Powell v. Baker Ice Mach. Co.

8 F.2d 125, 1925 U.S. App. LEXIS 3243
Court of Appeals for the Eighth Circuit·Decided September 14, 1925·No. No. 6931·Published·Cited by 3 cases

Opinion

LEWIS, Circuit Judge.

This is a mechanic’s lien suit. Appellee, the lien claimant, manufactures at Omaha, Nebraska, and sells ice-making and refrigerating machinery and equipment. Moody Engineering Company entered into a written contract with appellants October 21, 1922, by which it agreed to furnish, deliver and install in two ice-making plants belonging to appellants at Fayetteville and Springdale, Washington County, Arkansas, specified machinery and equipment for ice-making purposes; and appellants agreed to pay Moody Engineering Company $30,000 therefor. That contract contains this clause:

“The seller (Moody Engineering- Co.) attaches hereto Baker Catalogue No. 30 and Bulletin No. 70 — page 6, covering a complete description of the ammonia compressors for Fayetteville and Springdale and Murray Catalogue No. 85 page 25, showing engine purchased under this contract. All of the above catalogues in so far as they refer to machinery or equipment in this contract are to become a part of same.”

For the purpose of fulfilling its obligations under the contract Moody Engineering Company on November 13th following made up its order No. 0590, addressed to appellee, wherein it described in general terms four items of machinery and ico-making equipment, with the request that appellee enter the order for shipment to Fayetteville. On the same day Moody Engineering Company made up its order No. 0591, addressed to appellee, describing in general terms three items of machinery and ice-making equipment, and requested appellee to enter the order for shipment to Springdale, and that it be shipped in the same car with the Fayetteville shipment, with stop-over at Spring-dale. The two orders were enclosed in one envelope and were received by appellee in due course. Before appellee could manufacture and send out the equipment called for in the orders changes were made by Moody Engineering Company in both of them. There were eliminations, substitutions and additions. After these changes had been made the equipment called for in order No. 0590 as amended, except the fourth item, was shipped out to Fayetteville February 9, 1923. The changes requested in order No. 0591 caused delay and the equipment for the Springdale plant was not shipped out until May 11, 1923. When the shipment of February 9th arrived at Fayetteville and it was discovered that it did not contain some of the equipment in order No. 0590, Moody Engineering- Company on April 19th wired to appellee about its omission and on April 21st sent an order with instructions to ship the omitted item, and added two other parts to be made up in conjunction therewith. [126] TMs order was gotten out and shipped to Fayetteville on May 7th. There was testimony that the part of the equipment omitted from the February 9th shipment was omitted because there was not then sufficient information furnished to appellee to make it up. Moody Engineering Company installed the equipment received from appellee in the three shipments in appellants’ plants, that contained in the two shipments of February 9th and May 7th in the plant at Fayetteville and that contained in the shipment of May 11th in the Springdale plant. Nothing was paid to appellee, and notice' was given to appellants by appellee that it claimed a lien on the two plants for the price of equipment which it had furnished, it filed with the clerk of the Circuit Court of Washington County its claim of statutory lien and brought this suit to have that lien adjudged and enforced. It obtained a decree accordingly and an order that the two parcels óf real estate (describing them) on which the plant were situate be sold as an entirety, appellee’s claim and costs to be paid out of the purchase price therefor. This appeal is from that order and decree.

In furnishing the equipment appellee dealt only with Moody Engineering Company. It sent to the latter from time to time as shipments were made itemized statements of the prices it charged for the material contained in the three shipments, but Moody Engineering Company failed to make payment thereifor or to cause appellants to pay. On July 11, 1923, less than sixty days after the material contained in the last two shipments was received at the two plants, appellee served appellants with notice of its elaim, that it was for machinery, equipment and material furnished to the Moody Engineering Company that had been placed in the improvements upon the lots on which the two plants were situate, naming the lots and blocks in each city. The Arkansas mechanic’s lien statute, Crawford & Moses. Digest, § 6906, gives to any person who furnishes material, fixtures or machinery, etc., for any building, erection or improvement upon land, or for repairing same, under any contract with the owner or his contractor, a lien thereon for the material or machinery so furnished, upon his complying with the. requirements of the statute. One of these requirements, section 6922, is that the person claiming the lien shall file with the clerk of the circuit court for the county in which the building, erection or improvement to be charged /with the lien is situate, and within ninety days after the things aforesaid shall have been furnished, a just and true account of the demand due or owing to him,, after allowing all_ credits, and containing a correct description of the property to be charged with said lien, verified by affidavit. On August 9th, well within the time limited, appellee filed with the clerk of the circuit court of Washington County its verified claim of lien on the property in each city, describing it, embodying therein a statement of the different kinds of machinery and equipment which it had furnished, the price charged for each item thereof, that the equipment so described had been used in the construction of appellants’ ice-manufacturing plants in each of the cities, that it had been delivered by appellee to Moody Engineering Company and that it claimed a lien on the real estate described and the buildings thereon situate. There is some criticism of the lien claim filed with the clerk, but the court held it to be in proper form and within the required time, and we have no doubt it was a substantial compliance with the statute. Furthermore, appellee instituted its suit to enforce its claimed lien on the two plants within ninety days after the last of the material furnished was delivered at the plants, and the Supreme Court of Arkansas has held that when that is the ease it is unnecessary to file the lien claim with the clerk of the circuit court, that the institution of the suit within the time limited serves every purpose intended by the requirement that a lien statement shall be filed with the clerk. Simpson v. J. W. Black Lbr. Co., 114 Ark. 464, 172 S. W. 883; Carr v. Hahn & Carter, 133 Ark. 401, 202 S. W. 685.

Free access — add to your briefcase to read the full text and ask questions with AI

Powell v. Baker Ice Mach. Co., 8 F.2d 125, 1925 U.S. App. LEXIS 3243 (8th Cir. 1925).

8 F.2d 125 (Powell v. Baker Ice Mach. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related