Prestige Land Company v. Brian Mullins Excavating Contractors, Inc.

CourtCourt of Appeals of Tennessee
DecidedOctober 29, 2010
DocketE2009-02609-COA-R3-CV
StatusPublished

This text of Prestige Land Company v. Brian Mullins Excavating Contractors, Inc. (Prestige Land Company v. Brian Mullins Excavating Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prestige Land Company v. Brian Mullins Excavating Contractors, Inc., (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE September 22, 2010 Session

PRESTIGE LAND COMPANY v. BRIAN MULLINS EXCAVATING CONTRACTORS, INC.

Appeal from the Chancery Court for Roane County No. 15233 Frank V. Williams, III, Chancellor

No. E2009-02609-COA-R3-CV - FILED OCTOBER 29, 2010

Prestige Land Company (“Developer”) owned land upon which it intended to build a commercial shopping center. An estimate to complete the project was obtained. Thereafter, the project was opened up for bidding. Brian Mullins Excavating Contractors, Inc. (“Contractor”) bid on the project. Although Contractor’s bid was significantly lower than the next lowest bid, it was only 10% lower than the estimated costs of construction. Contractor was unaware that it had made a unilateral mistake in its bid. Contractor was awarded the project. Eventually, Contractor was unable to complete the project because it ran out of money due to its unilateral bidding mistake. Developer sued for breach of contract, and Contractor filed a counterclaim for fraud and other claims. The Trial Court awarded Contractor a judgment for $101,357.05. Finding no clear and convincing evidence of fraud by Developer, we vacate the judgment for Contractor and enter a judgment for Developer in the amount of $128,326.56.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Vacated; Case Remanded

D. M ICHAEL S WINEY, J., delivered the opinion of the court, in which H ERSCHEL P. F RANKS, P.J., and J OHN W. M CC LARTY, J., joined.

C. Paul Harrison and Garrett P. Swartwood, Knoxville, Tennessee, for the Appellant, Prestige Land Company.

Richard M. Smith and Craig N. Mangum, Nashville, Tennessee, for the Appellee, Brian Mullins Excavating Contractors, Inc. OPINION

Background

This construction lawsuit involves the building of Pinnacle Pointe Development in Harriman, Tennessee. Developer sued Contractor for breach of contract after Contractor ran out of money and was unable to complete the project as required by the contract between the parties. Developer also sued Ohio Farmers Insurance Company (“Ohio Farmers”) on a performance bond issued on the project. According to the complaint:

On or about April 1, 2003, [Developer] entered into a written contract (the “Contract”) with [Contractor] in connection with a construction project in Harriman, Tennessee, known as the Pinnacle Pointe Development (the “Project”). . . .

In accordance with the Contract, [Contractor] was required, among other things, to perform its work in accordance with a certain schedule of Completion Dates attached to the Contract.

On or about April 1, 2003, Ohio Farmers provided a Performance Bond in connection with the Project. . . . The Performance Bond bound Ohio Farmers to perform the Contract between [Developer and Contractor], in the event [Contractor] failed to perform.

Work by [Contractor] commenced in or about April of 2003.

[Contractor], however, failed to complete the work under the Contract in a timely manner pursuant to the Schedule of Completion Dates.

[Contractor’s] default under the Contract delayed the use of the Project by [Developer], thereby causing [Developer] significant damages. [Developer] is entitled to recover liquidated damages for these delays from [Contractor] in the amount of $7,000.00 per day under the terms of the Contract.

-2- [Developer] notified Ohio Farmers of [Contractor’s] default and Ohio Farmers has refused to render performance of the Contract pursuant to the terms of the Performance Bond.

As a direct result of [Contractor’s] failure to complete the Project timely, and Ohio Farmer’s failure to perform under the Performance Bond, [Developer] was forced to complete the work itself with another contractor.1 (original paragraph numbering omitted; footnote added)

Contractor filed an answer and counterclaim against Developer. In its answer, Contractor denied any liability to Developer. According to Contractor2 :

[Contractor] served as the site work contractor on the Project and held a prime contract with [Developer]. The above referenced Project involved the development of multiple parcels of real estate in preparation for a multi-use retail development. [Contractor] bid the work on or around March 28, 2003. [Contractor’s] bid did not anticipate the poor subsurface conditions, and thus underestimated the labor and material needed to complete the Project. [Contractor’s] bid was fifty five percent or $1,869,220.00 lower then (sic) the next lowest bidder. Subsequent to the bid opening [Developer] falsely represented to [Contractor] that the bid spread between the contractors was very close. [Contractor] relied on the assurances provided by [Developer] and entered into a contract with [Developer] on April 1, 2003, for an amount significantly below the cost of construction. . . .

[Contractor] diligently prosecuted the work and has supplied or caused to be supplied materials and labor necessary for improvements to the Project. [Contractor] struggled throughout the Project to meet their financial obligations due to

1 Ohio Farmers eventually settled Developer’s claims against it for $150,000 and an order of partial dismissal was entered. The agreed order of partial dismissal specifically stated that it did not affect any claims between Ohio Farmers and Contractor. We will discuss Ohio Farmers only to the extent its settlement with Developer affects the claims against Contractor or is otherwise pertinent to resolving this appeal. 2 The counterclaim consists of numerous one-sentence paragraphs. When quoting the counterclaim, we have combined the paragraphs and eliminated the paragraph numbering.

-3- their mounting losses. Near the end of the Project, [Contractor] had consumed all of its operating capitol (sic) and was unable to complete a small portion of the project.

Contractor filed several liens pursuant to Tenn. Code Ann. § 66-11-101, et seq. and sought enforcement of these liens. Contractor also brought claims against Developer for fraud, misrepresentation and deceit, and unjust enrichment. Contractor sought a judgment in the amount of $958,565.56.

Developer responded to the counterclaim and denied any liability to Contractor. Developer further claimed, among other things, that the liens were statutorily defective, that Contractor was estopped from making the claims asserted in the counterclaim, and that Contractor failed to state a claim for unjust enrichment.

In February 2009, Developer filed a motion for summary judgment seeking dismissal of Contractor’s counterclaim. Developer claimed that the undisputed material facts established that: (1) Contractor waived any and all lien claims when it executed a Final Waiver and Release in June 2004; (2) Contractor failed to comply with the requirements of Tenn. Code Ann. § 66-11-126 when it failed to bring suit against the owners of the property in question; and (3) Contractor failed to state a claim for quantum meruit because Contractor already had been paid more than the contract price. Attached to the motion was a document titled “Final Waiver and Release of Lien” signed by Contractor’s president, Brian Mullins, and which provides as follows:

[Contractor] releases all liens and rights to lien the property, any state or federal statutory bond right, any private bond right, any claim for payment and any rights under any similar ordinances, rule or statute related to claim or payment rights for persons in the undersigned’s position, the undersigned has on the real property at Pinnacle Pointe Development in Harriman Tennessee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
Brooks v. Brooks
992 S.W.2d 403 (Tennessee Supreme Court, 1999)
Dobbs v. Guenther
846 S.W.2d 270 (Court of Appeals of Tennessee, 1992)
Devorak v. Patterson
907 S.W.2d 815 (Court of Appeals of Tennessee, 1995)
Marron v. Scarbrough
314 S.W.2d 165 (Court of Appeals of Tennessee, 1958)
McMillin v. Great Southern Corporation
480 S.W.2d 152 (Court of Appeals of Tennessee, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Prestige Land Company v. Brian Mullins Excavating Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/prestige-land-company-v-brian-mullins-excavating-c-tennctapp-2010.