Primos Chemical Co. v. Fulton Steel Corp.

266 F. 945, 1920 U.S. Dist. LEXIS 1098
District Court, N.D. New York·Decided August 9, 1920·Published·Cited by 2 cases

Opinion

RAY, District Judge.

THe special master has found the facts as follows:

“First. That on or about July 20, 1918, claimant and Fulton Steel Corporation made and entered into the written contract, Exhibit 8 herein, whereby claimant agreed to furnish and Fulton Steel Corporation to take an electric crane: that the agreed sum to be paid by said Fulton Steel Corporation to said claimant for said crane was 812,600, 50 per cent, of which was to 'become due and payable upon receipt of invoice and bill of lading by Fulton Steel Corporation, and the balance in cash 60 days from the day of shipment of said crane to Fulton Steel Corporation; that said contract further iwovided that shipment of said crane by claimant should be not later than 75 days after receipt by claimant of complete data and O. K.’ed clearances; that said contract further provided that claimant would use every reasonable means to make shipment within the time specified, but assume no liability for loss or damage arising from nonfulfillment of said contract by reason of fires, strikes, delays in transportation, or any cause unavoidable or beyond its control.
“Second. That between the dates of July 20, 1918, and August 12, 1918, tne parties to said contract mutually agreed and did modify said contract, by changing certain of the specifications for said crane at agreed further compensation to claimant of $850, but not otherwise modifying the terms of said contract.
“Third. That final and O. K.’ed clearances for said crane in accordance with said amended contract were mailed to claimant by Fulton Steel Corporation on or about the 18th day of August, 1918, and were received by claimant on the 19th day of August, 1918.
“Fourth. That on the 19th day of August, 1918, claimant received from Fulton Steel Corporation a priority certificate from the War Industries Board of the United States, No. 1*90820, permitting and authorizing claimant to manufacture and deliver said crane under class A-6; that said certificate is Exhibit 17 herein; that on or about July 20, 1918. claimant contracted with the American Bridge Company for said American Bridge Company to manufacture for claimant a portion of said crane, to wit, the girder or bridge thereon, with certain appurtenances thereto, and sent to American Bridge Company certain drawings and specifications therefor in accordance with the original specifications of claimant’s original contract with Fulton Steel Corporation.
“Fifth. That said American Bridge Company did not deliver said girder and its fittings to claimant until December 11, 1918.
“Sixth. That subsequent to July 20, 1918, and prior to the date when said girder was contracted to be delivered to Fulton Steel Corporation, priority orders from the War Board of the United States government were received by claimant for other material and machines in process of manufacture by claimant, which priority certificates were of a higher classification than the priority certificate for the crane to be manufactured by claimant for Fulton Steel Corporation.
“Seventh. That subsequent to July 20, 1918, and before the time provided for the delivery of said crane to said Fulton Steel Corporation, certain persons representing themselves to be officials of the United States government visited the plant of claimant, and demanded and ordered that claimant proceed to manufacture and complete certain other cranes then in process of manufacture by claimant, before completing the crane to be manufactured and delivered' by claimant to Fulton Steel Corporation.
“Eighth. That on or about December 19, 1918, at a time when claimant was in default in the delivery and manufacture of said crane pursuant to its contract with Fulton Steel Corporation, said Fulton Steel Corporation, through its receivers, duly elected to rescind said contract, and gave due notice of such rescission to claimant.
“Ninth. That claimant did not manufacture and complete said crane until on or about December 24, 1918.
“Tenth. That prior to July 20, 1918, the Fulton Steel Corporation contemplated and had prepared, through the T. W. Price Engineering Company, Incorporated, a general scheme and plan for the extension of its plant.
[947]*947“Eleventh. Thai there was comprehended in said scheme and within the scope of said extension a stool building; that there was further comprehended in said scheme and within the scope of the extension an electric crane of a 10-ton capacity.
“Twelfth. That said electric crane was to be installed within and operated in said steel building; that on the 15th day of August, 1918, said Fulton Steel Corporation entered into a contract wilh Levering & Garrigues Company for the construction and erection of said steel building at the plant of Fulton Steel Corporation. Fulton, N. 3T.
“Thirteenth. That, the electric crane for which said Fulton Steel Corporation contracted with claimant herein was the crane which Fulton Steel Corporation contemplated installing in said steel building-.
“Fourteenth. That said steel building referred to herein had not been completed or erected on the 22d day of December, 1918, and has never been completed and erected at tire plant of the Fulton Steel Corporation.”

And as conclusions of law the special master held:

“First. That claimant, at and prior to December 19, 1918, had breached the contract, for said electric crane, by failing to complete and deliver said cram; to Fulton Steel Corporation within the time specified in the contract, Exhibit 3, as thereafter modified.
“Second. That while claimant was in default, as set forth in the first finding of fact herein, Pulton Steel Corporation duly elected to and did rescind said contract, and gave due, timely, and sufficient notice of such' rescission to claimant.
“Third. That claimant has failed to prove any just or legal claim or demand in any amount against Fulton Steel Corporation, which is the subject-matter of Exhibit 3 as modified.
“Fourth. That ilie claim of claimant, Milwaukee Electric Crane & Manufacturing Company, heroin, should be and is hereby wholly disallowed.”

The special master’s memorandum of opinion based thereon is as follows :

“The written contract between claimant and Fulton Steel Corporation is dated July 20, 1918. It provides, in substance, for the manufacture of an electric crane by claimant for Fulton Steel Corporation, with shipment to he made in from 60 to 75 days from receipt of complete data and O. K.’ed clearances from Fulton Steel Corporation. The contract also contains the following clause: ‘We will use all reasonable means to make shipment within the time specified, but assume no liability for loss or damage arising from non-fulfillment of contract by reason of fires, strikes, delays in transportation, or any cause unavoidable or beyond our control.’ Certain modifications in the specifications for the crane were thoreafler mutually agreed upon, but final complete specifications and O. K’cd clearances were mailed to claimant by Fulton Steel Corporation August 16, 1918, and received by it August 19, 1918.

Free access — add to your briefcase to read the full text and ask questions with AI

Primos Chemical Co. v. Fulton Steel Corp., 266 F. 945, 1920 U.S. Dist. LEXIS 1098 (N.D.N.Y. 1920).

266 F. 945 (Primos Chemical Co. v. Fulton Steel Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Freeto v. State Highway Commission
166 P.2d 728 (Supreme Court of Kansas, 1946)
Lloyd v. Murphy
153 P.2d 47 (California Supreme Court, 1944)