Private Mini Storage Realty, L.P. v. Larry F. Smith, Inc.

304 S.W.3d 854, 2010 Tex. App. LEXIS 683, 2010 WL 338151
CourtCourt of Appeals of Texas
DecidedFebruary 1, 2010
Docket05-08-01043-CV
StatusPublished
Cited by12 cases

This text of 304 S.W.3d 854 (Private Mini Storage Realty, L.P. v. Larry F. Smith, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Private Mini Storage Realty, L.P. v. Larry F. Smith, Inc., 304 S.W.3d 854, 2010 Tex. App. LEXIS 683, 2010 WL 338151 (Tex. Ct. App. 2010).

Opinion

OPINION

Opinion By

Justice MYERS.

Private Mini Storage Realty, L.P., GJR Management Holdings, L.P., and Storage Realty, L.L.C. appeal the grant of Larry F. Smith, Inc.’s motion for summary judgment as to appellants’ liability and the award of damages and attorney’s fees to Smith following a trial before the court. *856 Appellants bring four issues asserting the trial court erred in granting Smith’s motion for summary judgment, the evidence is legally and factually insufficient to support the award of damages, and the court erred in awarding Smith its attorney’s fees. We affirm the trial court’s judgment.

BACKGROUND

In 1999, appellants had a storage facility built on their property. Raus Construction Company was the general contractor for the project, and Raus hired Smith as a subcontractor to perform the concrete work. Smith submitted invoices to Raus for about $593,000. Pursuant to the subcontract between Raus and Smith, when Raus paid the invoices, Raus retained ten percent of the amount. Raus did not pay Smith any part of approximately $18,000 that Smith invoiced.

On November 12, 1999, Smith sent appellants a notice stating it was owed $74,400.21 consisting of $16,784.10 for unpaid work and $57,616.11 for the retained funds. Smith requested that appellants retain the money they would otherwise have paid to Raus, and Smith demanded that appellants pay Smith the amount it was owed. On December 14, 1999, Smith notified appellants it had filed a mechanic’s lien affidavit for $18,649 for unpaid labor and materials. As required by statute, appellants retained ten percent or $321,849 of the contract amount owed to Raus, but they never paid any of that to Smith.

On December 31, 2001, Smith filed suit against appellants. In its petition, Smith alleged quantum meruit, a statutory claim under section 53.084 of the Texas Property Code, and a claim for foreclosure of its mechanic’s lien. Smith and appellants filed cross-motions for summary judgment on the issue of appellants’ liability to Smith. Smith asserted in its motion for summary judgment that appellants were also liable under section 53.083(b) of the property code. 1

Subchapter E of the property code requires an owner to retain ten percent of the funds to be paid to a general contractor to secure payment to “artisans and mechanics” who were not paid by the general contractor. When the time expires for filing a claim on these retained funds, the owner pays the retainage to the general contractor. See Tex. Prop.Code AnN. §§ 53.101-.107 (Vernon 2008). Subchapter D permits an owner to retain additional amounts due to the contractor upon the request of a subcontractor when the contractor fails to pay the subcontractor as required during the performance of the contract. See id. §§ 53.081-085. Under section 53.084, the owner will be personally liable for any amounts paid to the contractor after receiving the proper notice under the statute if the subcontractor’s lien has been secured and its claim reduced to judgment. See id. § 53.084. Section 53.083 permits a subcontractor to demand payment from an owner who was authorized to retain funds under subchapter D. The subcontractor must send a copy of the demand to the general contractor, who then has thirty days to notify the owner of the general contractor’s intent to dispute the subcontractor’s claim. If the general contractor does not give timely notice of intent to dispute the claim, “he is considered to have assented to the demand and *857 the owner shall pay the claim.” Id. § 53.088(b). Smith asserted in its motion for summary judgment that appellants were required to pay the claim under section 53.083(b) because it gave notice to Raus, and Raus did not notify appellants within thirty days of an intent to dispute Smith’s claim.

In their motion for summary judgment and responses to Smith’s motion for summary judgment, appellants asserted:

(1) Smith failed to meet the requirements for quantum meruit because there was a contract for the labor and materials provided.
(2) Smith’s lien claim fails because
(a) there was no lien for the ten percent contractually retained on the paid work;
(b) Smith did not give proper notice under sections 53.056 and .057 of the property code because the notice and lien affidavit were sent to appellants’ former address;
(c) appellants filed a bond under property code section 53.171 to discharge the lien; and
(d) Smith’s lien claim was barred by limitations.
(3) Smith failed to prove its claim under section 53.084 because
(a) Smith had not reduced its claim to judgment;
(b) Smith did not give timely notice because the notice was sent to appellants’ former address; and
(c) appellants did not pay Raus after receiving notice of Smith’s lien.
(4) Smith failed to prove its claim under section 53.083 because
(a)evidence showed Raus disputed Smith’s claim even though Raus did not give the notice of dispute set forth in section 53.083(b);
(b) appellants did not receive the notice of the lien as required;
(c) Smith’s claim had not been reduced to final judgment; and
(d) Smith’s claim under section 53.083 was premature in that it had not accrued when Smith demanded payment under section 53.083 because the work on the project had not been completed.

On January 24, 2007, the trial court denied appellants’ motion for summary judgment and granted Smith’s, ruling that Smith established appellants’ liability as a matter of law under its mechanic’s and materialman’s lien for unpaid work and on its claim for the funds Raus had retained pursuant to the subcontract. The trial court ordered the case set for trial to determine the amount, if any, of damages Smith was entitled to recover.

On May 21, 2007, while the trial was pending, appellants filed a motion for rehearing of the cross-motions for summary judgment presenting new arguments and new evidence on the issues determined in the trial court’s ruling on the motions for summary judgment. The trial court did not sign an order on the motion for rehearing.

In the trial before the court on damages, Smith’s president, Larry Smith, testified the total amount the company was owed for the project was $593,323.38 and that it was paid $513,331.63, leaving $79,991.75 it was still owed. The trial court’s judgment awarded Smith actual damages of $79,991.75, ordered that Smith was entitled to foreclosure of its mechanic’s and materi-alman’s lien, and awarded Smith attorney’s fees.

SUMMARY JUDGMENT

In their first and second issues, appellants assert the trial court erred in grant *858 ing Smith’s motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeff P. Jorgenson v. Joe v. Evans
Court of Appeals of Texas, 2016
James v. Valdez
378 S.W.3d 644 (Court of Appeals of Texas, 2012)
Examination Management Services, Inc. v. Kersh Risk Management, Inc.
367 S.W.3d 835 (Court of Appeals of Texas, 2012)
S & I Management, Inc. v. Sungju Choi
331 S.W.3d 849 (Court of Appeals of Texas, 2011)
McAfee, Inc. v. Agilysys, Inc.
316 S.W.3d 820 (Court of Appeals of Texas, 2010)
Exel Transportation Services, Inc. v. Aim High Logistics Services, LLC
323 S.W.3d 224 (Court of Appeals of Texas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
304 S.W.3d 854, 2010 Tex. App. LEXIS 683, 2010 WL 338151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/private-mini-storage-realty-lp-v-larry-f-smith-inc-texapp-2010.