Potelco, Inc. v. Department Of Labor & Industries

Procedural entryThis page is a short order in Potelco, Inc. v. Department Of Labor & Industries. Read the opinion of the Court — 194 Wash. App. 428
Court of Appeals of Washington·Decided March 7, 2016·No. 73735-0·Unpublished

Opinion

IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON

POTELCO, INC., No. 73735-0-1 c/V<5 .; era

Appellant, cr> "•"tt2 3>*i —«_j v. DIVISION ONE rnrn 1 WASHINGTON STATE DEPARTMENT UNPUBLISHED OPINION —1 ••cor"" i^-oft) OF LABOR & INDUSTRIES, 3» %g& FILED: March 7, 2016 :rs~ Respondent. \0 ** GS$j| CO d$*W-'' -'• vO 2S:f5i\

Leach, J. — Poteico Inc. challenges a Board of Industrial Insurance

Appeals (Board) decision affirming its citation for two serious violations. After an

employee was injured in a work site accident, the Department of Labor and

Industries (Department) cited Poteico for allowing two unqualified employees to

work near a high-voltage transmission line and failing to hold a safety meeting

when work site hazards changed. The Board found facts supporting those

citations, and the trial court found that substantial evidence supported the

Board's findings. Because we agree, we affirm.

Background

Poteico Inc. appeals a trial court order affirming a Department citation.

The Department cited Poteico after an accident that occurred in June 2012 as

Poteico replaced a high-voltage transmission line for Puget Sound Energy.

Poteico was dismantling an existing 115,000-volt transmission line, Baker line 2, No. 73735-0-1 / 2

from the generating plant at Baker Dam to a substation 24 miles away in Sedro

Woolley. This required taking down and rebuilding the structures that supported

the line. A second line, Baker line 1, ran parallel to Baker line 2 and during the

project remained energized with 115,000 volts. For most of their length, the lines

ran parallel, about 60 feet apart. Where the lines turned, however, they came

closer together.1

Before beginning work on the project, Poteico surveyed the area. It knew

where to build each of the new structures because Puget Sound Energy had

designated the locations of the structures and their anchor points. Some

structures were inaccessible by road, so Poteico had to arrange for a helicopter

to fly in materials for constructing the new structures. It used the services of

Salmon River Helicopters on two days, June 25 and June 26, 2012.

On June 26, a Poteico civil crew was building "structure 4/3" at a point

where Baker lines 1 and 2 turned. To do so, the crew had to build three anchors

to support the structure. This required digging three anchor holes by hand and

filling them with gravel and concrete. The helicopter flew these materials in at

the end of a "long line." The long line carried concrete in an aluminum hopper.

The last hole to be filled, anchor hole A, was so close to the energized Baker line

1 that the long line would come within five feet four inches of it. This was the

1 The Board's unchallenged findings of fact are verities on appeal. See Robelv. Roundup Corp., 148 Wn.2d 35, 42, 59 P.3d 611 (2002). -2- No. 73735-0-1 / 3

closest to Baker line 1 that any Poteico worker had to work while a helicopter

was in use.

The long line "was either made of, or wrapped in, Kevlar and had an

extension cord inside of it" to allow the helicopter to drop the load in an

emergency. Both the aluminum hopper and the long line were conductive.

When the helicopter approached for the last drop of the day on June 26,

two Poteico civil employees, Shane Wheeler and Alan Jesmer, were there to

receive it. As Wheeler went to unload the concrete, the long line touched Baker

line 1. When Wheeler then touched the aluminum hopper, he received an

electric shock. He suffered serious injuries and spent two weeks in a burn unit.

Because Poteico did not challenge the above findings, they are verities on

appeal.2

After the Department investigated the accident, it cited Poteico for four

violations of the Washington Industrial Safety and Health Act of 1973 (WISHA),

chapter 49.17 RCW, regulations, with penalties totaling $21,000.3 This appeal

involves two alleged serious violations: (1) failing to hold a conference when a

2 Robel, 148Wn.2dat42. 3 The citation described 4 violations: • Item No. 1-1 A: A serious violation of WAC 296-45-055(5) with a penalty of $7,000; • Item No. 1-1B: A serious violation of WAC 296-45-065(1) with no penalty; • Item No. 1-2: A serious violation of WAC 296-45-67507(2) with a penalty of $7,000; and • Item No. 1-3: A serious violation of WAC 296-45-325(1) with a penalty of $7,000. No. 73735-0-1/4

change in hazards occurred and (2) failing to ensure that only qualified

employees worked "on or near conductive objects brought into close proximity of

high voltage lines."

