Power Up Lending Group, LTD. v. Cardinal Energy Group, Inc.

CourtDistrict Court, E.D. New York
DecidedMay 21, 2020
Docket2:16-cv-01545
StatusUnknown

This text of Power Up Lending Group, LTD. v. Cardinal Energy Group, Inc. (Power Up Lending Group, LTD. v. Cardinal Energy Group, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Power Up Lending Group, LTD. v. Cardinal Energy Group, Inc., (E.D.N.Y. 2020).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF NEW YORK -------------------------------------------------------X POWER UP LENDING GROUP, LTD.,

Plaintiff, MEMORANDUM AND ORDER 2:16-cv-1545 (DRH)(ST)

- against –

CARDINAL ENERGY GROUP, INC. and TIMOTHY W. CRAWFORD,

Defendants. -------------------------------------------------------X

APPEARANCES

NAIDICH WURMAN LLP Attorneys for Plaintiff 111 Great Neck Road, Suite 214 Great Neck, NY 11021 By: Richard S. Naidich, Esq. Robert P. Johnson, Esq.

THE BASILE LAW FIRM Attorney for Defendant Cardinal Energy Group, Inc. 400 Jericho Turnpike, Suite 104 Jericho, NY 11753 By: Mark R. Basile, Esq. HURLEY, Senior District Judge:

INTRODUCTION

Plaintiff Power Up Lending Group, LTD. (“Plaintiff”) brought the instant action for breach of contract and fraud against Defendants Cardinal Energy Group, Inc. (“Cardinal”) and Timothy W. Crawford (“Crawford,” together with Cardinal, “Defendants”). Presently before the Court are Defendant Cardinal’s Rule 60(b) motion to vacate this Court’s April 3, 2019 Memorandum and Order granting summary judgment on Plaintiff’s breach of contract claim (the “Summary Judgment Order”) and Plaintiff’s Rule 54(b) motion to enter judgment against Cardinal based on the Summary Judgment Order. For the reasons set forth below, Defendant Cardinal’s motion is denied and Plaintiff’s motion is granted. BACKGROUND The Court assumes the parties’ familiarity with the facts, see Power Up Lending Grp., Ltd. v. Cardinal Energy Grp., Inc., 2019 WL 1473090 (E.D.N.Y. Apr. 3, 2019), but finds it useful to provide a summary of the procedural history of this case. Defendants have caused delays throughout the course of this action, which has been pending since March 30, 2016. (ECF No. 1.) On March 13, 2017, Plaintiff made a letter application for a pre-motion conference in anticipation of moving for summary judgment against Cardinal and dismissal without prejudice against Crawford. (ECF No. 21.) Neither defendant responded to this request, and on March 31, 2017, I set a briefing schedule for Plaintiff’s motion. Plaintiff filed its motion for summary judgment on June 2, 2017. (ECF No. 22.) Defendants did not oppose the motion on the date set in the briefing schedule, and over six months went by without any activity from Defendants. On December 15, 2017, one of Defendants’ attorneys, John P. Falcone, moved to withdraw from the case due to “non-existent” communication with Defendants and because his legal fees had not been paid. (ECF No. 23.) On December 21, 2017, Defendants’ other attorney, Brian Zets, moved to withdraw because Defendants had retained new counsel. (ECF No. 25.)

On December 22, 2017, Mark Basile entered an appearance on behalf of Defendant Cardinal only. (ECF No. 26.) That same day, Mr. Basile filed a letter with the Court requesting leave to amend the answer on behalf of Defendant Cardinal to include an affirmative defense of criminal usury and for an extension of time to respond to Plaintiff’s motion for summary judgment, or alternatively, to move to dismiss the complaint. (ECF No. 28.) Defendant Cardinal’s request was granted, and on April 6, 2018, it filed an amended answer. (ECF No. 35.) On June 14, 2018, Defendant Cardinal filed its opposition to Plaintiff’s motion for summary judgment, which was resubmitted that month. (ECF No. 39.) On March 26, 2019, Plaintiff withdrew the part of its motion that sought to dismiss Defendant Crawford. (ECF No. 40.) On April 3, 2019, I granted Plaintiff’s motion for summary judgment on its

