Powers & Sons Construction Co. v. Healthy East Chicago

919 N.E.2d 137, 2009 Ind. App. LEXIS 2842, 2009 WL 5149282
CourtIndiana Court of Appeals
DecidedDecember 30, 2009
Docket45A05-0904-CV-204
StatusPublished
Cited by1 cases

This text of 919 N.E.2d 137 (Powers & Sons Construction Co. v. Healthy East Chicago) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powers & Sons Construction Co. v. Healthy East Chicago, 919 N.E.2d 137, 2009 Ind. App. LEXIS 2842, 2009 WL 5149282 (Ind. Ct. App. 2009).

Opinion

OPINION

ROBB, Judge.

Case Summary and Issue

Powers & Sons Construction Company, Inc. ("Powers & Sons") filed a motion for summary judgment alleging Healthy East Chicago, Inc. (Healthy East Chicago") filed its complaint outside the applicable statute of limitation. The trial court denied Powers & Sons's motion for summary judgment. Powers & Sons appeals, raising one issue for our review, which we restate as whether the trial court properly denied summary judgment. Concluding the complaint is governed by the ten-year statute of limitation applicable to written contracts and Healthy East Chicago's complaint was filed within that time, we affirm

Facts and Procedural History

Healthy East Chicago hired Powers & Sons pursuant to a contract dated December 1, 1997, to serve as the construction manager for the construction of a health service facility in East Chicago, Indiana. The contract contained the following provisions:

1.1 RELATIONSHIP OF PARTIES
The Construction Manager accepts the relationship of trust and confidence established with the Owner by this Agreement, and covenants with the Owner to furnish the Construction Manager's reasonable skill and judgment and to cooperate with the Architect in furthering the interests of the Owner....
[[Image here]]
212 CONSULTATION

The Construction Manager shall consult with the Owner and Architect regarding site and use improvements, and the selection of materials, building systems and equipment....

#6oseook

21.6 SUBCONTRACTORS SUPPLIERS AND
The Construction Manager shall ... furnish to the Owner and Architect for their information a list of possible subcontractors....
[[Image here]]
2.3.2.1 Those portions of the Work that the Construction Manager does not customarily perform with the Construction Manager's own personnel shall be performed under subcontracts or by other appropriate agreements with the Construction Manager. The Construction Manager shall obtain bids from Subcontractors ... from the list previously reviewed and, after analyzing such bids, shall deliver such bids to the Owner and Architect. The Owner shall then determine, with the advice of the Construe *140 tion Manager and subject to the reasonable objection of the Architect, which bids will be accepted.... The Construetion Manager shall not be required to contract with anyone to whom the Construction Manager has reasonable objection.
tok ock
24 PROFESSIONAL SERVICES
The Construction Manager shall not be required to provide professional services which constitute the practice of architecture or engineering....

Appellee's Appendix at 11-13. Carras-Szany and Associates, Inc. ("Carras-Sza-ny") provided architectural and engineering services for the facility. Powers & Sons subcontracted the excavation and preparation of the site to Fred Eggers & Sons, Inc., and the concrete work to Walker Construction Company.

At some time after construction was completed in December 1998, Healthy East Chicago noticed cracks in the floors, walls, and ceilings of the building. Healthy East Chicago contacted Powers & Sons and Carras-Szany about the defects and steps were taken to discover the cause. Powers & Sons responded to Healthy East Chicago's concerns by letter dated March 20, 2000, indicating "continuing concrete slab movement should be considered normal and ... continuing minor drywall cracking at exterior walls was the result of normal exterior wall settling." Appendix of Appellant Powers & Sons at 42, Carras-Szany responded to Healthy East Chicago's concerns by letter dated August 14, 2001, recommending "core samples of the concrete slab and subgrade be taken and analyzed." Id. A letter dated December 11, 2002, from Carras-Szany to Healthy East Chicago detailed the results of a meeting at the site between representatives of Carras-Szany and Powers & Sons, as well as a structural engineer. Additional inspections of the building were made in 2004, 2005, and 2006.

On February 15, 2007, Healthy East Chicago filed a complaint against Powers & Sons alleging breach of contract. 1 Specifically, Healthy East Chicago alleged Powers & Sons knew or should have known the proposed building site contained toxic and organic materials and a high water table, it failed to have the toxic and organic materials removed, failed to properly supervise the installation of the concrete slab underlying the building, and failed to warn Healthy East Chicago of the presence of the toxic and organic materials and/or improper installation of the concrete slab could damage the floors, walls, and ceilings of the building. On July 21, 2008, Powers & Sons filed a motion for summary judgment, contending Healthy East Chicago's complaint was governed by a two-year statute of limitation, and further contending there was no genuine issue of material fact that Healthy East Chicago knew of the damage more than two years prior to February 15, 2007. Powers & Sons subsequently filed a motion to strike Healthy East Chicago's response and designation of evidence as untimely. Following a hearing, 2 the trial court entered an order granting Powers & Sons's motion to strike and denying Powers & Sons's motion for summary judgment because "there exist genuine issues as to material fact which would preclude the Court from granting summary judgment." Appendix of Powers & Sons at 18. Powers & Sons then sought and was *141 granted permission to pursue an interlocutory appeal in this court.

Discussion and Decision

I. Summary Judgment Standard of Review

Summary judgment is appropriate only when the designated evidence "shows that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Ind. Trial Rule 56(C). "A genuine issue of material fact exists where facts concerning an issue which would dispose of the litigation are in dispute or where the undisputed facts are capable of supporting conflicting inferences on such an issue." Scott v. Bodor, Inc., 571 N.E.2d 313, 318 (Ind.Ct.App.1991).

We review the grant or denial of a motion for summary judgment de novo. Univ. of S. Ind. Found. v. Baker, 843 N.E.2d 528, 531 (Ind.2006). We examine only those materials properly designated by the parties to the trial court. Trietsch v. Circle Design Group, Inc., 868 N.E.2d 812, 817 (Ind.Ct.App.2007). We construe all facts and reasonable inferences drawn from them in favor of the non-moving party, Am. Home Assurance Co. v. Allen, 814 N.E.2d 662, 666 (Ind.Ct.App.2004), trans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
919 N.E.2d 137, 2009 Ind. App. LEXIS 2842, 2009 WL 5149282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/powers-sons-construction-co-v-healthy-east-chicago-indctapp-2009.