GOODWIN, J.

The defendants appeal from a verdict and judgment for Leslie N. Pruett for damages resulting from severe burns inflicted by an electrical trauma in the course of his employment.

Pruett was employed as a construction worker by a partnership engaged in the general contracting business. He was working with concrete in the building of a bridge on a Jackson County road known as Ross Lane. The bridge crossed Jackson Creek parallel to *617 an electrical transmission line. The wires were about 25 feet above the northern edge of the bridge.

On July 27, 1954, the day of the accident which gave rise to this litigation, there was present at the construction site a mobile crane. The crane was being used to swing a concrete bucket from a point near the bridge where concrete-mixer trucks disgorged their contents to the places on the bridge where Pruett’s employers might utilize the cement during the course of construction. This crane was owned and operated by the defendants, all of whom are members of a partnership which was engaged in both the pre-mixed cement business and also in the business of renting heavy equipment.

On the day of the accident, the defendants, as they will be referred to hereafter, were the suppliers of the ready-mix concrete used in the construction of the bridge. While the evidence established that the business of selling concrete and the business of furnishing heavy equipment to other contractors did not always go hand in hand, the defendants were, on July 27, 1954, furnishing both services to Pruett’s employers.

The defendants, like the employers of Pruett, had secured coverage for their workmen under the Workmen’s Compensation Act. The man who was operating the defendants’ crane on the date of the accident was a partner in the defendants’ business, but there is no dispute that he was, like the other workmen of both employers, covered by the Compensation Act.

The procedure usually followed by Pruett’s employers may be briefly described as follows: The defendants’ ready-mix trucks would deliver their contents to the job by means, of a chute fastened to the rear of the truck. At the point where the wet concrete *618 left the chute, it became the duty of the purchaser (Pruett’s employers) to place the concrete in the forms. If the forms were close enough to the truck, the operation was comparatively simple. The truck operator merely regulated the flow of the concréte down the chute to accommodate the workmen who spread the concrete and worked it into the forms. If the truck could not approach the forms close enough for direct placement into the forms, Pruett and his fellow workmen ordinarily wheeled the wet concrete away from the truck in wheeled bucket carts, or “buggies”, as the witnesses called them.

On or before the day of the accident, it was decided by Pruett’s employers to utilize a crane with a bucket suspended from a boom to receive the contents of the ready-mix trucks.- The crane would then swing the wet concrete out over the bridge to the point where it was desired that it be placed in the forms. The use of the crane eliminated the necessity of workmen wheeling the buggies- over the surface of the bridge and also speeded the work. Since the-bridge contractors did not own a crane, they hired, at an hourly rate, the use of the defendants’ crane.

The financial arrangements between Pruett’s employers and the defendant's were not formalized in writing. The evidence showed that the defendants charged Pruett’s employers the prevailing price for concrete delivered to the job, and then charged an additional sum for the hourly use of the crane with an operator. The crane operator was selectd by the defendants, paid by them, and was under the supervision of the defendants in the manner in which he operated and maintained the equipment. The operator was, however, under the supervision of the bridge contractors in that they could and did give him in *619 structions with reference to when and where the concrete bucket was to be emptied. The testimony revealed that these instructions, as is customary in work of that kind, were for the most part unspoken, and were given by signals and gestures from the workmen on the biidge Pruett was one of the workmen who gave signals to the crane operator.

While the work described above was in progress, Pruett either pushed the crane bucket, or had a hand on it, when the boom from which the bucket was suspended swung into the proximity of the power line above the bridge. There was a conflict in the testimony whether Pruett pushed the cement-filled bucket or whether the crane operator caused the cable to approach the power line. In any event, the cable suspending the crane bucket either touched the power line or came so close to the wire that a charge of 7,200 volts of electricity was caused to pass through Pruett’s body. The evidence on the question of negligence was resolved by the jury in favor of Pruett.

