Process Gas Consumers Group v. Federal Energy Regulatory Commission

177 F.3d 995, 336 U.S. App. D.C. 162, 1999 U.S. App. LEXIS 9770, 1999 WL 317037
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 21, 1999
DocketNos. 98-1075, 98-1089
StatusPublished
Cited by4 cases

This text of 177 F.3d 995 (Process Gas Consumers Group v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Process Gas Consumers Group v. Federal Energy Regulatory Commission, 177 F.3d 995, 336 U.S. App. D.C. 162, 1999 U.S. App. LEXIS 9770, 1999 WL 317037 (D.C. Cir. 1999).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

Tennessee Gas Pipeline Company (“Tennessee”) filed a tariff revision with the Federal Energy Regulatory Commission (“FERC” or “Commission”) in 1996. The company sought to change the method it uses to allocate requests for available capacity on its natural gas pipeline, switching from “first come-first served” to “net present value,” or “NPV.” Over objections, FERC ultimately approved a twenty-year cap on bids evaluated under NPV. It also approved the use of NPV to evaluate requests from shippers to change the primary points at which their gas enters or leaves the pipeline. Numerous petitioners argue that FERC failed to engage in reasoned decision making in both instances in violation of the Administrative Procedure Act (“APA”). Petitioners also contend that Tennessee did not give sufficient notice that NPV would apply to point change requests. We agree with both of petitioners’ APA claims and therefore grant the petitions for review, remanding the issues to FERC, but hold that petitioners lack standing to raise the notice claim.

I. Background

Tennessee transports natural gas via a pipeline system from Louisiana, Texas, and the Gulf of Mexico to areas as far north as New England. Prior to the orders at issue in this case, Tennessee awarded available firm capacity1 on the pipeline on a first come-first served basis; the first shipper to submit a request that satisfied the requirements of Tennessee’s tariff received the capacity. The pipeline found that method unsatisfactory:

Under the first come-first served policy, Tennessee must- award capacity to any shipper, even one that requests service for a very short term (which could be for as little as just a few days), if the short-term shipper satisfactorily submits its request for service as little as one hour before a long term shipper submits its request for service. Plainly, an efficient market would not function in this way, as a merchant exercising rational business judgment would typically favor a creditworthy long-term customer (even if the long-term customer requested a reasonable discount) that ... would provide more overall benefits than those provided by the short-term customer. Similar inefficiencies arise where a short-haul shipper submits its request for service prior to another shipper that wishes to transport gas to points further downstream or upstream.

Letter from Marguerite N. Woung, Attorney, Tennessee Gas Pipeline Company, to Lois D. Cashell, Secretary, FERC 3 (June 12, 1996). Pursuant to section four of the Natural Gas Act, 15 U.S.C. § 717c, Tennessee therefore submitted tariff revisions to FERC on June 12, 1996, proposing a change from the first come-first served method of evaluating capacity requests to the NPV method.2 The change would be [998]*998accomplished through the addition to Tennessee’s tariff of a new section five, entitled “Awards of Generally Available Capacity.” Under NPV, Tennessee would announce an open season each time it wanted to sell available capacity. The highest bidder during the open season, based on the net present value of the bid, would receive the capacity (absent unusual circumstances). This approach would take into account differences in the proposals such as price, volume of gas, and duration of contract. Using more technical language, Tennessee described the NPV of a bid as the “discounted cash flow of incremental revenues per dekatherm to Transporter produced, lost or affected.... ”

A. The Twenty-Year Cap

Tennessee’s initial proposal did not include or discuss a cap on the length of a bid that would be considered in NPV calculations. A cap may prevent an end run around the maximum rates approved by FERC, a concern when monopoly conditions are present. See United Distribution Cos. v. FERC, 88 F.3d 1105, 1140 (D.C.Cir.1996) (“UDC”) (“Competing bidders who come up against the rate ceiling for this scarce resource — capacity on constrained pipelines — may bid up the length of the contract term to try to win the auction. In effect, bidding for a longer contract term becomes a surrogate for bidding beyond the maximum rate level.”). A cap functions like this: under a ten year cap, two shippers who want to submit otherwise identical fifteen and twelve year bids cannot; they are limited to ten year bids, producing the same NPV, and a tiebreaker determines the winner.3 Without the cap, the fifteen year bidder wins. The goal of a cap in a' monopoly situation, just as with the setting of maximum rates, is to simulate the end product of a competitive market. See Stephen G. Breyer & Richard B. Stewart, Administrative Law and Regulatory Policy 237 (3d ed.1992) (“In principle, ratemaking might be thought to have as its object the setting of prices equal to those that the firm would set if it did not have monopoly power; i.e., to replicate a ‘competitive price.’ ”). Bids in a competitive market limited in duration to ten years thus help to prevent a pipeline’s market power from causing market distortions.

A month after its June 12 filing, Tennessee addressed concerns raised by Process Gas Consumers Group (“Process Gas”), an association of industrial users of natural gas and one of the petitioners here, about the lack of a cap. Instead of incorporating a cap in the tariff itself, however, Tennessee stated that it would “include a cap on the duration of any bid as part of the open season posting ... that is applicable to the particular service being offered.” Response of Tennessee Gas Pipeline Company to Protests to NPV Filing at 6.

FERC ruled on Tennessee’s proposed revisions on July 31, 1996, generally approving of the switch from first come-first served to NPV:

A net present value evaluation ... allocates capacity to the shipper who will produce the greatest revenue and the least unsubscribed capacity. As such, it is an economically efficient way of allocating capacity and is consistent with Commission policy.

Tennessee Gas Pipeline Company, 76 F.E.R.C. ¶ 61,101, at 61,522 (1996) (“Tennessee Gas 7”). FERC was not wholly satisfied, however, and while it accepted the filing (with a minimal suspension period), it did so subject to certain conditions. One condition involved the cap: “Tennessee should explain why it proposes to vary the cap on a transaction by transaction basis rather than include a uniform cap in its tariff.” Id. at 61,519. In response, Tennessee proposed a twenty-year cap: “Since bids beyond the 20th year are un[999]*999likely to have a significant impact on the NPV analysis, Tennessee is willing to include in its tariff a 20-year limitation on the NPV bids.” Letter from Marguerite N. Woung, Attorney, Tennessee Gas Pipeline Company, to Lois D. Cashell, Secretary, FERC 6 (Aug. 15,1996).

During the same time period, a cap had become an issue in a different circumstance arising out of FERC’s Order No. 636, part of the restructuring of the natural gas industry. In our review of Order No. 636, we addressed a twenty-year cap selected by FERC in the right-of-first-refusal context.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
177 F.3d 995, 336 U.S. App. D.C. 162, 1999 U.S. App. LEXIS 9770, 1999 WL 317037, Counsel Stack Legal Research, https://law.counselstack.com/opinion/process-gas-consumers-group-v-federal-energy-regulatory-commission-cadc-1999.