with a long-standing Company policy” and that the cost of administering a surcharge program would be excessive.

The BG & E “petition” was referred to the Commission’s technical staff for review. On June 4,1985, the staff filed a report dated May 10, 1985, in which it objected to rate base treatment and recommended instead, that the utility’s cost be recovered through surcharges on BG & E’s Annapolis customers. The staff seemed to accept the notion that 50% of the cost would be paid by the City and dealt only with how the other half, to be advanced by the utility, would be recovered. They observed that the Commission had never established any policy in that regard, that the C & P Telephone Co., which also had overhead lines in the historic district, had recommended the surcharge approach, and that there was some question of whether the project would actually proceed beyond Phase I ($175,000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)
American Insurance v. United States
62 Fed. Cl. 151 (Federal Claims, 2004)
Cornejo-Ortega v. United States
61 Fed. Cl. 371 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
526 A.2d 975, 71 Md. App. 593, 1987 Md. App. LEXIS 339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-commission-v-city-of-annapolis-mdctspecapp-1987.