Price Trucking Corp. v. Norampac Indus., Inc.

CourtCourt of Appeals for the Second Circuit
DecidedMarch 18, 2014
Docket11-2917-cv
StatusPublished

This text of Price Trucking Corp. v. Norampac Indus., Inc. (Price Trucking Corp. v. Norampac Indus., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Price Trucking Corp. v. Norampac Indus., Inc., (2d Cir. 2014).

Opinion

11‐2917‐cv Price Trucking Corp. v. Norampac Indus., Inc.

1 UNITED STATES COURT OF APPEALS

2 FOR THE SECOND CIRCUIT

3 August Term, 2012

4 (Argued: September 24, 2012 Decided: March 18, 2014)

5 Docket No. 11‐2917‐cv

6 ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

7 Price Trucking Corp.,

8 Plaintiff‐Counter‐Defendant‐Appellee,

9 ‐ v ‐

10 Norampac Industries, Inc.,

11 Defendant‐Counter‐Claimant‐Appellant.

12 ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

13 Before: KATZMANN, Chief Judge, and STRAUB and SACK, Circuit Judges.

14 Appeal from a judgment of the United States District Court for the Western

15 District of New York (Richard J. Arcara, Judge). The district court, upon the

16 report and recommendation of Magistrate Judge Hugh B. Scott, granted the

17 plaintiff partial summary judgment on the issue of liability, and subsequently

18 entered final judgment at the request of both parties. The district court 1 concluded that the federal Comprehensive Environmental Response,

2 Compensation, and Liability Act permitted the plaintiff subcontractor to recover

3 the value of unpaid work directly from the defendant landowner, although the

4 landowner had already paid the general contractor for the plaintiffʹs work, and

5 the general contractor had failed to make the required payments to the

6 subcontractor. Because we conclude that the Act does not impose such liability,

7 the judgment of the district court is

8 REVERSED and the case REMANDED.

9 _____________

10 JOHN GILBERT HORN (Craig A. Slater, of 11 counsel), Harter Secrest & Emery LLP, Buffalo, 12 N.Y., for Appellant.

13 KEVIN M. HOGAN, Phillips Lytle LLP (Patricia 14 A. Mancabelli, of counsel), Buffalo, N.Y., for 15 Appellee.

16 SACK, Circuit Judge:

17 This dispute presents an issue of apparent first impression regarding the

18 federal Comprehensive Environmental Response, Compensation, and Liability

19 Act (ʺCERCLAʺ). The defendant, a landowner, paid a general contractor for costs

20 associated with the cleanup of a contaminated parcel of land that the defendant

21 owned. The general contractor failed, however, to remit those payments to the

2 1 plaintiff, a subcontractor who had performed work on the site. The plaintiff then

2 sought payment directly from the defendant landowner. The sole question

3 presented on appeal is whether CERCLA grants the subcontractor a right of

4 recovery against the landowner in these circumstances, effectively requiring the

5 landowner to pay twice for the same work performed – once to the contractor

6 and once to the subcontractor. We conclude that it does not. Accordingly, we

7 reverse the district courtʹs grant of partial summary judgment to the plaintiff

8 subcontractor and remand the case with instructions to grant summary judgment

9 in favor of the defendant.

10 BACKGROUND

11 The principal facts underlying this lawsuit are undisputed. At all relevant

12 times, the defendant Norampac Industries, Inc., owned a parcel of land in Erie

13 County, New York. After Norampac discovered that soil at the site contained

14 levels of lead and other contaminants that exceeded maximums set by the New

15 York State Department of Environmental Conservation (ʺDECʺ), the company

16 entered into a Brownfield Site1 Cleanup Agreement with the DEC. The

1 The New York Environmental Conservation Law, pursuant to which this agreement was entered into, defines a ʺBrownfield siteʺ as ʺany real property, the redevelopment or reuse of which may be complicated by the presence or potential presence of a contaminant.ʺ N.Y. Envtl. Conserv. Law § 27‐1405(2); see also 42 U.S.C. § 9601(39)(A) (setting out a similar definition under CERCLA).

3 1 Agreement required Norampac to prepare and submit a plan for investigating

2 and remedying the soil contamination.

3 In October 2007, pursuant to its cleanup obligations under the Agreement,

4 Norampac contracted with AAA Environmental, Inc., a contractor located in

5 upstate New York, to perform remedial work, including the excavation and

6 removal of contaminated soil. The contract required that Norampac make

7 ʺprogress paymentsʺ to AAA Environmental at regular intervals based on the

8 amount of work completed. The agreement between Norampac and AAA

9 Environmental required the contractor to furnish performance and payment

10 bonds in amounts equal to the total contract price, but these requirements were

11 waived in a contract addendum.

