PROMAC, INC., Appellant, v. Togo D. WEST, Jr., Secretary of Veterans Affairs, Appellee

203 F.3d 786, 2000 U.S. App. LEXIS 1676, 2000 WL 137076
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 8, 2000
Docket99-1075
StatusUnpublished
Cited by12 cases

This text of 203 F.3d 786 (PROMAC, INC., Appellant, v. Togo D. WEST, Jr., Secretary of Veterans Affairs, Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PROMAC, INC., Appellant, v. Togo D. WEST, Jr., Secretary of Veterans Affairs, Appellee, 203 F.3d 786, 2000 U.S. App. LEXIS 1676, 2000 WL 137076 (Fed. Cir. 2000).

Opinion

PLAGER, Circuit Judge.

Promac, Inc. (“Promac”) was the lowest bidder for a contract with the Department of Veterans Affairs to construct a new medical research building. When performance was almost complete, Promac filed a claim for reformation of its contract based upon alleged violations of the Federal Acquisition Regulations by the Government in the bidding process. The Contracting Officer (“CO”) denied Promac’s claims. The Department of Veterans Affairs Board of Contract Appeals (“DVAB-CA” or “Board”) upheld the CO’s decision. See Promac, Inc. v. VA Med. Ctr., 1998 WL 780537, VABCA No. 5345 (VABCA Oct. 27, 1998). Because the Board did not err, we affirm.

BACKGROUND

In June of 1995, the Department of Veterans Affairs (“VA” or “Government”) issued an Invitation for Bids (“IFB”) for the construction of a 13,000 square foot research building at the VA’s Medical Center in Providence, Rhode Island. Although the VA’s Architect Engineering firm (“A/ E”) made a final estimate for the project *787 of $3,075,000 with deductive alternates totaling $307,000, the IFB stated the cost of the project to be between $2 and $5 million. At the time the IFB was issued, the Medical Center in Providence had only received approval to spend $2,648,000 on the construction project.

The VA opened bidding on August 1, 1995. Seven firms returned bids ranging from $3,119,000 to $3,354,700. After bids were received, the A/E wrote to the CO that Promac’s bid was within 1% of the final cost estimate and that it was the A/E’s opinion that the VA had received a valid and fair low bid. According to Pro-mac, the Contracting Officer notified Pro-mac that it was the low bidder and that there was a funding problem. The CO allegedly told Promac that the VA was attempting to secure sufficient funds to make an award to Promac.

The VA Medical Center in Providence requested an increase in its budget for the project. That request, however, was not granted. Under the applicable Federal Acquisition Regulations (“FAR”), the VA was required to initiate a new bidding round. FAR 14.404-1 provides that if an IFB is canceled because the bid prices received were unreasonable, an agency may proceed with procurement through negotiations with the original bidders. However, if the IFB was canceled for other reasons, then procurement should continue with a new acquisition. The VA’s staff architect devised a scheme to avoid the delays a rebid would add and also manage to lower the existing bid prices. In a letter to the CO, the staff architect suggested that instead of soliciting bids again, the VA should simply negotiate with the existing bidders in hopes of bringing the bids down. The CO adopted that scheme, writing a letter that stated that the IFB was canceled because “all bids received, although otherwise acceptable, are unreasonable in price.” Thus, even though the lowest bid was within 1% of the A/E’s final cost estimate, the IFB was canceled due to “unreasonable” bid prices and procurement was set to proceed through negotiations rather than a new acquisition.

Before beginning negotiations with the original bidders, the VA made some minor changes to the project. The VA notified the bidders of the changes and that the deductive items of the IFB were now to be included in the base bid. It then requested that the original bidders submit new offers.

After receiving the revisions to the project, Promac’s president received a telephone call from the CO. According to Pro-mac, the CO proceeded to violate FAR 15.610 by stating that Promac would have to offer a price of around $2.7 million to remain competitive in the procurement. FAR 15.610 provides that indicating to an offeror a price that it must meet to obtain further consideration is a prohibited auction technique. The CO denied that he ever suggested a target price. In calculating its new bid, Promac reduced its profit, overhead, and field supervision expenses so that its new price was $2,723,000. After all the new prices were submitted, which ranged between $2,723,000 and $2,900,000, it turned out that, once again, Promac was the lowest bidder.

