Providence Lloyds Insurance Co. v. Crystal City Independent School District

877 S.W.2d 872, 1994 Tex. App. LEXIS 1599, 1994 WL 248438
CourtCourt of Appeals of Texas
DecidedJune 8, 1994
Docket04-93-00483-CV
StatusPublished
Cited by32 cases

This text of 877 S.W.2d 872 (Providence Lloyds Insurance Co. v. Crystal City Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Providence Lloyds Insurance Co. v. Crystal City Independent School District, 877 S.W.2d 872, 1994 Tex. App. LEXIS 1599, 1994 WL 248438 (Tex. Ct. App. 1994).

Opinion

BUTTS, Justice.

Providence Lloyds Insurance Company (Providence), insurer, appeals a judgment granted in favor of Crystal City Independent School District (the District), insured, following a jury trial regarding the disputed cash values and loss after a fire. The trial court awarded the District $222,199 which is the difference between the $1,237,000 jury verdict and a $1,014,801 sum previously paid by Providence.

In eight points of error, Providence argues that (1) the trial court erred by not enforcing the appraisal process and by permitting this case to be tried, and (2) various errors occurred during the trial regarding pleading and evidence, as well as the jury charge. By cross point, the District argues that it is entitled to attorney fees. We reverse and render.

The essential facts surrounding this controversy are undisputed. Following a February 9, 1992 fire at the Benito Juarez Elementary School, Providence and the District disagreed as to cash values of the loss. The District filed a lawsuit in March 1992, alleging both (1) bad faith by Providence regarding handling of the claim and (2) breach of the insurance contract and the resulting claim for damages. The trial court severed the bad faith cause of action. This appeal is from the judgment on the breach of contract cause of action.

By agreement of the parties, the trial court abated the suit for the parties to participate in the insurance policy appraisal process. Providence and the District had failed to agree on the cash values of the loss. After abatement, they engaged in the required ap *874 praisal process with an umpire pursuant to the following insurance policy clause:

Appraisal. In case the Insured and this Company shall fad to agree as to the actual cash value of the amount of loss, then, on the written demand of either, each shall select a competent and disinterested appraiser and notify the other of the appraiser selected within twenty days of such demand. The appraisers shall first select a competent and disinterested umpire; and failing for fifteen days to agree upon such umpire, then, on request of the Insured or this Company, such umpire shall be selected by a judge of a district court of a judicial district where the loss occurred. The appraisers shall then appraise the loss, stating separately actual cash value and loss to each item; and, failing to agree, shall submit their differences only to the umpire. An award in writing, so itemized, of any two when filed with this Company shall determine the amount of actual cash value and loss. Each appraiser shall be paid by the party selecting him and the expenses of appraisal and umpire shall be paid by the parties.

(emphasis added).

The District selected Joe Lopez as its appraiser; Providence selected Preston Harvey. The trial court appointed George Ozu-na as the umpire, after the parties disagreed about the umpire choice.

Harvey (for Providence) initially determined the school could be restored for $851,-149.98; Lopez (for the District) estimated repairs at $1,747,640.00. The record shows that of the forty-eight items in dispute, Harvey and Lopez then resolved their differences and agreed on the following twenty-six items:

1. supervision $24,000.00
2. project manager & travel 20,000.00
3. portable commode 600.00
4. office trailer 2,000.00
5. dumpster rental & debris removal 10,000.00
6. crane rental 2,000.00
7. clean & seal for smoke odor 21,202.04
8. clean & treat concrete slab for odor 1,500.00
9. glass, windows & doors 4,500.00
10. suspended ceiling with insulation 35,250.00
11. laminated cabinets 23,397.75
12. remove & replace bath accessories & toilet partitions 20,247.01
13. chalk & tack boards 9,100.00
14. structural steel 37,175.00
15. clock system 2,995.00
16. a/c heat energy control (Honeywell) 2,990.00
17. remove & replace wall a/e & heating unit in Room 17 966.00
18. general cleaning during and after construction 6,133.00
19. remove & replace wood window frames 0.00
20. plywood walls 1,191.80
21. mariyte wall in bath 268.00
22. repair concrete columns 150.00
23. remove & reset metal stairway and gate and burglar bars 1,540.00
24. remove & replace molding and trim 4,493.50
25. 6" construction fence and gate 2,475.00
26. permits 2,500.00
$236,674.10

Ozuna then reviewed the twenty-two 2 remaining items, those upon which the appraisers were unable to agree, and assigned values to them, as follows:

*875 1. builders risk 0.00
2. power & telephone 0.00
3. project secretary 0.00
4. demolition of acoustic tile, ceiling, metal grid, insulation, walls, roof and carpet 47,500.00
5. masonry 28,000.00
6. metal stud walls, sheetrock, wall insulation, int. & ext. gyp board 39,901.00
7. doors & frames 16,620.00
8. hardware 5,965.41
9. plaster exterior 16,950.00
10. carpet, vinyl & base 60,000.00
11. painting & vinyl walls 41,783.00
12. remove & replace 4-ply built-up roof, roof insulation & sheetmetal 111,000.00
13. lockers 0.00
14. plumbing 40,000.00
15. fire alarm system 14,405.00
16. intercom 7,560.00
17. electric with switch gear and light fixtures 93,380.00
18. HVAC 100,164.00
19. clean metal ducts 0.00
20. performance bond 21,278.75
21. labor 0.00
22. labor (subs) 0.00
$644,507.16

Ozuna then added $132,365.38 as one lump sum which included overhead, insurance and profit, previously separated items.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Security Fire & Casualty Co. v. Hurst
523 S.W.3d 840 (Court of Appeals of Texas, 2017)
Candelaria Garcia v. State Farm Lloyds and Sylvia Garza
514 S.W.3d 257 (Court of Appeals of Texas, 2016)
Rosa Ena Cantu v. Southern Insurance Company
Court of Appeals of Texas, 2015
United Neurology, P.A. v. Hartford Lloyd's Insurance
101 F. Supp. 3d 584 (S.D. Texas, 2015)
TMM Investments, Limited v. Ohio Casualty Insuranc
730 F.3d 466 (Fifth Circuit, 2013)
State Farm Lloyds v. Johnson
290 S.W.3d 886 (Texas Supreme Court, 2009)
Franco v. Slavonic Mutual Fire Insurance Ass'n
154 S.W.3d 777 (Court of Appeals of Texas, 2004)
Jerry & Elva Breshears v. State Farm Lloyds
Court of Appeals of Texas, 2004
Breshears v. State Farm Lloyds
155 S.W.3d 340 (Court of Appeals of Texas, 2004)
Allison v. Fire Insurance Exchange
98 S.W.3d 227 (Court of Appeals of Texas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
877 S.W.2d 872, 1994 Tex. App. LEXIS 1599, 1994 WL 248438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/providence-lloyds-insurance-co-v-crystal-city-independent-school-district-texapp-1994.