Protect the Historic Amador Waterways v. Amador Water Agency

11 Cal. Rptr. 3d 104, 116 Cal. App. 4th 1099
CourtCalifornia Court of Appeal
DecidedApril 9, 2004
DocketC042915
StatusPublished
Cited by57 cases

This text of 11 Cal. Rptr. 3d 104 (Protect the Historic Amador Waterways v. Amador Water Agency) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Protect the Historic Amador Waterways v. Amador Water Agency, 11 Cal. Rptr. 3d 104, 116 Cal. App. 4th 1099 (Cal. Ct. App. 2004).

Opinion

Opinion

ROBIE, J.

In this mandamus case, plaintiff Protect the Historic Amador Waterways challenged the environmental impact report (EIR) defendant Amador Water Agency (Agency) certified for a project that would replace the 130-year-old Amador Canal with a pipeline. The Agency acknowledges that “leakage from the Amador Canal contributes to the surface flow of water in local streams” and that putting the water from the canal into a pipe will reduce the summer flows in those streams, including a significant reduction in the south fork of Jackson Creek. Nonetheless, the Agency concluded in its EIR that this reduction in stream flow would not constitute a significant effect on the environment within the meaning of the California Environmental Quality Act (CEQA; Pub. Resources Code, 1 § 21000 et seq.) The superior court denied plaintiff’s petition, finding the Agency had complied with CEQA and its conclusion was supported by substantial evidence.

*1103 On appeal, plaintiff contends the Agency “abused its discretion when it concluded that modifying the hydrology of local creeks from perennial to intermittent surface flows (i.e., drying local streams during the late summer and early fall) due to the dewatering of Amador Canal was not a significant adverse physical change to the existing environmental conditions . . . .” According to plaintiff, the Agency “inappropriately used irrelevant thresholds of significance to avoid a meaningful, fair, and reasonable evaluation of the substantial evidence demonstrating significant adverse environmental changes in local stream hydrology.”

We conclude the Agency abused its discretion because the EIR does not contain a required statement indicating the reasons why the Agency determined that the reduction in the surface flow of local streams would not be significant. Accordingly, we will reverse the superior court’s judgment denying plaintiff’s petition for a writ of mandate and remand the matter for further proceedings.

FACTUAL AND PROCEDURAL BACKGROUND

Originally constructed in 1870, the Amador Canal is a mostly unlined earthen ditch that transports water along the natural contours of the land approximately 23 miles from Lake Tabeaud to the Tanner Reservoir. The Agency, which owns the canal, wants to replace it with a pipeline that would run approximately eight miles in a more direct line between the lake and the reservoir. The objectives of the pipeline project include improving water quality, reducing water loss, and improving reliability of the water supply.

Having determined in an initial study that the project would have potentially significant impacts on several environmental factors, the Agency prepared a draft EIR for the project in September 2000.

The “Environmental Analysis” section of the draft EIR addressed the areas in which the project would have potentially significant environmental effects, including water resources and biological resources. The hydrology portion of the water resources section of the EIR discussed the results of a detailed hydrological analysis that was performed at the Agency’s request to determine if leakage from the mostly unlined canal was contributing to the surface flow of local streams. Based on data from field studies in 1998, the Agency determined that the surface flow in parts of six local streams was increased in varying degrees by leakage from the canal, particularly in the summer and early fall (June through October). The Agency further determined that canal leakage was probably keeping the affected parts of some of these streams from becoming intermittent during drier years.

The Agency acknowledged in the EIR that the pipeline project would eliminate all leakage from the Amador Canal and that, as a result, “no *1104 contribution to local surface discharges would occur” and “the flows in local streams now influenced by canal leakage and runoff capture would return to their historical hydrological conditions,” i.e., the conditions that existed before the canal was built. The Agency predicted that the south fork of Jackson Creek and some of its tributaries would become intermittent “during August and September, and possibly October, in all but the wettest water-years” if the pipeline were constructed. The Agency similarly predicted intermittent flow in the middle fork of Jackson Creek, New York Ranch Gulch, Cooper’s Gulch (already “intermittent or nearly so by the fall of most years”), and Oneida Creek (“barely perennial under current conditions”) as a result of the pipeline.

Having identified the pipeline’s likely impact on the surface flow of these streams, the EIR addressed the significance of that impact as follows: “The change in local hydrology associated with dewatering the Amador Canal and eliminating all leakage is not considered to be a significant hydrological impact per se. The hydrological changes may have effects on other resources dependent on hydrology, for example, water quality or wildlife, and these effects are discussed elsewhere in the [EIR], Consequently, changes in hydrology are not significant. The impact of the Pipeline Alternative on hydrology is determined to be less than significant.”

The EIR went on to address the potential effects of the pipeline on various biological resources, including wetland and riparian habitats in the project area. The EIR explained that the montane riparian habitat “occurs along seasonal and perennial streams in the project area,” including the south fork of Jackson Creek and New York Ranch Gulch. The EIR discussed in several paragraphs the potential impact of the pipeline on various areas of wetland habitat created or supplemented by leakage from the canal. After noting the pipeline’s impact on this wetland habitat would be “less than significant,” the EIR addressed the impact of the pipeline on riparian habitat in a single sentence, as follows: “Similarly, the montane riparian vegetation would continue to thrive along local streamcourses, even if canal leakage is eliminated.” The EIR then drew the following conclusion regarding the effect of the pipeline on “the wildlife habitats and the associated wildlife communities of the project area”: “While the dewatering of the Amador Canal, attributed to the Pipeline Alternative, would change local hydrological conditions along the Amador Canal and in associated watersheds by eliminating leakage and restoring natural runoff, the interaction of these changes are not expected to significantly affect local wildlife communities or their distribution in the project area. It is determined that the effect of eliminating leakage on wildlife resources is less than significant.”

*1105 After circulating the draft EIR for public review and comment, the Agency prepared a final EIR and in May 2001 adopted a resolution certifying the EIR and approving the project. The final EIR did not contain any relevant revisions to the sections of the draft EIR discussed above. 2

In June 2001, plaintiff filed a petition for a writ of mandate in the superior court asserting, among other things, that the EIR failed to comply with the mandatory requirements of CEQA in various particulars.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russian Riverkeeper v. City of Ukiah CA1/3
California Court of Appeal, 2024
Yolo Land and Water Defense v. County of Yolo
California Court of Appeal, 2024
V Lions Farming, LLC v. County of Kern
California Court of Appeal, 2024
Novaresi v. County of Placer CA3
California Court of Appeal, 2020
South of Mkt. Cmty. Action Network v. City and County of San Francisco
245 Cal. Rptr. 3d 174 (California Court of Appeals, 5th District, 2019)
Jensen v. City of Santa Rosa
California Court of Appeal, 2018

Cite This Page — Counsel Stack

Bluebook (online)
11 Cal. Rptr. 3d 104, 116 Cal. App. 4th 1099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/protect-the-historic-amador-waterways-v-amador-water-agency-calctapp-2004.