Premier Land Development v. Joseph Kishfy Bel Air Tile Company, Inc. v. Joseph Kishfy

Supreme Court of Rhode Island·Decided January 11, 2023·No. 21-72,73·Published

Opinion

January 11, 2023 Supreme Court

Premier Land Development :

v. : No. 2021-72-Appeal.

(PC 12-341)

Joseph Kishfy et al. :

Bel Air Tile Company, Inc., et al. :

v. : No. 2021-73-Appeal.

(PM 12-1218)

Joseph Kishfy. :

NOTICE: This opinion is subject to formal revision before publication in the Rhode Island Reporter. Readers are requested to notify the Opinion Analyst, Supreme Court of Rhode Island, 250 Benefit Street, Providence, Rhode Island 02903, at Telephone (401) 222-3258 or Email: opinionanalyst@courts.ri.gov, of any typographical or other formal errors in order that corrections may be made before the opinion is published.

Supreme Court

Premier Land Development :

v. : No. 2021-72-Appeal.

(PC 12-341)

Joseph Kishfy et al. :

Bel Air Tile Company, Inc., et al. :

v. : No. 2021-73-Appeal.

(PM 12-1218)

Joseph Kishfy. :

Present: Suttell, C.J., Goldberg, Robinson, Lynch Prata, and Long, JJ.

OPINION

Justice Goldberg, for the Court. This case came before the Supreme Court on October 4, 2022, pursuant to an order directing the parties to appear and show cause why the issues raised in this appeal should not be summarily decided. The defendant, Joseph Kishfy (defendant), appeals from a final judgment1 entered in

1 The underlying cases, PC 12-341 and PM 12-1218, were consolidated by order of the Superior Court on January 5, 2018.

favor of Premier Land Development (plaintiff), arising from a construction contract.2 After considering the parties’ written and oral submissions and reviewing the record, we are satisfied that cause has not been shown and that this case may be decided without further briefing or argument. For the reasons stated herein, we affirm the judgment of the Superior Court.

Facts and Travel

In August 2011, defendant entered into a purchase-and-sales agreement with Robert Lanni (Lanni) for property located at 15 Paddock Drive, Lincoln, Rhode Island, for $630,000.00. The defendant agreed to purchase the property “as is,” and waived all inspections and contingencies, except for radon gas testing. The defendant himself inspected the property prior to executing the purchase-and-sales agreement. The defendant testified that the property was structurally complete on the exterior, with the exception of a rear deck, while the interior of the property was lacking a kitchen and most flooring, apart from some flooring in the family room.3 A real estate closing was held on August 17, 2011. On the date of the closing, defendant also entered into a separate contract, designated as an “Amendment to Purchase and Sales/Construction Agreement” (construction contract) with Lanni and

2 Although, there is a suggestion by defendant that this property constituted new construction. 3 This property was an existing home, built in 1995.

plaintiff, which Lanni signed as the owner of the property, and David Corsetti signed as the contractor.4 This transaction terminated Lanni’s connection to this case. In the construction contract, defendant agreed to pay plaintiff the sum of $150,000.00 for improvements to the residence at 15 Paddock Drive. Payment was to occur in three installments, to be mutually agreed upon by the parties, with a project completion date of no later than October 28, 2011. A time-is-of-the-essence clause was included in the agreement.

The construction contract contained an itemized list of improvements to be made to the property, for a total project cost of $150,000.00. The work performed by plaintiff was to be guaranteed for one year from the date of completion and the construction contract outlined the allowances for the improvements to be made on the home. If the amount spent was lower than the allowance granted to defendant, he would receive a credit; and he would pay the difference if the amount paid was greater than the allowance.5 Work commenced in August 2011; defendant paid plaintiff $40,000.00 as an initial deposit. A handwritten note on the check indicated that it was a “1st draw to

4 The parties filed a stipulation that David Corsetti, at all material times, was doing business as Premier Land Development. 5 The labor to install the kitchen and vanities, and all plumbing and hardware, was included in the $630,000.00 sale price of the property, and not the construction contract.

David Corsetti.” A second check in the amount of $11,000.00 was tendered to plaintiff on November 11, 2011. The defendant made no further payments to plaintiff.

As work progressed, there were numerous change orders to the originally agreed-upon design of the home, all at defendant’s behest. According to plaintiff, defendant changed the entire layout of the kitchen, which required its subcontractors to install a new gas line and rewire the electrical lines in the kitchen. The plaintiff informed defendant that changing the layout of the kitchen would be an extra cost under the construction contract. Included in the changes to the kitchen layout, defendant added a room, which required a subcontractor to “build it, frame it, board, plaster, [and] electric” the space, all of which was an extra cost. The defendant also requested an elaborate, small, mosaic-like tile back-splash that required extensive labor, and led to a delay in procuring the tile because defendant purchased tile from a store different than the one set forth in the construction contract. The plaintiff again informed defendant that these requested changes were above and beyond the scope of the construction contract and would constitute additional charges.

