Price Trucking Corp. v. Norampac Indus., Inc.

Court of Appeals for the Second Circuit·Decided March 18, 2014·No. 11-2917-cv·Published

Opinion

11‐2917‐cv Price Trucking Corp. v. Norampac Indus., Inc.

1 UNITED STATES COURT OF APPEALS 2 FOR THE SECOND CIRCUIT 3 August Term, 2012 4 (Argued: September 24, 2012 Decided: March 18, 2014) 5 Docket No. 11‐2917‐cv 6 ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 7 Price Trucking Corp., 8 Plaintiff‐Counter‐Defendant‐Appellee, 9 ‐ v ‐ 10 Norampac Industries, Inc., 11 Defendant‐Counter‐Claimant‐Appellant. 12 ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 13 Before: KATZMANN, Chief Judge, and STRAUB and SACK, Circuit Judges. 14 Appeal from a judgment of the United States District Court for the Western 15 District of New York (Richard J. Arcara, Judge). The district court, upon the 16 report and recommendation of Magistrate Judge Hugh B. Scott, granted the 17 plaintiff partial summary judgment on the issue of liability, and subsequently 18 entered final judgment at the request of both parties. The district court

1 concluded that the federal Comprehensive Environmental Response, 2 Compensation, and Liability Act permitted the plaintiff subcontractor to recover 3 the value of unpaid work directly from the defendant landowner, although the 4 landowner had already paid the general contractor for the plaintiffʹs work, and 5 the general contractor had failed to make the required payments to the 6 subcontractor. Because we conclude that the Act does not impose such liability, 7 the judgment of the district court is 8 REVERSED and the case REMANDED. 9 _____________

10 JOHN GILBERT HORN (Craig A. Slater, of 11 counsel), Harter Secrest & Emery LLP, Buffalo, 12 N.Y., for Appellant.

13 KEVIN M. HOGAN, Phillips Lytle LLP (Patricia 14 A. Mancabelli, of counsel), Buffalo, N.Y., for 15 Appellee.

16 SACK, Circuit Judge: 17 This dispute presents an issue of apparent first impression regarding the 18 federal Comprehensive Environmental Response, Compensation, and Liability 19 Act (ʺCERCLAʺ). The defendant, a landowner, paid a general contractor for costs 20 associated with the cleanup of a contaminated parcel of land that the defendant 21 owned. The general contractor failed, however, to remit those payments to the

1 plaintiff, a subcontractor who had performed work on the site. The plaintiff then 2 sought payment directly from the defendant landowner. The sole question 3 presented on appeal is whether CERCLA grants the subcontractor a right of 4 recovery against the landowner in these circumstances, effectively requiring the 5 landowner to pay twice for the same work performed – once to the contractor 6 and once to the subcontractor. We conclude that it does not. Accordingly, we 7 reverse the district courtʹs grant of partial summary judgment to the plaintiff 8 subcontractor and remand the case with instructions to grant summary judgment 9 in favor of the defendant. 10 BACKGROUND 11 The principal facts underlying this lawsuit are undisputed. At all relevant 12 times, the defendant Norampac Industries, Inc., owned a parcel of land in Erie 13 County, New York. After Norampac discovered that soil at the site contained 14 levels of lead and other contaminants that exceeded maximums set by the New 15 York State Department of Environmental Conservation (ʺDECʺ), the company 16 entered into a Brownfield Site1 Cleanup Agreement with the DEC. The

1

The New York Environmental Conservation Law, pursuant to which this agreement was entered into, defines a ʺBrownfield siteʺ as ʺany real property, the redevelopment or reuse of which may be complicated by the presence or potential presence of a contaminant.ʺ N.Y. Envtl. Conserv. Law § 27‐1405(2); see also 42 U.S.C. § 9601(39)(A) (setting out a similar definition under CERCLA).

1 Agreement required Norampac to prepare and submit a plan for investigating 2 and remedying the soil contamination. 3 In October 2007, pursuant to its cleanup obligations under the Agreement, 4 Norampac contracted with AAA Environmental, Inc., a contractor located in 5 upstate New York, to perform remedial work, including the excavation and 6 removal of contaminated soil. The contract required that Norampac make 7 ʺprogress paymentsʺ to AAA Environmental at regular intervals based on the 8 amount of work completed. The agreement between Norampac and AAA 9 Environmental required the contractor to furnish performance and payment 10 bonds in amounts equal to the total contract price, but these requirements were 11 waived in a contract addendum. 12 In December 2007, AAA Environmental subcontracted with Price Trucking 13 to transport from the site and dispose of the contaminated soil. Throughout the 14 following year, Price Trucking hauled the soil to licensed disposal facilities. 15 AAA Environmental initially paid Price for this service, but on or about 16 October 6, 2008, the payments stopped. Once AAA Environmental refused to 17 pay outstanding invoices, Price Trucking stopped working on the project, 18 insisting that Norampac first agree to pay Price Trucking directly for its portion

