Professional Engineering Services v. City of Red Boiling Springs, TN

CourtCourt of Appeals of Tennessee
DecidedApril 26, 2000
DocketM1999-00342-COA-R3-CV
StatusPublished

This text of Professional Engineering Services v. City of Red Boiling Springs, TN (Professional Engineering Services v. City of Red Boiling Springs, TN) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Engineering Services v. City of Red Boiling Springs, TN, (Tenn. Ct. App. 2000).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE

PROFESSIONAL ENGINEERING SERVICES, INC. v. CITY OF RED BOILING SPRINGS, TENNESSEE

Direct Appeal from the Chancery Court for Macon County No. 2557; The Honorable C. K. Smith, Judge

No. M1999-00342-COA-R3-CV - Decided April 26, 2000

This appeal involves a dispute over whether a contract to provide services was formed between defendant-city and plaintiff-engineers and if so, whether defendant-city breached the contract. The court below held that a contract was formed between the parties and granted plaintiff-engineers recovery under the contract. In the alternative, the trial court held that plaintiff-engineers would be entitled to recover in quantum meruit in the absence of a valid contract. Defendant-city appeals.

Tenn. R. App. P. 3; Appeal as of right; Judgment of the Chancery Court Reversed in Part and Affirmed in Part

HIGHERS , J., delivered the opinion of the court, in which CRAWFORD , P.J., W.S., and FARMER, J., joined.

Jacky O. Bellar, BELLAR & BELLAR, Carthage, Tennessee for Appellant

A. Russell Brown, Lafayette, Tennessee for Appellee

OPINION

City of Red Boiling Springs (“City”) appeals the trial court’s holding that City breached its contract with Professional Engineering Services (“PES”). City also appeals the trial court’s alternative holding that PES was entitled to recovery under quantum meruit. For the following reasons, the decision of the trial court is affirmed in part and reversed in part.

Facts and Procedural History This appeal arises from a suit filed by PES against City for breach of contract. PES alleged that City contracted with PES to do both preliminary preparations and design work for a new water treatment facility, and that City later breached that contract. In the alternative, if the contract was found unenforceable, PES sought recovery in quantum meruit. City claimed that no contract existed with PES because of PES’s failure to gain the required approval of the contract by the city attorney and city council. The trial court found in favor of PES, holding that City had contracted with PES and subsequently breached that contract. The court further found that in the event this court found no contract existed, that PES was entitled to recovery in quantum meruit. City appeals based on the following facts.

In March 1992, City received a letter from the Tennessee Department of Environment and Conservation (“TDEC”) indicating that surface water had contaminated the City water system. The City was instructed to hire an engineer to determine a feasible solution for the problem and to submit the engineer’s study within ninety days. In addition, the City was given an October 1, 1993, deadline for construction of a filtration treatment system or other redevelopment of the groundwater source. Failure to comply with the letter’s instructions would violate TDEC regulations and could result in fines.

The city council voted for local engineer Ronnie Reece (PES) to do the required study. 1 This was memorialized in an “Engineering Agreement” signed by Mayor Tommy Spivey, providing for PES to prepare the study, assist in application for grant or loan assistance, and if approved, to provide various other services and documents. The Engineering Agreement also specified PES’s compensation based upon the construction cost of the project. This agreement was signed on April 28, 1992. PES kept one copy of the contract in its files and delivered two copies of the contract to the City.

PES prepared the study as was requested, and forwarded it to the City for approval. The study included estimates for the construction of a water treatment plant, an engineering design fee, and an inspection fee, as well as a recommendation regarding funding. After approval by the City, PES sent the study to the TDEC. The TDEC approved PES’s study and recommendations on September 28, 1992.

At a city council meeting in October, PES reported the TDEC’s approval to the council and made funding recommendations which were approved by the City. The council voted for PES to proceed with the plans on the water filtration plant. PES did so, picking a site for the proposed facility, locating needed equipment, and performing other preparatory work.2 In addition, PES appeared before the city council each month to provide an update on the design status of the project.

In December 1992, the City approved PES’s proposal to apply for a loan from the Tennessee Association of Utility Districts (TAUD) for funding of the filtration plant. In January 1993, the City learned that its loan application had been approved. In April, the City authorized the Mayor to apply for an additional loan/grant. This loan/grant application contained a signed “Agreement For Engineering Services” providing that PES was to perform the engineering services for the project.

1 Ronnie Reece and Ricky White were partners in Professional Services Group Ltd, a company that was at that time working on another job for the City. The first agreement at issue was between Professional Services Group and the City. Professional Services Group was incorp orated as P rofessional E ngineering S ervices prio r to the second agreement at issue in this lawsuit. For the sake of clarity, the party will be referred to as PES throughout this opinion.

2 During this period, Ricky White took over the primary functions of the job, acting as design engineer and overseeing the drafting and writing of the pro ject specifications.

-2- In June, the City decided to apply for a Community Development Block Grant (CDBG) for additional funding. As required by the CDBG, the City advertised for an engineer and administrator for the project. PES prepared and submitted the CDBG application for the City. In July 1993, the council discussed the hiring of engineers for the project. At this time, it was noted that PES had a contract authorizing it to proceed with the design of the project. The council also discussed a bill for $46,088.92 that it had received from PES. The council passed a motion to hire PES as engineer for the city CDBG water filtration project.

In August 1993, the council discussed payment of PES’s invoice and the validity of the contract between the City and PES. The council voted that the contract was not valid and advised PES to work with the City attorney to prepare a new contract and proceed with the project.

In October 1993, the City passed a resolution requiring PES to produce a preliminary engineering report for the project. The resolution stated that pending approval of the CDBG, PES would be engaged to design plans, inspect construction, and perform other required project services. Later that month, the CDBG grant was approved.

In November 1993, the council hired Water Management Services to study the feasibility of alternatives to the construction of a new water treatment facility. In April 1994, PES explained the difference between the conventional water treatment plant and a pressure filter plant. A motion was made and passed by the council to have a conventional water treatment plant installed. On May 12, 1994, the council voted to employ Water Management Services as engineers to install a water pressure filter system. The new water treatment plant was built on the site previously chosen by PES.

On August 3, 1994, PES filed suit against the City for breach of contract. PES alleged that both the Engineering Agreement of April 1992 and the Agreement for Engineering Services of April 1993 were contracts for PES’s services. In addition, PES alleged that it was never paid for its work and that it was not allowed to complete the project. According to PES, the designs were eighty-five percent complete at the time the City breached the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnes v. Ingram
397 S.W.2d 821 (Tennessee Supreme Court, 1965)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
City of Lebanon v. Baird
756 S.W.2d 236 (Tennessee Supreme Court, 1988)
Barnes v. City of Dayton
392 S.W.2d 813 (Tennessee Supreme Court, 1965)
Crocker v. Town of Manchester
156 S.W.2d 383 (Tennessee Supreme Court, 1941)
Rutherford v. City of Nashville
79 S.W.2d 581 (Tennessee Supreme Court, 1935)
City of Chattanooga v. Tennessee Electric Power, Co.
112 S.W.2d 385 (Tennessee Supreme Court, 1938)
Kemmons Wilson, Inc. v. Allied Bank of Texas
836 S.W.2d 104 (Court of Appeals of Tennessee, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Professional Engineering Services v. City of Red Boiling Springs, TN, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-engineering-services-v-city-of-red-bo-tennctapp-2000.