Process Gas Consumers Group v. Federal Energy Regulatory Commission

912 F.2d 511, 286 U.S. App. D.C. 111
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 24, 1990
DocketNo. 87-1620
StatusPublished
Cited by1 cases

This text of 912 F.2d 511 (Process Gas Consumers Group v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Process Gas Consumers Group v. Federal Energy Regulatory Commission, 912 F.2d 511, 286 U.S. App. D.C. 111 (D.C. Cir. 1990).

Opinion

PER CURIAM:

I. Introduction

Petitioners, Process Gas Consumers Group, Nabisco Brands, Inc. and National Gypsum Company (collectively “PGC”), move pursuant to Fed.R.App.P. 42(b) to dismiss voluntarily their petition for review. SCM Corporation (“SCM”), which did not participate in the proceedings before respondent, the Federal Energy Regulatory Commission (“FERC”), but was granted intervenor status by this court, does not object to PGC’s withdrawal, but instead seeks to continue prosecuting the petition itself.

Because SCM did not participate in the proceedings before FERC, petition for rehearing before FERC on the issues it seeks to press before this court, or file a petition for judicial review within the time period prescribed by § 19 of the Natural Gas Act (“the Act”), 15 U.S.C. § 717r, it is jurisdictionally barred from obtaining judicial review of FERC’s decision. Therefore, SCM cannot assume the role of petitioner and continue suit after PGC withdraws, and we grant PGC’s motion to dismiss.

II. Background

PGC filed the instant petition for review on October 23, 1987. In their petition, PGC challenged FERC’s approval of a 1985 contested settlement (“1985 Settlement”) of numerous rate proceedings involving Columbia Gas Transmission Corporation (“Columbia”). SCM did not participate in the FERC proceedings underlying the 1985 Settlement. By Clerk’s Order filed July 14, 1989, this court nevertheless granted the motion of SCM and several others to intervene.

After oral argument on May 1, 1989, PGC entered into settlement negotiations with Columbia. On June 29, 1989, Colum[113]*113bia filed an offer of Settlement (“1989 Settlement”) with FERC which encompassed the instant proceeding and others pending before FERC and other courts. SCM was not a party either to the negotiations or the 1989 Settlement.

Under the 1989 Settlement, PGC agreed to seek voluntary dismissal of this petition. On July 7, 1989, PGC moved to hold the instant proceedings in abeyance pending FERC’s approval of the 1989 Settlement. On August 9, 1989, despite SCM’s opposition, this court granted that motion.

On October 19, 1989, FERC approved the 1989 Settlement with certain modifications. The modifications were accepted, and the 1989 Settlement was placed into effect as of November 1, 1989. The 1989 Settlement became “final” on June 20, 1990.

In accordance with the terms of the 1989 Settlement, PGC has now moved for voluntary dismissal of their petition for review. In support, PGC asserts:

[t]he 1989 Settlement resolves PGC’s dispute in this case. In addition, that settlement resolves over 30 Commission dockets and more than 20 other court cases. It provides significant rate relief and rate design improvements for all consumers. It also provides for new pipeline facilities and services which are vital to many parties. The Commission found the 1989 Settlement to be in the public interest and to produce just and reasonable rates.

See Motion for Voluntary Dismissal of Appeal With Prejudice (“Motion for Voluntary Dismissal”) at 3.

SCM, however, opposes the motion to dismiss. While conceding that “it may be appropriate to permit PGC to withdraw as a party to this case,” see Answer of SCM Corporation in Opposition to Motion to Dismiss Appeal (“SCM Opposition”) at 4, SCM argues that it should be permitted to continue suit. In support of its position, SCM relies on United States v. Western Electric Co., 900 F.2d 283, 310 (D.C.Cir.1990), which, SCM suggests, recognized “an intervenor’s right to continue suit in the absence of the party on whose side intervention was permitted.” SCM further contends that the right to continue suit is contingent only upon a showing that the intervenor satisfies Article III requirements of “an injury in fact fairly traceable to the conduct it is challenging and likely to be redressed by the relief it has requested.”

The issue thus presented is whether, under the Act, an intervenor who did not participate in proceedings before FERC may continue suit and obtain review of a FERC order after the original petitioner withdraws.

III. Analysis

SCM’s argument is based on the premise that by obtaining intervenor status, SCM may assume the role of petitioner and obtain judicial review. This premise, however, is incompatible with the statutory scheme of the Act which establishes strict jurisdictional prerequisites for review of FERC orders. Section 19 of the Act provides:

(a) Any person ... aggrieved by an order issued by the Commission ... may apply for a rehearing____ The application for rehearing shall set forth specifically the ground or grounds upon which such application is based____ No proceeding to review any order of the Commission shall be brought by any person unless such person shall have made application to the Commission for a rehearing thereon____
(b) Any party to a proceeding ... aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the court of appeals ... by filing in such court, within sixty days after the order of the Commission upon the application for rehearing, a written petition praying that the order of the Commission be modified or set aside in whole or in part____ Upon the filing of such petition such court shall have jurisdiction ... to affirm, modify, or set aside such order in whole or in part. No objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the [114]*114application for rehearing unless there is reasonable ground for failure to do so.

15 U.S.C. § 717r.

The plain language of the Act suggests that three prerequisites must be satisfied in order to obtain judicial review of a FERC order. First, a litigant seeking review must have participated in the proceedings before the agency. See Goodman v. Public Service Comm’n of the District of Columbia, 497 F.2d 661, 664 n. 5 (D.C.Cir.1974) (judicial review under the Natural Gas Act is limited “to those who were parties to the agency proceeding”). Next, the party seeking review must raise its objections in its own application for rehearing to the Commission. See Columbia Gas Transmission Corp. v. FERC, 848 F.2d 250, 255 (D.C.Cir.1988) (citing Asarco, Inc. v. FERC, 777 F.2d 764, 773 (D.C.Cir.1985)). Thus, a court cannot “consider an objection not raised by petitioner but argued to FERC by another party to the same proceeding.” Columbia Gas Transmission Corp., 848 F.2d at 255.

Finally, the party must file within sixty days after the Commission’s disposition of the application for rehearing a petition for review “praying that the order of the Commission be modified or set aside in whole or in part.” 15 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
912 F.2d 511, 286 U.S. App. D.C. 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/process-gas-consumers-group-v-federal-energy-regulatory-commission-cadc-1990.