Prote Contracting Co. v. Board of Education

171 A.D.2d 621, 567 N.Y.S.2d 687, 1991 N.Y. App. Div. LEXIS 3965
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 28, 1991
StatusPublished
Cited by1 cases

This text of 171 A.D.2d 621 (Prote Contracting Co. v. Board of Education) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prote Contracting Co. v. Board of Education, 171 A.D.2d 621, 567 N.Y.S.2d 687, 1991 N.Y. App. Div. LEXIS 3965 (N.Y. Ct. App. 1991).

Opinion

Order, Supreme Court, New York County (Leonard N. Cohen, J.), entered November 22, 1989, denying plaintiff’s motion for partial summary judgment on its second cause of action, while granting defendant’s cross-motion for summary judgment dismissing that cause of action, is affirmed, without costs or disbursements.

Education Law § 3813 (1) requires presentation of a claim against a school board or district "within three months after the accrual of such claim”. Plaintiff concededly let sixteen months pass before filing a notice of claim for unpaid extra work performed under a change order approved by defendant.

[622]*622While plaintiff contends its claim for extra work never accrued because it was never rejected, the claim for extra work accrued upon completion of the work. (See, Matter of Board of Educ. [Wager Constr. Corp.J, 37 NY2d 283, 291.) The failure of plaintiff to present its claim within the statutory time limitations was a "fatal defect” (Parochial Bus Sys. v Board of Educ., 60 NY2d 539, 547). Concur — Milonas, J. P., Asch and Smith, JJ.

Wallach and Kassal, JJ., dissent in a memorandum by Kassal, J., as follows: The $89,056 at issue in this appeal represents a sum approved by defendant for work performed by plaintiff pursuant to defendant’s authorization. Because of the cumbersome and time-consuming municipal payment process, with which those in the construction industry are well familiar, plaintiff did not file a notice of claim within 90 days of the submission of its requisition for payment. Rather, in reliance upon defendant’s approval of both the extra work required to complete the project and the payment requisition therefor, plaintiff waited approximately 16 months before resorting to litigation in order to obtain compensation, and now finds itself time-barred. I cannot agree that the applicable statute and the body of case law developed in this area were intended to permit this result, and must respectfully dissent.

Education Law § 3813 (1) provides that no action may be brought against the Board of Education unless a "written verified claim” was filed "within three months after the accrual of [the] claim”. The purpose of this section is "to give a school district prompt notice of claims 'so that investigation may be made before it is too late for investigation to be efficient’ ” (Matter of Board of Educ. [Wager Constr. Corp.], 37 NY2d 283, 289). The Wager Court held that the claims of contractors accrue, "when their damages accrued (as distinguished from the event which incurs them), that is, when their damages were ascertainable” (37 NY2d, supra, at 290).

Much attention to the critical date on which a claim accrues has understandably been given in subsequent court rulings in this area. (See, e.g., F & G Heating Co. v Board of Educ., 103 AD2d 791, 793; Castagna & Son v Board of Educ., 151 AD2d 392, 392-393.) The case at bar, however, requires a shift of focus to what, exactly, is contemplated by the use of the word "claim” in this context. Does the mere submission of a bill, in an amount approved and for work authorized, constitute a "claim” for the purposes of Education Law § 3813 (1)? Wager (supra, at 290) advances the need for prompt and efficient investigation of claims, and refers to the accrual of "dam[623]*623ages”. Surely this language, with its portent of litigation, does not contemplate the undisputed, pre-approved billing amount of a contractor who has in good faith fully performed under a contract with the Board of Education and now seeks rightful compensation. It has been held that a claim against a municipality accrues when it refuses to make payment. (Matter of City of White Plains v City of New York, 63 AD2d 396, 403, Iv denied 46 NY2d 707; see also, Leith Constr. Co. v Board of Educ., 75 AD2d 615 [a claim does not accrue until defendant informs plaintiff of the amount it intends to pay].)

To interpret Education Law § 3813 (1) in the manner approved by the majority is to require a contractor to automatically follow its payment requisition, within 90 days, with a notice of claim — thereby entailing unnecessary legal expenses and triggering whatever mechanisms go into effect when the City receives notice of impending litigation — despite the well-known fact that municipal bills are rarely, if ever, paid within three months.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bri-Den Construction Co. v. Board of Education
200 A.D.2d 605 (Appellate Division of the Supreme Court of New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
171 A.D.2d 621, 567 N.Y.S.2d 687, 1991 N.Y. App. Div. LEXIS 3965, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prote-contracting-co-v-board-of-education-nyappdiv-1991.