Prewett v. Iberg (In Re Iberg)

395 B.R. 83, 2008 Bankr. LEXIS 3050, 2008 WL 4604067
CourtUnited States Bankruptcy Court, E.D. Arkansas
DecidedOctober 16, 2008
DocketBankruptcy No. 4:07-BK-12286. Adversary No. 4:07-ap-01233
StatusPublished
Cited by7 cases

This text of 395 B.R. 83 (Prewett v. Iberg (In Re Iberg)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prewett v. Iberg (In Re Iberg), 395 B.R. 83, 2008 Bankr. LEXIS 3050, 2008 WL 4604067 (Ark. 2008).

Opinion

MEMORANDUM OPINION

RICHARD D. TAYLOR, Bankruptcy Judge.

Before the court is the Complaint Objecting to Discharge and to Determine Dis-chargeability of a Debt [Complaint] filed by Teresa Prewett [Prewett], and the Answer filed by the debtors, Craig and Gayla Iberg. In her Complaint, Prewett seeks monetary damages for breach of contract, denial of discharge based on 11 U.S.C. § 727(a)(5), and a determination of dis-chargeability pursuant to 11 U.S.C. § 523(a)(6). This matter was tried on September 8, 2008. The parties appeared personally and by their attorneys. For the reasons stated below, the discharge and dischargeability counts are denied and dismissed as to both Craig and Gayla Iberg, and Prewett is awarded judgment in the amount of $67,075.06 against separate debtor Craig Iberg. Prewett may elect to file a proof of claim for that amount. 1

I. Jurisdiction

This court has jurisdiction over this matter under 28 U.S.C. §§ 1334 and 157. This is a core proceeding under 28 U.S.C. § 157(b)(2)(I), (J), and (0). The following opinion constitutes findings of fact and conclusions of law in accordance with Federal Rule of Bankruptcy Procedure 7052. A separate judgment will be entered pursuant to Federal Rule of Bankruptcy Procedure 7054.

II. Findings of Fact

A. Home Construction

Intending to build a home on property she owned, Prewett sought bids based on detailed architectural plans and specifications [the Plans]. Craig Iberg submitted the lowest bid by approximately $100,000. Pursuant to a Contractor Agreement [the Agreement], dated May 18, 2005, Prewett contracted solely with Craig Iberg, d/b/a Iberg Builders [the debtor], to construct a new home for $305,000. Article 1 of the Agreement incorporated the Plans as well as an addendum prepared by the debtor concerning specific items. The addendum was not a substitute for the Plans, as argued by the debtor; rather, the Agreement incorporated the Plans. Further, the Agreement called for the debtor to complete construction by December 31, 2005.

The debtor failed to construct the home in a timely or proper manner. The debt- or’s principal defense to a litany of horrific construction problems was an assertion that Prewett’s acceptance of his low bid was an acknowledgment and acquiescence to both non-compliance with the Plans and substandard (i.e. “cutting corners”) construction. Prewett’s acceptance of the debtor’s bid had neither consequence. The acceptance of a low bid did not relieve the debtor from his contractual obligation to build the home according to the Plans and “in a workman-like manner and in compliance with all building codes and oth *87 er applicable laws.” (PL’s Ex. B at 2, Art. 5, ¶ 1.) The debtor also argued that although he might be a bad contractor, his deficiencies did not equate to willful and malicious conduct sufficient to find the underlying debt nondischargeable.

The debtor used substandard materials as well as unacceptable and inadequate construction practices, which resulted in a flawed and unsafe dwelling. Prewett’s home inspection expert, Tom Allen, put it best when he stated the following in his December 9, 2006, report:

The invasive inspections revealed the most blatant disregard for your physical safety and financial waste I have witnessed in my over 30 years in this profession. The report by Mr Lewis is shocking but not surprising. In most structures I encounter deficiencies in a specific area where there is failure to perform on the part of a contractor or a sub contractor. This isolates the area of concern and makes correction manageable. This is not the case with your property.
There were no areas above the foundation that conformed to “best practice”, the building code, the energy code; in fact there was more effort than necessary expended in doing the work wrong than had it been done properly. With that in mind it appears that hast[e], inexperience, lack of oversight, lack of basic engineering, deliberate substitution of inappropriate materials, lack of product knowledge, and disregard of existing Protective Code requirements has produced a structure that is in failure.

(PL’s Ex. JJ.)

He concluded, “[t]his is an unfortunate situation with no good solution.” Id.

Phillip Lewis, a structural engineer hired by Prewett, harshly concluded the following in his November 24, 2006, report:

1. It appears that the contractor had blatant disregard for what was designed and specified on the plans with regards to structural framing. Additionally, it appears that his efforts were even fraudulent in that he was able to cover all of the framing with sheetrock without any attempt to correct the issues.
2. His efforts (or lack thereof) have severely compromised the structural integrity of the residence. Undersized framing members coupled with improperly supported roof rafters and major beams have led to this condition.
5. The owners of the residence did not receive the structure that was specified in great detail (above average for most residential house plans) on the design drawings that they paid for and the contractor specifically bid from.

(PL’s Ex. KK.)

Among other remedial measures, the structural engineer recommended removing and replacing the entire roofing infrastructure. Id. The framing was inadequate and undersized in full load conditions, such as wind and snow. He noted a systematic use of substandard materials, both in quality and size, which caused potentially catastrophic safety concerns. (PL’s Ex. KK.) Mr. Lewis was also troubled by the debtor sheetrocking over obviously improper framing, thus hiding the deficient work. Id. The structural engineer concluded that the home was built in a manner that would clearly cause Prewett financial harm. Id.

The debtor acknowledged his poor workmanship and inadequate construction. He completely lacked the requisite skill sets to hold himself out as a contractor. He was not even appropriately licensed; rather, his wife, separate debtor Gayla Iberg, held a contractor’s license. According to the debtor, he is incapable of passing the licensing test. The Agreement, however, *88

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Derek Luebbert v. Global Control Systems, Inc.
987 F.3d 771 (Eighth Circuit, 2021)
Page v. LaMantia
D. Maine, 2019
Harris v. Kamps (In re Kamps)
575 B.R. 62 (E.D. Pennsylvania, 2017)
Fulton, N.A. v. Robbins (In re Robbins)
562 B.R. 83 (E.D. Pennsylvania, 2016)
Coleman v. Fields (In re Fields)
544 B.R. 156 (E.D. Arkansas, 2016)
Carter v. Patterson (In re Patterson)
485 B.R. 905 (E.D. Arkansas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
395 B.R. 83, 2008 Bankr. LEXIS 3050, 2008 WL 4604067, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prewett-v-iberg-in-re-iberg-areb-2008.