The defendant additionally requested a change in the design of the floor in rooms on the second floor, deviating from the original pattern. The plaintiff authorized subcontractors to perform this additional labor, which represented an

extra cost. The defendant also sought changes to certain lighting, replacement of existing plugs and switches, and construction of framing for a chandelier.

In addition to an increase in costs, the changes to the design of the home impeded delivery of materials, resulting in delays in the progress of the work. The owner of Bel-Air Tile Company, Inc., a subcontractor, testified that he was required to return to the project on multiple occasions because the necessary tiles were not on site. He further testified that he did not receive certain tiles from defendant until November 30, 2011, well after the scheduled completion date of October 30, 2011.

The defendant e-mailed Corsetti on December 5, 2011, regarding the delay in the completion of the work and questioned when the renovations would be completed. Mr. Corsetti responded that same day reminding defendant that he had assumed the role of quasi-contractor, had completely retrofitted the original design of the house, and that his delay in obtaining and delivering the tile had led to the delay in completion. Mr. Corsetti also informed defendant that plaintiff was owed a substantial amount of money, the balance of which needed to be addressed. He e- mailed defendant on December 11, 2011, with an itemized account of the work that had been completed at that point. There was no response. In the face of defendant’s silence and his failure to satisfy the outstanding invoice, plaintiff and its subcontractors ceased work at the property. These consolidated actions ensued.

In PC 12-341, plaintiff filed an action against defendant and his wife, Paula Kishfy, alleging one count of breach of contract, one count of unjust enrichment, and one count of breach of the implied covenant of good faith and fair dealing. The defendants’ answer denied the allegations of the complaint, and included counterclaims for breach of contract, negligence, and fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Premier Land Development v. Joseph Kishfy Bel Air Tile Company, Inc. v. Joseph Kishfy, (R.I. 2023).

Premier Land Development v. Joseph Kishfy Bel Air Tile Company, Inc. v. Joseph Kishfy (Premier Land Development v. Joseph Kishfy Bel Air Tile Company, Inc. v. Joseph Kishfy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

HUNT TRUCK SALES, ETC. v. Holopak Village
363 So. 2d 27 (District Court of Appeal of Florida, 1978)
Marketing Design Source, Inc. v. Pranda North America, Inc.
799 A.2d 267 (Supreme Court of Rhode Island, 2002)
Casavant v. Campopiano
327 A.2d 831 (Supreme Court of Rhode Island, 1974)
Gem Plumbing & Heating Co., Inc. v. Rossi
867 A.2d 796 (Supreme Court of Rhode Island, 2005)
Nichols v. R.R. Beaufort & Associates, Inc.
727 A.2d 174 (Supreme Court of Rhode Island, 1999)
Women's Development Corp. v. City of Central Falls
764 A.2d 151 (Supreme Court of Rhode Island, 2001)
Alpha Omega Construction, Inc. v. Proprietors of Swan Point Cemetery
962 A.2d 733 (Supreme Court of Rhode Island, 2008)
Haronian v. Quattrocchi
653 A.2d 729 (Supreme Court of Rhode Island, 1995)
Parker v. Byrne
996 A.2d 627 (Supreme Court of Rhode Island, 2010)
Lizotte v. Mitchell
771 A.2d 884 (Supreme Court of Rhode Island, 2001)
Faraone v. Faraone
413 A.2d 90 (Supreme Court of Rhode Island, 1980)
Padula v. J. J. Deb-Cin Homes, Inc.
298 A.2d 529 (Supreme Court of Rhode Island, 1973)
Hernandez v. JS PALLET CO., INC.
41 A.3d 978 (Supreme Court of Rhode Island, 2012)
Sophie F. Bronowiski Mulligan Irrevocable Trust v. Bridges
44 A.3d 116 (Supreme Court of Rhode Island, 2012)
McDonald v. Kelly
14 R.I. 335 (Supreme Court of Rhode Island, 1884)
Charles E. Fogarty v. Ralph Palumbo James Ottenbacher v. Ralph Palumbo
163 A.3d 526 (Supreme Court of Rhode Island, 2017)
Management Capital, L.L.C. v. F.A.F., Inc.
209 A.3d 1162 (Supreme Court of Rhode Island, 2019)