Psalm 23 Project, Inc. v. H. J. Russell & Co.

698 S.E.2d 379, 304 Ga. App. 886, 2010 Fulton County D. Rep. 2435, 2010 Ga. App. LEXIS 670
CourtCourt of Appeals of Georgia
DecidedJuly 8, 2010
DocketA10A0036
StatusPublished
Cited by1 cases

This text of 698 S.E.2d 379 (Psalm 23 Project, Inc. v. H. J. Russell & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Psalm 23 Project, Inc. v. H. J. Russell & Co., 698 S.E.2d 379, 304 Ga. App. 886, 2010 Fulton County D. Rep. 2435, 2010 Ga. App. LEXIS 670 (Ga. Ct. App. 2010).

Opinion

BARNES, Presiding Judge.

H. J. Russell & Company (“Russell”) sued The Psalm 23 Project, Inc. (“Psalm 23”) and The Promise Project, Inc. (“Promise Project”) for payments due under several construction contracts. Both defendants answered, and Psalm 23 filed a counterclaim alleging that Russell owed it money. Following discovery, Russell moved for summary judgment on its claims and Psalm 23’s counterclaim. The trial court granted the motion, and the defendants appeal. For the reasons that follow, we affirm in part and reverse in part.

I. Summary judgment is appropriate when no genuine issues of material fact remain and the moving party is entitled to judgment as a matter of law. Mustaqeem-Graydon v. Suntrust Bank, 258 Ga. App. 200, 205 (1) (573 SE2d 455) (2002). We review the grant of summary judgment de novo, construing the evidence and all reasonable inferences favorably to the nonmoving party. Id.

So viewed, the record shows that in the late 1990s, Green Pastures Christian Ministries, Inc. (“Green Pastures”) decided to build two independent living facilities for senior citizens on land it owned in DeKalb County. Green Pastures was awarded two grants from the United States Department of Housing and Urban Development (“HUD”) to assist in the construction costs. It then formed two not-for-profit corporations — Psalm 23 and Promise Project — to own and operate the separate facilities.

On July 1, 2004, Psalm 23 contracted with Russell, a general contractor, to construct the first facility, which became known as Green Pastures Commons I. That same day, Promise Project contracted with Russell to construct Green Pastures Commons II, the second facility. As required by county authorities, Psalm 23 also entered into a standard American Institute of Architects (“ALA”) agreement with Russell to widen the road fronting the facilities for an entrance lane and to build a “lift station” to pump sewage from the property.

The ALA agreement obligated Psalm 23 to pay Russell $800,000 *887 for the road widening and lift station project. HUD regulations prohibited Psalm 23 from using grant money to fund this type of “offsite” work. The regulations also demanded, however, that the work be completed. HUD thus required Psalm 23 to escrow the $800,000 needed to pay for the project. Although Psalm 23 did not have the necessary funds, Green Pastures raised $800,000 by selling land that it owned next to the assisted living facility sites to Etowah Development, Inc. (“Etowah”). Psalm 23 placed this money into an escrow account in July 2004.

Approximately eight months later, on March 1, 2005, Green Pastures, Etowah, and Russell entered into a separate agreement regarding the road widening and lift station project (“the March 2005 agreement”). Apparently, Etowah planned to develop a subdivision on the property it had purchased from Green Pastures and wanted to use the entrance way and lift station. Under this new agreement, Green Pastures and Etowah expressed a desire to “share in the cost of” certain infrastructure work that included, but was not limited to, the road widening, entrance way, and lift station improvements. They thus agreed that Green Pastures would be responsible for one-third of the project costs, while Etowah would bear two-thirds of the costs. The contract provided that Green Pastures had “escrowed funds necessary to cover its . . . share of the Costs, which shall not exceed the amount of $800,000.” It also obligated Etowah to perform work on the infrastructure project and submit invoices for Green Pastures’ share of the costs to Russell, which would review the invoices and obtain payment approval from HUD.

Without dispute, Russell built the two facilities and completed the contract work. On June 8, 2006, it requested $71,674.55 from Psalm 23 for final payment under the AIA agreement. That same day, it sent letters indicating that final payment of $100,959 from Psalm 23 and $107,811 from Promise Project would be due on the Green Pastures Commons I and Commons II projects “[u]pon authorization by HUD.” In August 2007, HUD issued closing memo-randa designating August 17, 2007, as the “Date of Final Closing” for both projects. Later that fall, Russell demanded final payment as to these two contracts, as well as the outstanding balance on the AIA contract.

When Psalm 23 and Promise Project did not remit the requested sums, Russell filed suit, seeking payment of principal due under the three contracts plus interest and attorney fees. Psalm 23 filed a counterclaim, alleging that Russell owed it money relating to the road widening and lift station project. According to Psalm 23, the March 2005 agreement modified the AIA contract and reduced its $800,000 liability by two-thirds. In its view, it did not owe any money on the project and, in fact, had substantially overpaid Russell *888 following the modification. Ultimately, Psalm 23 sought to recover approximately $500,000 from the general contractor.

After several months of litigation, Psalm 23 and Promise Project paid the principal balances owed under the Green Pastures Commons I and Commons II contracts. Disputes remained, however, about the interest owed under these contracts, as well as liability relating to the road widening/lift station project. Russell subsequently moved for summary judgment. The trial court granted the motion, awarding Russell $30,287.70 in interest on the Green Pastures Commons I contract; $32,343.30 in interest on the Green Pastures Commons II contract; and $71,645.55 in principal owed under the ALA contract, plus $29,386.57 in interest. The court also dismissed Psalm 23’s counterclaim as moot.

Psalm 23 and Promise Project challenge these rulings on appeal. Psalm 23 argues that issues of fact remain as to its liability under the ALA contract and its counterclaim against Russell. Both defendants also question the interest awarded on the various contracts.

(a) Psalm 23 claims that its $800,000 obligation under the July 2004 ALA contract was modified by the March 2005 agreement executed by Green Pastures, Etowah, and Russell. The contracts at issue, however, do not support this claim. The ALA contract clearly obligated Psalm 23 to pay Russell $800,000 for the road widening and lift station work. Nothing in the March 2005 agreement altered this obligation. The agreement did not reference the ALA contract or Psalm 23. And despite Psalm 23’s claims, the March 2005 agreement did not reduce its liability to Russell by two-thirds or require Russell to forfeit or pay back any portion of the $800,000 allocated for the work. Rather, the agreement provided that Etowah and Green Pastures would share (on a two-thirds to one-third basis) the cost of infrastructure work that included, but was not limited to, the road widening and lift station, and it capped Green Pastures’ payment at $800,000 — the amount already escrowed for the road widening and lift station project.

Absent an ambiguity, a court must enforce a contract as written. ESI Companies v. Fulton County, 271 Ga. App. 181, 183 (1) (a) (609 SE2d 126) (2004). Certainly, the March 2005 agreement lacks clarity in some respects. The fact that it does not reference Psalm 23, for example, is odd. But the agreement’s language cannot be interpreted as altering the ALA contract or reducing Psalm 23’s liability under that contract by two-thirds. At best, it confirmed that Green Pastures/Psalm 23’s obligation for

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Davidson v. Lindfield Holdings, LLC
Court of Appeals of Georgia, 2021

Cite This Page — Counsel Stack

Bluebook (online)
698 S.E.2d 379, 304 Ga. App. 886, 2010 Fulton County D. Rep. 2435, 2010 Ga. App. LEXIS 670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/psalm-23-project-inc-v-h-j-russell-co-gactapp-2010.