There are numerous assignments of error, but the key question is whether the trial court erred in ruling upon two affirmative defenses, which, under the facts stated above, presented questions of law for the court.

The defendants had pleaded two theories which would bring the case within the exclusive coverage of the Workmen’s Compensation Act: (a) joint supervision and control under OPS 656.154; and, in the alternative, (b) that the crane operator was in the same employ as Pruett on the theory that the crane operator was a loaned employe. Each theory was sufficient, if established, to bar the action and to limit Pruett’s remedy to his benefits under the Workmen’s Compensation Act.

The pleading of alternative defenses, as of alter *620 native statements of the same cause of action, is permissible so long as each is separately stated. Cook v. Kinzua Pine Mills Co. et al, 207 Or 34, 293 P2d 717; Susznik v. Alger Logging Co., 76 Or 189, 147 P 922, Ann Cas ’17C700; Clark, Handbook of the Law of Code Pleading (2d ed, 1947) 629, §99; 1 Bancroft, Code Pleading (1926) 401-414, §§248-256. Our code provides that the defendant may plead any new matter constituting a defense, ORS 16.290 (b); separate defenses must be pleaded separately, ORS 16.090; and pleadings must be liberally construed, ORS 16.120. It is within the trial court’s discretion whether to allow a motion to require an election. Cook v. Kinzua Pine Mills Co. et al, supra at 59.

It is the rule in Oregon that inconsistent defenses may not be pleaded when they are so contradictory that if one is true then the other must be false in fact. Sussnih v. Alger Logging Co., supra. Such a pleading may be stricken as sham under ORS 16.100.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynaga v. Northwest Farm Bureau
709 P.2d 1071 (Oregon Supreme Court, 1985)
Cody v. Disco, Inc.
628 P.2d 766 (Court of Appeals of Oregon, 1981)
Roberts v. Mitchell Bros. Truck Lines
611 P.2d 297 (Oregon Supreme Court, 1980)
Perkins v. Willamette Industries, Inc.
542 P.2d 473 (Oregon Supreme Court, 1975)
Sanders v. City Center Lumber Co.
518 P.2d 1032 (Oregon Supreme Court, 1974)
Tidyman v. Industrial Air Products Co.
512 P.2d 792 (Oregon Supreme Court, 1973)
Vetter v. Pacific Motor Trucking Co.
512 P.2d 785 (Oregon Supreme Court, 1973)
Deitz v. Savaria
491 P.2d 620 (Oregon Supreme Court, 1971)
Bass v. DUNTHORPE MOTOR TRANSPORT CO.
484 P.2d 319 (Oregon Supreme Court, 1971)
Carlston v. Greenstein
471 P.2d 806 (Oregon Supreme Court, 1970)
Cornelison v. Seabold
460 P.2d 1009 (Oregon Supreme Court, 1969)
Layton v. Leep Logging, Inc.
430 P.2d 1008 (Oregon Supreme Court, 1967)
Tallmon v. Toko Kaium K.K. Kobe
278 F. Supp. 452 (D. Oregon, 1967)
Richey v. Sumoge
273 F. Supp. 904 (D. Oregon, 1967)
Penrose v. Mitchell Bros. Crane Division, Inc.
426 P.2d 861 (Oregon Supreme Court, 1967)
Shoemaker v. Johnson
407 P.2d 257 (Oregon Supreme Court, 1965)
Mayor v. Dowsett
400 P.2d 234 (Oregon Supreme Court, 1965)
Mason v. Sutherlin MacHine Works, Inc.
399 P.2d 1016 (Oregon Supreme Court, 1965)
Hadeed v. Willamette Hi-Grade Concrete Co.
395 P.2d 553 (Oregon Supreme Court, 1964)
Beers v. CHAPMAN
370 P.2d 941 (Oregon Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
356 P.2d 547, 224 Or. 614, 1960 Ore. LEXIS 715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pruett-v-lininger-or-1960.