Poteico appealed to the Board. The Board found the following facts:

Poteico has two classes of workers: journeymen linemen trained to work

on and close to energized lines and civil workers who perform excavation and

construction but have little knowledge of electrical work. Poteico gave civil

workers training "of limited duration," which "basically trained the civil workers to

stay away from energized lines." It did not teach them "how to work on energized

lines or how to protect themselves from hazards posed by working in close

proximity to energized electrical lines."

"Poteico either knew or, through the exercise of reasonable diligence,

could have known that the long line" could conduct electricity.

"Poteico either knew or, through the exercise of reasonable diligence,

could have known, that. . . neither Mr. Wheeler nor Mr. Jensen were . . . trained

to be working where they were." In particular, neither was

trained in the skills and techniques necessary ... to determine the nominal voltage of exposed live parts, the minimum approach distances corresponding to the voltages to which they were exposed, and the proper use of the special precautionary techniques, personal protective equipment, insulating and shielding materials, and insulated tools for working on or near exposed energized parts of electrical equipment.

The work at structure 4/3 was a change in hazards for Potelco's workers

because that structure was so much closer to Baker line 1 than other locations No. 73735-0-1 / 5

where Poteico had worked with a helicopter with a conductive long line. Poteico

either knew or could have known this, and it should have held a conference

before work started to make sure all workers understood the hazards they would

face and precautions they needed to take.

Finally, Wheeler and Jesmer "did not have the training to appreciate the

hazards, and were not utilizing personal protective equipment that could have

reduced the hazards."

The Board found two violations occurred, found two other alleged

violations did not, and reduced the penalty to $14,000.

Poteico appealed to the trial court, which found that substantial evidence

supported all the challenged Board findings of fact. The trial court adopted the

Board's conclusions of law as its own and affirmed its order. Poteico appeals.

Analysis

WISHA governs judicial review of a Board decision.4 This court directly

reviews that decision based on the record before the Board.5 The Board's

findings of fact are conclusive if they are supported by substantial evidence when

viewed in light of the record as a whole.6 Substantial evidence is evidence

sufficient to persuade a fair-minded person of the truth of the matter asserted.7

We view this evidence in the light most favorable to the party that prevailed in

Free access — add to your briefcase to read the full text and ask questions with AI

Potelco, Inc. v. Department Of Labor & Industries, (Wash. Ct. App. 2016).

Potelco, Inc. v. Department Of Labor & Industries (Potelco, Inc. v. Department Of Labor & Industries) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

JE Dunn Northwest, Inc. v. DEPT. OF LABOR & INDUSTRIES
156 P.3d 250 (Court of Appeals of Washington, 2007)
BD Roofing, Inc. v. STATE DOL AND INDUSTRIES
161 P.3d 387 (Court of Appeals of Washington, 2007)
MOWAT CONST. CO. v. Department of Labor and Industries
201 P.3d 407 (Court of Appeals of Washington, 2009)
Robel v. Roundup Corp.
148 Wash. 2d 35 (Washington Supreme Court, 2002)
J.E. Dunn Northwest, Inc. v. Department of Labor & Industries
139 Wash. App. 35 (Court of Appeals of Washington, 2007)
BD Roofing, Inc. v. Department of Labor & Industries
139 Wash. App. 98 (Court of Appeals of Washington, 2007)
Mowat Construction Co. v. Department of Labor & Industries
148 Wash. App. 920 (Court of Appeals of Washington, 2009)
Erection Co. v. Department of Labor & Industries
160 Wash. App. 194 (Court of Appeals of Washington, 2011)
Lodis v. Corbis Holdings, Inc.
292 P.3d 779 (Court of Appeals of Washington, 2013)
Frank Coluccio Construction Co. v. Department of Labor & Industries
329 P.3d 91 (Court of Appeals of Washington, 2014)