12 In December 2007, AAA Environmental subcontracted with Price Trucking

13 to transport from the site and dispose of the contaminated soil. Throughout the

14 following year, Price Trucking hauled the soil to licensed disposal facilities.

15 AAA Environmental initially paid Price for this service, but on or about

16 October 6, 2008, the payments stopped. Once AAA Environmental refused to

17 pay outstanding invoices, Price Trucking stopped working on the project,

18 insisting that Norampac first agree to pay Price Trucking directly for its portion

4 1 of all subsequent services performed. Norampac agreed to this arrangement, and

2 made direct payments to Price for the final stages of its work.

3 As of September 19, 2008, the parties had substantially finished work on

4 the site, and the DEC subsequently certified completion. By that time, Norampac

5 had paid AAA Environmental more than $3 million for services related to the

6 cleanup effort, in addition to the payments that Norampac had made directly to

7 Price Trucking pursuant to the arrangement noted above. But Price was unable

8 to recover the balance of the payments due to it from AAA Environmental.

9 Other subcontractors who worked on the site also complained that they had not

10 been paid in full. The parties agree that Price completed its work in compliance

11 with the Agreement, the contract between Norampac and AAA, the subcontract

12 between AAA and Price, and all applicable laws and regulations, and that Price

13 received no objections from AAA Environmental, Norampac, or the DEC

14 regarding its work.

15 On November 16, 2009, Price Trucking instituted this lawsuit against

16 Norampac in the United States District Court for the Western District of New

17 York, seeking $780,204.08 in unpaid bills for its work regarding the site. Priceʹs

18 sole theory of recovery in this action was premised on CERCLAʹs liability

5 1 provision, codified at 42 U.S.C. § 9607, the relevant provisions of which are

2 discussed below.

3 On March 31, 2010, Price moved for partial summary judgment against

4 Norampac on the issue of liability. Norampac cross‐moved for summary

5 judgment and an order dismissing the lawsuit. On June 17, 2010, Magistrate

6 Judge Hugh B. Scott recommended that the district court rule in favor of Price

7 Trucking on both motions. Price Trucking Corp. v. Norampac Indus., Inc., No. 09‐

8 cv‐990A, 2010 WL 4069223, 2010 U.S. Dist. LEXIS 113216 (W.D.N.Y. June 17,

9 2010). District Judge Richard J. Arcara subsequently adopted the reportʹs

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W.R. Grace & Co. v. Zotos International, Inc.
559 F.3d 85 (Second Circuit, 2009)
Isbrandtsen Co. v. Johnson
343 U.S. 779 (Supreme Court, 1952)
Kamen v. Kemper Financial Services, Inc.
500 U.S. 90 (Supreme Court, 1991)
United States v. Bestfoods
524 U.S. 51 (Supreme Court, 1998)
Simon v. Navon
116 F.3d 1 (First Circuit, 1997)
NEPSK, Inc. v. Town of Houlton
283 F.3d 1 (First Circuit, 2002)
Key Tronic Corp. v. United States
511 U.S. 809 (Supreme Court, 1994)
Niagara Mohawk Power Corp. v. Chevron U.S.A., Inc.
596 F.3d 112 (Second Circuit, 2010)
Marsh v. Rosenbloom
499 F.3d 165 (Second Circuit, 2007)
United States v. Chem-Dyne Corp.
572 F. Supp. 802 (S.D. Ohio, 1983)
Kahn v. Kahn
256 A.D. 1000 (Appellate Division of the Supreme Court of New York, 1939)
Perma Pave Contracting Corp. v. Paerdegat Boat & Racquet Club, Inc.
156 A.D.2d 550 (Appellate Division of the Supreme Court of New York, 1989)
Schiavone v. Pearce
79 F.3d 248 (Second Circuit, 1996)
Prisco v. A & D Carting Corp.
168 F.3d 593 (Second Circuit, 1999)
Commander Oil Corp. v. Barlo Equipment Corp.
215 F.3d 321 (Second Circuit, 2000)
Marrama v. Citizens Bank
127 S. Ct. 427 (Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Price Trucking Corp. v. Norampac Indus., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/price-trucking-corp-v-norampac-indus-inc-ca2-2014.