JoNES, Chief Judge,

delivered the opinion of the court:

Plaintiff, a veteran preference eligible, sues for back pay as supervisory maintenance engineer at the Naval Air Technical Training Center, Norman, Oklahoma, for the period beginning May 7, 1957, the date of his allegedly unlawful separation. He contends that there was a failure to comply with section 14 of the Veterans’ Preference Act of 1944, 58 Stat. 387, as amended, 61 Stat. 723, and the Navy Civilian Personnel Instructions in the removal action accomplished by the installation. In addition, he asserts that the review action taken by the Civil Service Commission was arbitrary and capricious in that it did not include an adequate investigation of the facts connected with the agency action.

On April 5, 1957, plaintiff was served with a notification of proposed removal for cause which set forth in paragraph 2 a series of remarks descriptive of the manner of his performance of duty since his assignment as a civilian employee at the Norman installation. The third paragraph of the notice recited seven “examples” of plaintiff’s ineffectiveness in the performance of his job. These seven subparagraphs included dates, places, and other particulars identifying the “examples” of ineffectiveness. Plaintiff was advised that he had the right to reply to the charges and to request a personal interview concerning them.

He replied in due time in the nature of a general denial. That is, he did not address himself to the seven “examples” of inefficiency; rather, he stated that the proposed removal was not in conformity with applicable law, and was without merit. Plaintiff did not request a hearing within the agency.

Plaintiff was notified by the installation commanding officer that the charges were correct as stated in the notice of proposed action and that he would be separated for inefficiency, effective May 7, 1957. This notice of removal restated the seven “examples” of inefficiency. Plaintiff was notified also that he had the right to appeal the action to the Civil Service Commission or to the Secretary of the Navy through Navy channels, whichever he preferred. On April 15, 1957, plaintiff, through his attorney, appealed the discharge action and certain other personnel actions not pertinent to this opinion. He requested that he be afforded a [42]*42bearing before an appeals examiner of the Eighth Civil Service Eegion and that an investigation of the “total situation” underlying his separation be conducted. He referred to a number of occurrences which he apparently considered to be evidence of retaliation against him by other persons at the air installation, which retaliation was the true cause of his discharge.

An investigation was conducted from May 10,1957, to September 11,1957, and on October 22,1957, a hearing was conducted before a Civil Service Commission appeals examiner at Oklahoma City.

The decision of the appeals examiner treated each of the seven “examples” of inefficiency, and specific consideration was given to information apparently developed in the course of the investigation. The examiner found that six of the seven charges made by the agency were supported and he offered the opinion that the discharge of an employee responsible for such deficiencies would promote the efficiency of the service. The decision also stated that the other incidents referred to by plaintiff in his request for investigation were not deemed to fall within the purview of the applicable law.

Plaintiff appealed the decision of the regional examiner to the Board of Appeals and Eeview which concluded that a complete review of all the evidence disclosed no reason to reverse the regional examiner. Similarly, the Civil Service Commissioners, after studying the record in full, could find no reason to reopen the case.

Plaintiff’s petition in this court attacks the advance notice and notice of termination as failing to satisfy the requirements of the Veterans’ Preference Act, the Navy Civilian Personnel Instructions, and the Federal Personnel Manual, and it alleges that a discharge based on “examples” of inefficiency rather than reasons or charges of inefficiency is illegal. The plaintiff claims, in any event, that the “examples” were not specific or in detail and that certain of the reasons for dismissal were abandoned by the agency during the Civil Service proceedings. Finally, the petition charges arbitrary and capricious conduct at every stage of the Civil Service involvement in the case, particularly in that it did [43]*43not conduct an adequate investigation at the regional level.

The basic circumstance of what plaintiff calls retaliation occurred in the early part of 1956 when the Navy instituted a new maintenance control program at its installations which departed radically from the program in effect theretofore. Plaintiff seems to have felt that it was his obligation to see that the program was implemented at the Norman installation, although it appears that there were several Navy officers whose authority and responsibility exceeded plaintiff’s. At any rate, it seems that the new program caused some controversy and that antagonism developed between plaintiff and most of the people with whom he came in contact. His failure to achieve results prompted plaintiff to institute a formal grievance proceeding which, in effect, challenged the maintenance control system as it then existed and sought to force the military and civilian personnel concerned to comply with measures desired by plaintiff. Plaintiff feels that his action in instituting the grievance hearing led his superiors to retaliate against him by causing his discharge.

Let us begin by saying that we can find no violation of the procedural safeguards of section 14 of the Veterans’ Preference Act at the agency level. He was given an advance written notice of the proposed action more than 30 days before it took place and he was informed of his right to answer the charges personally and in writing. We think that the “examples” of inefficiency were set forth in such detail and with such specificity that he was adequately informed in what respects his work was unsatisfactory and that he could have prepared a response to the charges. He was informed of his right to appeal the agency decision to the Civil Service Commission, which he did. Eegardless of what label they bore, the “examples” of inefficiency were clearly “reasons” within the meaning of section 14.

Plaintiff suggests that the notice of proposed removal did not contain all the reasons therefor because it failed to specify that one reason was management’s desire to retaliate against him. We find it somewhat surprising to expect that the agency would inform an employee that he was being fired because it desired to violate or circumvent the law. Be that as it may, before this court will make a determination [44]*44that there were reasons for plaintiff’s discharge other than those disclosed in the advance notice, it must be convinced from the record that this is so.

Though it is by no means clear that the petition alleges retaliation by the agency, the point may be said to be raised in the brief. The only material in the record addressed to this contention is an affidavit of another former employee of the installation. We are of the opinion that this document does no more than point to events of equivocal significance which could be interpreted as reprisal against plaintiff. The other exhibits which are a part of the record, in our opinion, only show that plaintiff’s actions on the job were such as might have invited retaliation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sokoloff v. United States
4 Cl. Ct. 140 (Court of Claims, 1983)
Staton v. United States
228 Ct. Cl. 797 (Court of Claims, 1981)
Yarnall
652 F.2d 69 (Court of Claims, 1981)
Taylor v. United States
197 Ct. Cl. 855 (Court of Claims, 1972)
Keener v. United States
165 Ct. Cl. 334 (Court of Claims, 1964)
Stevenson v. United States
155 Ct. Cl. 592 (Court of Claims, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
150 Ct. Cl. 39, 1960 U.S. Ct. Cl. LEXIS 106, 1960 WL 8502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/preble-v-united-states-cc-1960.