Pro-Steel Buildings, Inc. v. United States

810 F. Supp. 2d 1302, 108 A.F.T.R.2d (RIA) 5678, 2011 U.S. Dist. LEXIS 102565
CourtDistrict Court, N.D. Florida
DecidedMay 16, 2011
DocketCase 4:09cv512-RH/WCS
StatusPublished
Cited by1 cases

This text of 810 F. Supp. 2d 1302 (Pro-Steel Buildings, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pro-Steel Buildings, Inc. v. United States, 810 F. Supp. 2d 1302, 108 A.F.T.R.2d (RIA) 5678, 2011 U.S. Dist. LEXIS 102565 (N.D. Fla. 2011).

Opinion

ORDER AWARDING ATTORNEY’S FEES AND COSTS

ROBERT L. HINKLE, District Judge.

This interpleader action is before the court on the plaintiff stakeholder’s claim for attorney’s fees and costs. This order approves the claim and directs the clerk to disburse funds accordingly.

I

The plaintiff Pro-Steel Buildings, Inc. (“Pro-Steel”) owed $60,304.37 for construction work. Three parties — the government, B.M.C. Contractors, Inc. (“BMC”), and Big Metal Construction, Inc. (“Big Metal”) — claimed all or part of the funds. With court approval, Pro-Steel deposited the full amount of the debt into the court’s registry. See ECF No. 34 at 5 of 11.

The government’s claim to the funds was based on a tax levy against BMC. The *1304 government moved for partial summary judgment on the ground that, as between BMC and Big Metal, it was undisputed that at least $34,710.05 was owed to BMC, and that, based on the levy, the government was entitled to at least that amount. BMC and Big Metal did not dispute the government’s analysis and agreed that partial summary judgment should be entered. See ECF No. 36. By order docketed February 23, 2011, the partial-summary-judgment motion was granted and the clerk was directed to disburse $34,710.05 to the government.

The government, BMC, and Big Metal then entered a settlement agreement allocating $9,000 of the remaining funds to Big Metal — subject only to Pro-Steel’s claim for costs and attorney’s fees — and allocating the balance to the government. Pro-Steel objected on the ground that it was entitled to recover its costs and fees exceeded $9,000 and that it was entitled to recover the costs and fees from the entire fund — not just from the $9,000 allocated to Big Metal.

Under the controlling law of the circuit, Pro-Steel was entitled to recover its fees and costs only from funds not subject to the government’s tax lien. See Katsaris v. United States, 684 F.2d 758, 763 (11th Cir.1982). Pro-Steel did not challenge — and without forfeiting its status as a neutral and disinterested stakeholder could not have challenged — the other parties’ allocation of the remaining funds. On March 8, 2011, an order was entered (i) directing the clerk to disburse all but $9,000 in accordance with the settlement agreement, (ii) determining that Pro-Steel was entitled to recover its fees and costs from the remaining $9,000, and (iii) establishing procedures to determine the amount of recoverable fees and costs. See ECF No. 42 at 3 of 3. The $9,000 now has accrued interest of less than one dollar, but for convenience this order sometimes ignores the interest.

Pro-Steel now seeks the entire $9,000. See ECF No. 44. BMC and Big Metal filed objections, though only Big Metal has standing to object. See ECF No. 45.

II

Pro-Steel accurately notes that the objections were untimely. The March 8 order set Pro-Steel’s deadline for filing fee and cost materials as April 5, 2011. ECF No. 42 at 3 of 3. The order provided that Local Rule 54.1(E) would govern fee procedures from that point forward. Under that rule, Big Metal was required to file any objections to Pro-Steel’s fee claim within 14 days after service of Pro-Steel’s materials. Pro-Steel served and filed its materials on March 18. With three days added based on electronic service, the deadline for objections was April 4. The deadline for objecting to the cost claim was 10 days after service, so March 31. See N.D. Fla. Loc. R. 54.2(B). Big Metal filed its objections on April 14, well beyond the deadline. See ECF No. 46.

This would be a sufficient basis for overruling the objections. But the delay caused no apparent prejudice. And the objections are unfounded anyway. This order addresses the claim for fees and costs on the merits.

III

Pro-Steel claims $11,863.61 in attorney’s fees and $599.61 in taxable costs. Big Metal challenges the claim on four grounds. First, Big Metal says that filing an interpleader action was unnecessary because the Internal Revenue Code provides absolute immunity to a person who surrenders funds in response to a tax levy. Second, Big Metal says Pro-Steel should be allowed to recover from the $9,000 remain *1305 ing fund only a pro rata share of its fees, in effect allocating the other fees to the share of the fund recovered by the government. Third, Big Metal says Pro-Steel improperly filed the action in state court, causing increased fees when the government removed the action to federal court. And fourth, Big Metal says Pro-Steel unreasonably incurred fees obtaining a default that was later set aside. This order rejects each of the assertions.

A

Under both Florida and federal law, an interpleader plaintiff may recover its reasonable attorney’s fees and costs, so long as the plaintiff did not cause the conflicting claims, was disinterested, and acted in good faith. See, e.g., Katsaris v. United States, 684 F.2d 758, 763 (11th Cir.1982); Perkins State Bank v. Connolly, 632 F.2d 1306, 1311 (5th Cir.1980). The issue is essentially equitable: a stakeholder who merely wishes to avoid liability for an erroneous choice between conflicting claims ordinarily should be made whole. See, e.g., Sun Life Assurance Co. of Can. v. Sampson, 556 F.3d 6, 8 (1st Cir.2009) (quoting 7 Wright, Miller & Kane, Federal Practice & Procedure § 1719, at 675 (3d ed. 2001)); In re Mandalay Shores Coop. Hous. Ass’n, 21 F.3d 380, 383 (11th Cir.1994).

Big Metal argues that because the Internal Revenue Code would have protected Pro-Steel from any liability for turning over the funds to the government, the interpleader action was unnecessary. A person ordinarily must turn over funds in response to a federal tax levy and risks both personal liability and a 50% penalty for failing to do so. See 26 U.S.C. § 6332(a), (d). The Code protects a person who complies:

Any person in possession of (or obligated with respect to) property or rights to property subject to levy upon which a levy has been made who, upon demand by the Secretary, surrenders such property or rights to property (or discharges such obligation) to the Secretary (or who pays a liability under subsection (d)(1)) shall be discharged from any obligation or liability to the delinquent taxpayer and any other person with respect to such property or rights to property arising from such surrender or payment.

Id. § 6332(e). This provision might indeed have protected Pro-Steel even without the filing of the interpleader action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
810 F. Supp. 2d 1302, 108 A.F.T.R.2d (RIA) 5678, 2011 U.S. Dist. LEXIS 102565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pro-steel-buildings-inc-v-united-states-flnd-2011.