The VA awarded the contract to Pro-mac, and Promac completed performance in May 1997. Before Promac had completed performance, it filed a claim seeking reformation of the contract, alleging that it was due the difference between its original bid and its final bid. Promac asserted that it had submitted a reasonably priced original bid and that the VA had violated the FAR by canceling the IFB and continuing the procurement through negotiations. Because it suffered damages as a result of the VA’s actions, Promac alleged it was entitled to reformation of its contract to the extent that its price had been affected by the VA’s violations. The CO issued a final decision denying the claim.

Promac appealed the denial to the DVABCA. Both Promac and the VA *788 moved for summary judgment. In its summary judgment motion, Promac for the first time asserted that the CO’s suggestion of a target price was another violation of the FAR and consequently an additional ground for recovery. The Board denied Promac’s motion and granted the VA’s motion for summary judgment that Promac was not entitled to reformation. Viewing the facts in the light most favorable to Promac, the non-movant, the Board concluded that the original bid prices were reasonable, and thus the VA violated FAR 14.404-1 when it continued procurement by negotiations rather than by a new acquisition.

Despite the violation, the Board concluded that Promac’s claim for reformation failed because FAR 14.404-1, specifically subpart (e), was not adopted for the benefit of a low bidder. Interpreting LaBarge Prods., Inc. v. West, 46 F.3d 1547 (Fed.Cir.1995), the Board reasoned that Promac had to meet two requirements in order for it to be entitled to reformation: 1) the violated regulation was adopted for the benefit of Promac, and 2) Promac was damaged by the violation of the regulation. Since FAR 14.404-l(e) benefited bidders that did not submit the low bid by giving them a second chance to bid through a new acquisition, the low bidder, in this case Promac, certainly was not able to meet the first prong of the test. Thus, it was not entitled to reformation due to the violation of FAR 14.401-1.

The Board similarly reasoned that Pro-mac was not the intended beneficiary of FAR 15.610. FAR 15.610 provides that indicating to an offeror a price that it must meet to obtain further consideration is a prohibited auction technique. Although it was disputed whether the CO did set a target price, the Board reasoned that even if he had, Promac was not the intended beneficiary of such a regulation. Instead, it was the bidders who had not been privy to the disclosed target price that were the intended beneficiaries. Thus, even assuming all of Promac’s allegations to be true, Promac could not meet the first prong of the test. Consequently, Promac was not entitled to reformation even if the VA had violated FAR 15.610.

In addition, the Board noted that throughout the procurement process, Pro-mac not only did not complain of the alleged violations, but actively participated in all of these alleged violations. Thus, Promac did not have the clean hands necessary to receive the equitable remedy of reformation.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ricky N. Dawson v. Department of Agriculture
2014 MSPB 67 (Merit Systems Protection Board, 2014)
Precision Pine & Timber, Inc. v. United States
75 Fed. Cl. 80 (Federal Claims, 2006)
Greene v. United States
Federal Circuit, 2006
Falconwood Corp. v. United States
60 Fed. Cl. 485 (Federal Claims, 2004)
Renfro v. Indiana Michigan Power Co.
233 F. Supp. 2d 1174 (W.D. Michigan, 2002)
Lees v. Evans
31 F. App'x 680 (Federal Circuit, 2002)
Lockheed Martin Corp. v. United States
49 Fed. Cl. 241 (Federal Claims, 2001)
Kitt v. United States
47 Fed. Cl. 821 (Federal Claims, 2000)
GPA-I, LP v. United States
46 Fed. Cl. 762 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
203 F.3d 786, 2000 U.S. App. LEXIS 1676, 2000 WL 137076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/promac-inc-appellant-v-togo-d-west-jr-secretary-of-veterans-cafc-2000.