Public Power Council, Inc. v. Bonneville Power Administration

442 F.3d 1204, 2006 WL 851737
CourtCourt of Appeals for the Ninth Circuit
DecidedApril 4, 2006
DocketNos. 04-73240, 04-73939, 04-73952, 04-73934
StatusPublished
Cited by1 cases

This text of 442 F.3d 1204 (Public Power Council, Inc. v. Bonneville Power Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Power Council, Inc. v. Bonneville Power Administration, 442 F.3d 1204, 2006 WL 851737 (9th Cir. 2006).

Opinion

FERNANDEZ, Circuit Judge.

Public Power Council, Inc., and others (collectively PPC) petition for a review of the decision of the Bonneville Power Administration (BPA) to trigger the Safety-Net Cost Recovery Adjustment Clause (SN CRAC) portion of its General Rate Schedule Provisions (GRSPs), as a result of which a rate setting proceeding took place. Canby Utility Board also petitions for a review on the basis that because it had a special contract with BPA, its rates could not be changed in any event. We deny the petitions.

BACKGROUND

BPA is a “self-financing power marketing agency,” which markets wholesale electricity from federal hydroelectric plants and several other power plants in the Pacific Northwest. Aluminum, Co. of Am. v. Bonneville Power Admin., 903 F.2d 585, 588 (9th Cir.1990). “It owns and operates approximately eighty percent of the Pacific Northwest’s high-voltage transmission system and markets approximately forty percent of the electric power consumed in the Pacific Northwest.” Indus. Customers of N.W. Utils. v. Bonneville Power Admin., 408 F.3d 638, 641 (9th Cir.2005). “BPA’s customers include federal agencies, public bodies (including public utilities), private utilities,” and Direct Service Industrial customers. Kaiser Aluminum & Chem. Corp. v. Bonneville Power Admin., 261 F.3d 843, 845 (9th Cir.2001).

Essentially, BPA is governed by four organic statutes: “the Bonneville Project Act of 1937, 16 U.S.C. §§ 832-832m (‘Project Act’); the Pacific Northwest Consumer Power Preference Act of 1964, 16 U.S.C. §§ 837-837h (‘Preference Act’); the Pacific Northwest Federal Transmission System Act of 1974, 16 U.S.C. §§ 838-8381 (‘Transmission Act’); and the Pacific Northwest Electric Power Planning and Conservation Act of 1980, 16 U.S.C. §§ 839-839h (‘Northwest Power Act’).” Kaiser Aluminum & Chem. Corp., 261 F.3d at 845. It is authorized to issue and sell bonds to the United States Treasury “to assist in financing the construction, acquisition, and replacement of the transmission system.” 16 U.S.C. § 838k(a). However, it must repay a projected amount of those bonds each fiscal year; if it fails to do so, the Treasury, with some exceptions, may increase the applicable interest rate for that year’s outstanding bonds. Id.

Since 1974, BPA’s electricity sales have been its source of revenue. See Indus. Customers, 408 F.3d at 641. Thus, the Northwest Power Act requires BPA “to establish rates that will produce sufficient revenues to ensure BPA’s fiscal independence and repay the U.S. Treasury for the federal funds that were borrowed to build the projects in the Federal Columbia River Power System.” Cal. Energy Comm’n v. Bonneville Power Admin., 909 F.2d 1298, 1303(9th Cir.1990). At the same time, “[t]he statute also requires that rates be as low as possible consistent with sound business principles.” Cent. Lincoln [1207]*1207Peoples’ Util. Dist. v. Johnson, 735 F.2d 1101, 1116 (9th Cir.1984).

In order to fulfill its mission, BPA must periodically revise its rates. See Indus. Customers, 408 F.3d at 642. It does so pursuant to § 7 of the Northwest Power Act (16 U.S.C. § 839e). Its power rates, other charges, cost adjustments and rate methodology are then defined in its wholesale power rate schedules. The rate schedules contain GRSPs, which set out the provisions that govern the various rates in question. See Indus. Customers, 408 F.3d at 642.

In August of 1999, BPA proposed to revise its wholesale power rates for the five year period between October 1, 2001, and September 30, 2006 (the “WP-02 Rates”).1 BPA conducted hearings in accordance with § 7(i) of the Northwest Power Act (16 U.S.C. § 839e(i)). Those are hereafter referred to as the “WP-02 Rate Proceeding.” On May 10, 2000, BPA completed the final record of decision for the proposed WP-02 Rates (May 2000 ROD). On July 6, 2000, BPA filed its proposed WP-02 Rates with the Federal Energy Regulatory Commission (FERC) for approval.

During the summer of 2000, however, wholesale power rates rose precipitously. As a result, BPA’s proposed WP-02 Rates became far more attractive to prospective customers. Its preference customers thus sought to purchase much more power for the 2002-2006 period than BPA had anticipated. Supplying that would require BPA to make up any shortfall in its production capacity by purchasing power on the open market. It, therefore, became concerned that the WP-02 Rates established in the May 2000 ROD would not be sufficient to cover its costs. Consequently, on August 4, 2000, BPA filed a motion with FERC to stay review of BPA’s WP-02 Rates. See BPA’s Proposed Safety-Net Cost Recovery Adjustment Clause Adjustment to 2002 Wholesale Power Rates, 68 Fed.Reg. 12,048, 12,049 (Mar. 13, 2003).

On September 4, 2000, BPA notified FERC that it would pursue modifications to the WP-02 Rates. In October 2000, after a public comment period, it notified FERC and parties to the WP-02 Rate Proceeding that it was initiating a limited § 7(i) (16 U.S.C. § 839e(i)) hearing, in which it would revise the WP-02 Rates in order to address its increased load obligations and high market prices. It matched its actions to its words, and on December 1, 2000, it proposed amendments to the proposed WP-02 Rates. BPA’s Proposed Amendments to 2002 Wholesale Power Rate Adjustment Proposal, 65 Fed.Reg. 75,272 (Dec. 1, 2000); see also Indus. Customers, 408 F.3d at 642. Once again, however, BPA’s announcement of proposed rates was followed by a downturn in its financial outlook. Its forecast for cash reserves dropped substantially, while market prices rose significantly more than expected. Those developments induced BPA to make various additional changes to its proposed amendments to the WP-02 Rates. See Indus. Customers, 408 F.3d at 642. That process led to the filing of the WP-02 Supplemental Proposal (June 2001 ROD) and to the ultimate adoption of three Cost Recovery Adjustment Clauses (CRACs) as a part of the GRSPs. Those were:

(1) The Load Based CRAC (LB CRAC), which triggers if BPA’s augmentation cost (cost of purchasing power on the open market) exceeds the forecasted amount. Essentially, the LB CRAC is a formula for increasing base rates by a certain percentage, depending on what BPA pays to acquire excess power.

[1208]*1208(2) The Financial Based CRAC (FB CRAC), which triggers if BPA’s accumulated net revenues fall below a certain threshold. Like the LB CRAC, the triggering of the FB CRAC results in a percentage increase to BPA’s base power rates.

(3) Finally, the SN CRAC, which triggers if, after implementation of the FB CRAC, BPA has missed, or reasonably expects to miss, a payment to the United States Treasury or another creditor. The disputes here revolve around the SN CRAC. As we have indicated previously:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
442 F.3d 1204, 2006 WL 851737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-power-council-inc-v-bonneville-power-administration-ca9-2006.