PR Contractors, Inc. v. United States

69 Fed. Cl. 468, 69 Fed. R. Serv. 352, 2006 U.S. Claims LEXIS 12, 2006 WL 163226
CourtUnited States Court of Federal Claims
DecidedJanuary 20, 2006
DocketNo. 03-30C
StatusPublished
Cited by4 cases

This text of 69 Fed. Cl. 468 (PR Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PR Contractors, Inc. v. United States, 69 Fed. Cl. 468, 69 Fed. R. Serv. 352, 2006 U.S. Claims LEXIS 12, 2006 WL 163226 (uscfc 2006).

Opinion

ORDER AND MEMORANDUM OPINION DENYING DEFENDANT’S MOTION IN LIMINE

WILLIAMS, Judge.

Plaintiff PR Contractors, Inc. (PR) seeks an equitable adjustment of its contract for the enlargement of the Wax Lake levee in St. Mary County, Louisiana, to compensate it for increased labor, trucking and fill costs. Pending before the Court is Defendant’s motion in limine seeking to exclude three exhibits and the testimony of Lin B. Heath, a consultant who prepared the claim. The challenged exhibits are the claim which underlies this action, as well as two memoranda recommending settlement of the claim prepared by Domingo Elguezabal, a former government employee. Because the challenged exhibits and testimony are best evaluated in the context of a trial after Plaintiff has attempted to lay a foundation for their admissibility, the motion in limine is denied.

Discussion

A motion in limine is a preliminary motion that serves a gatekeeping function and permits the trial judge to eliminate from further consideration evidentiary submissions that clearly would be inadmissible for any purpose. Jonasson v. Lutheran Child & Family Servs., 115 F.3d 436, 440 (7th Cir. 1997); see also Luce v. United States, 469 U.S. 38, 41 n. 4, 105 S.Ct. 460, 83 L.Ed.2d 443 (1984).1 Because of the preliminary nature of such motions, “[rjulings on motions in limine ... are subject to change as the case unfolds.” Ultra-Precision Mfg. v. Ford Motor Co., 338 F.3d 1353, 1359 (Fed.Cir.2003). Thus, while [“t]he prudent use of the in limine motion sharpens the focus of later trial proceedings and permits the parties to focus their preparation on those matters that will be considered ____ [sjome evidentiary submissions [ ] cannot be evaluated accurately or sufficiently by the trial judge in such a [470]*470procedural environment.” Jonasson, 115 F.3d at 440.

Exhibit 4, Claim for Equitable Adjustment dated April 16, 2001 drafted by Lin B. Heath

This exhibit consists of a cover letter signed by Plaintiffs president, Cedric Patin, seeking an equitable adjustment from the U.S. Army Corps of Engineers (COE) in the amount of $865,156. The letter contains a certification that the claim is accurate and made in good faith. Appended to this letter is a 57-page “Statement of Claim” which includes a discussion of the five components of the claim and data. The claim summary outlines the five elements of the claims as

follows:

I. Labor Wage Rate Variances: $145,172
II. Increased Trucking Costs: $168,074
III. Material Shrinkage Factor: $394,344
IV. Final Quantity Under-run: $ 43,660
V. Additional Fill Due to Settlement: $113,906
TOTAL AMOUNT OF CLAIM: $865,156

Defendant’s Appendix (DA) 11.

Labor Costs

Plaintiffs claim for increased labor costs stems from its inability to fulfill its labor needs at the Davis-Bacon rates and the COE’s alleged assurances that it would adjust the contract to make up the difference. The claim contains a one-page “Labor Wage Rate Variance Summary,” which lists the rates paid by Plaintiff for various job categories, the Davis Bacon rates and the variance. DA 16. The claim also contains a 16-page chart entitled “Labor Wage Rate Analysis Detail” purporting to list individual employees of PR and their pay for specified weeks. DA 17-32. Finally, the claim contains “General Decision Number LA 960049,” Mar. 15, 1996, listing wage rates in specified counties in Louisiana (including St. Mary) for job categories in River, Harbor and Flood Control Projects. DA 33-35.

Trucking Costs

The increased trucking costs represent costs over and above the $30 per hour trucking costs in Plaintiffs proposal. Plaintiff claims that the COE assured it that if PR could not fulfill its trucking requirements at this rate, it would adjust the contract to cover the variance. PR’s actual trucking cost per hour was $40. DA 12-13. The claim includes a one-page summary of PR’s actual truck rate per hour versus its claimed estimated truck rate per hour and the adjusted “truck unit cost” based upon the quantities of uncompacted and semi-compacted soil hauled. DA 36. This is followed by a one-page “Subcontract Trucking Summary” which lists truck sources, number of trucks, hours and payments, and a page entitled “Diamond C & Subs” listing the same type of information. DA 37-38. The claim also includes a “Payment Application Summary” for Diamond C, a letter agreement that Mel-grave, Inc. (Melgrave) would supply trucks to PR at $40 per hour and four copies of checks issued by Melgrave. DA 39-45.

Shrinkage of Fill Material

PR claims that it is entitled to payment for the full quantity of fill it hauled, not the shrunken fill quantity “in place.” DA 14. The claim contained a “material shrinkage” chart listing the difference in paid quantities and hauled quantities of fill. DA 45.

Final Quantity Under-run

Because the final approved and paid quantities for fill were less than 85 percent of the original estimated quantities, Plaintiff contends that the contract’s ‘Variation in Estimated Quantity” provision entitles it to compensation for this under-run. DA 14-15. The claim contains a chart listing the final surveyed quantity versus the contract quantity for uneompacted and sémi-compacted fill followed by a “Fill Cost Detail.”2 DA 46-50.

Additional Fee Due to Settlement

Plaintiff claims that it had to provide additional fill because settlement plates installed in the levee prior to the fill activity could not be located. Adjustments were made for the recovered plates, and Plaintiff seeks a similar adjustment for the lost plates. DA 15. The claim contains a chart showing the number of plates lost and recovered as well as the “av[471]*471erage subsidence volume,” fill quantity and unit prices followed by a six-page chart entitled “Settlement Computations.” DA 52-58.

The Wholesale Exclusion of Exhibit 4 and Mr. Heath’s Testimony Is Not Warranted at this Juncture

Defendant seeks to exclude Exhibit 4 on the grounds that the claim “is hearsay, contains expert opinions, purports to be an analysis of PR’s damages and is not based upon first hand knowledge.” Def.’s Motion in Limine at 2-3 (Def.’s Mot.). In support of this, Defendant argues that Mr. Heath, the consultant who prepared the claim, relied principally upon PR’s owner, Mr. Patin, for the information in this exhibit. Defendant argues that Mr. Heath’s trial testimony would be unreliable because at his deposition he had no backup documents, could not remember details about the exhibit, and admitted that the claim contained his own opinion. Defendant further submits that any testimony that may be proffered by Mr. Heath in support of Exhibit 4 will exceed the scope of proper lay opinion testimony and lack firsthand knowledge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davita Inc v. United States
Federal Claims, 2016
DaVita Healthcare Partners, Inc. v. United States
125 Fed. Cl. 394 (Federal Claims, 2016)
Rodriguez v. United States
69 Fed. Cl. 487 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
69 Fed. Cl. 468, 69 Fed. R. Serv. 352, 2006 U.S. Claims LEXIS 12, 2006 WL 163226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pr-contractors-inc-v-united-states-uscfc-2006.