Precision Stone, Inc. v. Arch Insurance

472 F. Supp. 2d 577, 2007 U.S. Dist. LEXIS 7964, 2007 WL 325790
CourtDistrict Court, S.D. New York
DecidedFebruary 1, 2007
Docket04 Civ. 9996(RWS)
StatusPublished
Cited by2 cases

This text of 472 F. Supp. 2d 577 (Precision Stone, Inc. v. Arch Insurance) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Stone, Inc. v. Arch Insurance, 472 F. Supp. 2d 577, 2007 U.S. Dist. LEXIS 7964, 2007 WL 325790 (S.D.N.Y. 2007).

Opinion

OPINION

SWEET, District Judge.

Upon all the proceedings had heretofore and upon the following findings of fact and conclusions of law, judgment will be entered in favor of the plaintiff, Precision Stone, Inc. (“Precision” or the “Plaintiff’), against the defendants, Arch Insurance Company and Lumbermens Mutual Casualty Company (the “Defendants” or the “Sureties”), on the labor and material payment bond (the “Bond”) that the Sureties issued in connection with a construction project in White Plains, New York.

The difficulties presented in the course of the construction, described below, are responsible for the controversy and this resulting contract action.

Prior Proceedings

This action was initiated by the filing of a complaint by Precision on December 17, 2004. Discovery proceeded.

*578 The action was tried to the Court on September 19, 20 and' 25, 2006. At the close of the Plaintiffs case, the Sureties moved to dismiss on the grounds that the action was time-barred as a result of the requirement in the Bond that any action be commenced within one year after work ceased on the project. By oral opinion on September 25, 2006, the motion was denied based upon the January 4, 2004 punch list of work yet to be done. Final submissions were filed on November 6, 2006.

The Facts

In November 2002, the City of White Plains (the “City”) granted George A. Fuller Company (“Fuller”), a construction company, a no-bid contract to be the general contractor for the construction of a new high-tech fountain and plaza along with the build-out of a public community theater (the “Projects”) within the City Center high-rise complex then under construction. Louis Cappelli (“Cappelli”) was the developer of the City Center and the owner of Fuller. He represented to the City that the total development and construction costs for both Projects, including the expenses incurred for the design and architect fees, would not exceed a certain amount of money that the City allocated and that Cappelli/Fuller would pay or absorb any costs in excess of that amount. (City of White Plains, Official Proceedings of the Common Council, vol. 88, no. 51 (November 4, 2002), attached as Exhibit 1 to Pl.’s Post Trial Mem.)

Cappelli also represented to the City that he wanted to substantially complete the construction of the Fountain and the Public Theater by the end of October 2003 (before Election Day) which was also the projected completion date of the City Center. The Bond issued by the Sureties, which are foreign corporations, was executed on April 16, 2003 for the benefit of persons who furnished labor and/or materials for the Project pursuant to the Bond’s terms and conditions. The Bond has not been voided and there are no issues of fact or law as to the validity and procurement of the Bond. The Bond provided that

any beneficiary-claimant hereunder who has not been paid in full within ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed or materials furnished, may sue the Surety and Principal on this bond for such sum as may be justly due, provided, however, that no such suit or action shall be commenced hereunder by such claimant after the expiration of one (1) year following the date on which the Principal ceased work on said contract nor other than in a State Court or United States District Court or competent jurisdiction in and for the County or District in which the contract work is situated.

(Pl.’s Trial Ex. 1.)

On May 8, 2003, at the request of HRH Construction LLC (“HRH”), the construction manager for Fuller, Precision, a New York corporation, submitted a bid for the stone work for the fountains and the plaza for a total price of $536,665.00. On May 14, 2003, HRH issued Precision a “Letter of Intent” to perform the stone work for an agreed contract price of $515,000.00. The Letter of Intent prepared by HRH to Precision provided as follows: “This agreement is in accordance with drawings and specifications from Sasaki dated 5/14/03 and is subject, to the execution of the formal contract by Cappelli Enterprises to follow.” (Pl.’s Trial Ex. 4.)

Precision’s Project Manager, Robert Shedrofsky (“Shedrofsky”), signed the Letter of Intent with qualifiers and conditions that he added to the Letter of Intent, namely, that the agreement was for “scope of work defined by Precision proposal dated 5/8/03” because the “drawings and *579 specs do not match [the actual] work [required.]” Shedrofsky testified that he wanted to be clear that the architectural drawings prepared could not be used to build the stone work for the fountain because they “didn’t represent the job that was described” and “didn’t make any sense.” (Trial Tr. of Sept. 19, 2006, at 13-14.) In addition, Precision conditioned acceptance of the Letter of Intent by incorporating its May 8, 2003 proposal which excluded overtime work. At the time the Letter of Intent was issued, Precision was not provided with a completion date.

Precision did not receive any schedules from HRH during the course of the Project, but was told that Fuller wanted the Project to be completed by the end of October. (Id. at 30.)

Precision first submitted its shop drawings, without which it could not order the stone, on June 3, 2003. Shedrofsky and Jon Tibett (“Tibett”), the owner of Precision, are both qualified and experienced contractors in the stone business for over twenty-five years, and were credible witnesses. According to Tibett, shop drawings are the most critical part of the process in this type of project because they are the “road map for the entire installation and everything that comes before [Precision’s work.]” (Trial Tr. of Sept. 25, 2006, at 103.) The architect for the Project reviewed Precision’s shop drawings and returned them to Precision as “rejected” on June 20, 2003.

On June 25, 2003, HRH wrote to Tibett complaining that Shedrofsky would not agree to order the stone pavers without HRH’s approval of the shop drawings. Shedrofsky responded on June 26, 2003:

You are correct in your last paragraph wherein you state that the stone production must conform to approved shop drawings. Unfortunately, [to] this date we do not have approved drawings and still don’t have final coordinated dimensions. The Architect[’]s note on our shop drawings state that the GC is to coordinate the dimensions with the other trades. Someone needs to approve the dimensions on our drawings. Your demand that we immediately order stone (when you know that we don’t have approved shop drawings) in one sentence and in another sentence reiterate that the need to have approved shop drawings before production is more than a bit confusing. Yesterday, I spoke to you about the Architect[’]s note that changed the stone coping to l'-4" from 1' — 0". You weren’t sure of why this change was made and were to get back to me. I would like to know how we were supposed to order stone when you yourself don’t know what size the coping is suppose[d] to be.

(Pl.’s Trial Ex. 7.) Precision then submitted its second set of shop drawings on June 27, 2003. These drawings were approved and returned to Precision on July 7, 2003. Precision placed its order to Brazil for the stone materials on July 11, 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shawnlee Construction, LLC v. J.K. Scanlan Co.
42 F. Supp. 3d 561 (S.D. New York, 2014)
Arch Insurance v. Precision Stone, Inc.
584 F.3d 33 (Second Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
472 F. Supp. 2d 577, 2007 U.S. Dist. LEXIS 7964, 2007 WL 325790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-stone-inc-v-arch-insurance-nysd-2007.