breach of contract claim, finding that the agreement between the parties was a merchant funding agreement, not a loan, and that New York’s usury laws therefore did not apply to the agreement. (ECF No. 41.) Because Plaintiff had other outstanding claims against both Defendants Cardinal and Crawford, no judgment was entered at that time. In late August of 2019, Plaintiff withdrew its remaining causes of action against Defendant Cardinal, leaving the breach of contract claim that it had already been granted summary judgment on and its claim for fraud against Defendant Crawford. (ECF No. 45.) Plaintiff then submitted a proposed judgment for the Court to enter against Defendant Cardinal. (ECF No. 46.) Because a claim against Defendant Crawford, for whom a new attorney had recently appeared, still remained, I directed Plaintiff to make a motion pursuant to Federal Rule of Civil Procedure 54(b) to enter judgment as to Defendant Cardinal. Plaintiff did so as directed. (ECF No. 49.) The day before Plaintiff was due to serve its Rule 54(b) motion, Defendant Cardinal filed

a motion to vacate the Summary Judgment Order pursuant to Federal Rule of Civil Procedure Rule 60(b). (ECF No. 47.) In the time since the parties filed their motions, Mr. Basile has moved to withdraw as attorney for Defendant Cardinal due to its failure to pay Mr. Basile’s legal fees. (ECF No. 58.) Additionally, Defendant Crawford filed an amended answer with a crossclaim for indemnification against Defendant Cardinal. (ECF No. 61.) After a principal for Defendant Cardinal twice failed to appear before Magistrate Judge Tiscione, a certificate of default was entered against Defendant Cardinal with respect to Plaintiff’s claim and Defendant Crawford’s crossclaim. (ECF No. 70.) DISCUSSION I. Federal Rule of Civil Procedure 60(b) Standard

Pursuant to Rule 60(b) a court may relieve a party from a final judgment for the following reasons “mistake, inadvertence, surprise or excusable neglect” or “any other reason that justifies relief.” Fed. R. Civ. Pro. 60(b)(1); 60(b)(6). “A motion under Rule 60(b) is addressed to the sound discretion of the trial court." Velez v. Vassallo, 203 F. Supp. 2d 312, 333 (S.D.N.Y. 2002) (citing Mendell in Behalf of Viacom, Inc. v. Gollust, 909 F.2d 724, 731 (2d Cir. 1990)). Nonetheless, the Second Circuit has cautioned that Rule 60(b) provides "extraordinary judicial relief" to be granted "only upon a showing of exceptional circumstances." Nemaizer v. Baker, 793 F.2d 58, 61 (2d Cir. 1986). “Relief under Rule 60(b) is generally not favored . . . .” Ins. Co, of N. Am. v. Pub. Serv. Mut. Ins. Co., 609 F.3d 122, 131 (2d Cir. 2010) (internal citation and quotation marks omitted). In evaluating a Rule 60(b) motion, the courts of this circuit also require that the evidence in support of the motion be highly convincing, that the movant show good cause for the failure to act sooner, and that no undue hardship be imposed on the other parties as a result. See, e.g., Kotlicky v. U.S. Fidelity & Guar. Co., 817 F.2d 6, 9 (2d Cir. 1987);

Williams v. New York City Dept. of Corr., 219 F.R.D. 78, 84 (S.D.N.Y. 2003). II. Federal Rule of Civil Procedure

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Curtiss-Wright Corp. v. General Electric Co.
446 U.S. 1 (Supreme Court, 1980)
Novick v. AXA NETWORK, LLC
642 F.3d 304 (Second Circuit, 2011)
Mendell v. Gollust
909 F.2d 724 (Second Circuit, 1990)
Petrello v. White
533 F.3d 110 (Second Circuit, 2008)
Velez v. Vassallo
203 F. Supp. 2d 312 (S.D. New York, 2002)
Citizens Accord, Inc. v. Town of Rochester
235 F.3d 126 (Second Circuit, 2000)
Phoenix Renovation Corp. v. Gulf Coast Software, Inc.
197 F.R.D. 580 (E.D. Virginia, 2000)
Williams v. New York City Department of Corrections
219 F.R.D. 78 (S.D. New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Power Up Lending Group, LTD. v. Cardinal Energy Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/power-up-lending-group-ltd-v-cardinal-energy-group-inc-nyed-2020.