1 of all subsequent services performed. Norampac agreed to this arrangement, and 2 made direct payments to Price for the final stages of its work. 3 As of September 19, 2008, the parties had substantially finished work on 4 the site, and the DEC subsequently certified completion. By that time, Norampac 5 had paid AAA Environmental more than $3 million for services related to the 6 cleanup effort, in addition to the payments that Norampac had made directly to 7 Price Trucking pursuant to the arrangement noted above. But Price was unable 8 to recover the balance of the payments due to it from AAA Environmental. 9 Other subcontractors who worked on the site also complained that they had not 10 been paid in full. The parties agree that Price completed its work in compliance 11 with the Agreement, the contract between Norampac and AAA, the subcontract 12 between AAA and Price, and all applicable laws and regulations, and that Price 13 received no objections from AAA Environmental, Norampac, or the DEC 14 regarding its work. 15 On November 16, 2009, Price Trucking instituted this lawsuit against 16 Norampac in the United States District Court for the Western District of New 17 York, seeking $780,204.08 in unpaid bills for its work regarding the site. Priceʹs 18 sole theory of recovery in this action was premised on CERCLAʹs liability

1 provision, codified at 42 U.S.C. § 9607, the relevant provisions of which are 2 discussed below. 3 On March 31, 2010, Price moved for partial summary judgment against 4 Norampac on the issue of liability. Norampac cross‐moved for summary 5 judgment and an order dismissing the lawsuit. On June 17, 2010, Magistrate 6 Judge Hugh B. Scott recommended that the district court rule in favor of Price 7 Trucking on both motions. Price Trucking Corp. v. Norampac Indus., Inc., No. 09‐ 8 cv‐990A, 2010 WL 4069223, 2010 U.S. Dist. LEXIS 113216 (W.D.N.Y. June 17, 9 2010). District Judge Richard J. Arcara subsequently adopted the reportʹs 10 findings and recommendations, found in favor of Price on the issue of liability, 11 and scheduled a trial to assess damages. Price Trucking Corp. v. Norampac Indus., 12 Inc., No. 09‐cv‐990, 2011 WL 767702, 2011 U.S. Dist. LEXIS 18631 (W.D.N.Y. Feb. 13 25, 2011). 14 Instead of litigating the issue of damages, the parties stipulated that if there 15 were liability, the damages were equal to the outstanding sum owed to Price 16 Trucking: $631,257.02, plus interest. This amount is less than that stated in the 17 complaint, reflecting, among other things, amounts recovered by Price Trucking 18 in one of two related state court lawsuits, although the suits were pending at the 19 time this appeal was brought.

Free access — add to your briefcase to read the full text and ask questions with AI

Price Trucking Corp. v. Norampac Indus., Inc., (2d Cir. 2014).

Price Trucking Corp. v. Norampac Indus., Inc. (Price Trucking Corp. v. Norampac Indus., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

W.R. Grace & Co. v. Zotos International, Inc.
559 F.3d 85 (Second Circuit, 2009)
Isbrandtsen Co. v. Johnson
343 U.S. 779 (Supreme Court, 1952)
Kamen v. Kemper Financial Services, Inc.
500 U.S. 90 (Supreme Court, 1991)
United States v. Bestfoods
524 U.S. 51 (Supreme Court, 1998)
Simon v. Navon
116 F.3d 1 (First Circuit, 1997)
NEPSK, Inc. v. Town of Houlton
283 F.3d 1 (First Circuit, 2002)
Key Tronic Corp. v. United States
511 U.S. 809 (Supreme Court, 1994)
Niagara Mohawk Power Corp. v. Chevron U.S.A., Inc.
596 F.3d 112 (Second Circuit, 2010)
Marsh v. Rosenbloom
499 F.3d 165 (Second Circuit, 2007)
United States v. Chem-Dyne Corp.
572 F. Supp. 802 (S.D. Ohio, 1983)
Kahn v. Kahn
256 A.D. 1000 (Appellate Division of the Supreme Court of New York, 1939)
Perma Pave Contracting Corp. v. Paerdegat Boat & Racquet Club, Inc.
156 A.D.2d 550 (Appellate Division of the Supreme Court of New York, 1989)
Schiavone v. Pearce
79 F.3d 248 (Second Circuit, 1996)
Prisco v. A & D Carting Corp.
168 F.3d 593 (Second Circuit, 1999)
Commander Oil Corp. v. Barlo Equipment Corp.
215 F.3d 321 (Second Circuit, 2000)
Marrama v. Citizens Bank
127 S. Ct. 427 (Supreme Court, 2006)