Prichard Bros., Inc. v. Grady Co.

407 N.W.2d 423
CourtCourt of Appeals of Minnesota
DecidedJuly 31, 1987
DocketC3-86-1530
StatusPublished
Cited by2 cases

This text of 407 N.W.2d 423 (Prichard Bros., Inc. v. Grady Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prichard Bros., Inc. v. Grady Co., 407 N.W.2d 423 (Mich. Ct. App. 1987).

Opinion

OPINION

FOLEY, Judge.

Respondents Prichard Brothers, Inc. and its owners, Harold B. Kertz and Robert J. Kertz, commenced this negligence action against respondents and cross-appellants Martin Grady and The Grady Company for damages arising out of delays in the completion of a construction project. The complaint was subsequently amended to include a claim against appellant Independent School District No. 353, Karlstad, Minnesota, based on negligent hire and retention and agency (vicarious liability), and for amounts due under a construction contract. Because we conclude that the parties’ duties and remedies are imposed solely by contract and that as a matter of law the evidence fails to show that those duties were breached, we reverse and vacate the judgment against Grady and the School District.

FACTS

This action arises out of a construction project. In March 1980, the School District contracted with Grady to provide architectural services in connection with construction of an addition to and the remodeling of a school building. The parties executed a standard American Institute of Architects (AIA) contract as owner and architect, which incorporated the AIA document governing general conditions.

In June 1981, the School District accepted a bid for the project submitted by Prich-ard Brothers. As owner and general contractor, these parties entered into a standard AIA contract for the general construction of the project which also incorporated the AIA general conditions. Construction began immediately and was scheduled to end in May or June 1982. Due to a series of delays, however, construction was not completed until October 10, 1982.

Prichard Brothers thereafter commenced this negligence action against Grady to recover increased costs and lost earnings. The School District was later brought into the action under an amended complaint. Trial eventually proceeded on the following counts in the second (and final) amended complaint: architect’s negligence, agency, and a claim against the School District for the contract balance of $25,465. A fourth count alleging negligent hire and retention had been dismissed prior to trial in re *425 sponse to a motion for partial summary-judgment by the School District.

By special verdict, the jury found that both Prichard Brothers and Grady had been negligent, that Grady was not acting as an agent of the School District at the time of its negligence, that Grady’s negligence was “the result of bad faith * * * or the result of his failure to exercise an honest judgment,” and that Prichard Brothers was entitled to no damages on the contract balance of $25,465. The jury apportioned negligence between the parties (36% to Prichard Brothers and 64% to Grady), and concluded that Prichard Brothers suffered damages of $257,940, $165,081 of which “were the direct result of the negligence of * * * Grady done in bad faith or without an honest judgment.”

Based on these responses, the trial court ordered that the claims against the School District (all of which were based on vicarious liability) be dismissed. Judgment was subsequently entered for Prichard Brothers against the Grady Company in the amount of $165,081.00.

Prichard Brothers then moved for judgment notwithstanding the verdict “on the ground that the law and the evidence presented does not support the jury’s negative response to question seven of the Special Verdict regarding the question of agency.” Grady also moved for JNOV or a new trial, or in the alternative for remittitur. The trial court subsequently denied Grady’s motions, but granted Prichard Brothers’ motion for JNOV and concluded that Grady was an agent of the School District as a matter of law and that the School District was therefore vicariously liable for his negligence. An amended judgment was accordingly entered jointly and severally against the Grady Company, Martin Grady individually, and the School District for $165,081 in damages together with prejudgment interest of $28,317.04.

The School District thereafter moved for a new trial and for judgment on its cross-claim for indemnity. The trial court denied the motion for a new trial, but granted the School District indemnity from Grady. A second amended judgment was entered. These appeals followed.

ISSUE

Did the trial court properly allow this case to proceed on a negligence theory?

ANALYSIS

Prichard Brothers’ claims of negligence centered around Grady’s actions in three general areas: 1) preparation of the plans and specifications for a roof expansion joint and finish hardware; 2) interpretation of specifications and response to shop drawings submitted; and 3) inspection of the project site. In rulings during trial and in its post-trial memoranda, the trial court correctly noted that the evidence established that Grady had been negligent, if at all, only with respect to the interpretation and response to shop drawings. Prich-ard Brothers conceded during trial that it was not claiming negligent preparation of plans and specifications, and the testimony of its own witnesses established that Grady’s inspection of the site was appropriate and not unreasonable. The damages awarded were thus for delays allegedly caused by Grady’s negligent interpretation of specifications and response to shop drawings.

To prevail in tort, it was necessary for Prichard Brothers to establish that Grady breached “some duty imposed by law, not merely one imposed by contract.” D & A Development Co. v. Butler, 357 N.W.2d 156, 158 (Minn.Ct.App.1984) (quoting Keiper v. Anderson, 138 Minn. 392, 398, 165 N.W. 237, 238 (1917)). Tort duties are independent of contract:

The fundamental difference between tort and contract lies in the nature of the interests protected. Tort actions are created to protect the interest in freedom from various kinds of harm. The duties of conduct which give rise to them are imposed by law, and are based primarily upon social policy, and not necessarily upon the will or the intention of the parties. * * * Contract actions are created to protect the interest in having *426 promises performed. Contract obligations are imposed because of conduct of the parties manifesting consent * * *.

D & A Development, 357 N.W.2d at 158 (quoting W. Prosser, Handbook of the Law of Torts § 92, at 613 (4th ed. 1971)).

A definite conflict exists between tort and contract principles in the area of construction litigation. At least one commentator has concluded that tort theories are inappropriate to resolution of these disputes, particularly where the parties' duties are imposed by contract and represent negotiated limitations and remedies. Espel, Liability and Loss Allocation for Economic Losses in Construction Litigation Involving Design Professionals, 13 Wm. Mitchell L.Rev. 81 (1987).

While the Minnesota Supreme Court has never squarely decided whether these types of claims for economic loss involving design professionals sound in contract or tort, it has been disinclined to allow tort theories to supersede rules of contract law in other commercial settings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prichard Bros., Inc. v. Grady Co.
436 N.W.2d 460 (Court of Appeals of Minnesota, 1989)
Prichard Bros., Inc. v. Grady Co.
428 N.W.2d 391 (Supreme Court of Minnesota, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
407 N.W.2d 423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prichard-bros-inc-v-grady-co-minnctapp-1987.