POST TENSIONED ENG'G. CORP. v. Fairways Plaza Assoc.

412 So. 2d 871
CourtDistrict Court of Appeal of Florida
DecidedMarch 9, 1982
Docket81-2473, 81-2604
StatusPublished
Cited by35 cases

This text of 412 So. 2d 871 (POST TENSIONED ENG'G. CORP. v. Fairways Plaza Assoc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
POST TENSIONED ENG'G. CORP. v. Fairways Plaza Assoc., 412 So. 2d 871 (Fla. Ct. App. 1982).

Opinion

412 So.2d 871 (1982)

POST TENSIONED ENGINEERING CORP. and Commercial Construction Corp., Petitioners,
v.
FAIRWAYS PLAZA ASSOCIATES, Respondent.

Nos. 81-2473, 81-2604.

District Court of Appeal of Florida, Third District.

March 9, 1982.
Rehearing Denied May 3, 1982.

*872 Mahoney, Hadlow & Valdes-Fauli and William L. Richey, Miami, Kent, Watts, Durden, Kent & Mickler and William G. Cooper, Jacksonville, for petitioners.

Fine, Jacobson, Block, Klein, Colan & Simon and Joseph H. Serota, Miami, for respondent.

Before SCHWARTZ, DANIEL S. PEARSON and JORGENSON, JJ.

DANIEL S. PEARSON, Judge.

Fairways Plaza Associates, the owner, filed suit against Commercial Construction Corporation, the contractor, and Commercial moved to compel arbitration pursuant to a contract which provides:

"7.9 ARBITRATION
"7.9.1 All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof ... shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise."

We review by writ of certiorari the trial court's denial of Commercial's motion.[1]

*873 In our view, the very issues Fairways seeks to resolve by litigation must be resolved in arbitration. First, Fairways' suit does not challenge the validity of the contract or its provision for arbitration, but instead, in full recognition of the contract, seeks damages for its breach. The Florida Arbitration Code, Section 682.03(1), Florida Statutes (1981), specifically provides:

"A party to an agreement or provision for arbitration subject to this law claiming the neglect or refusal of another party thereto to comply therewith may make application to the court for an order directing the parties to proceed with arbitration in accordance with the terms thereof. If the court is satisfied that no substantial issue exists as to the making of the agreement or provision, it shall grant the application. If the court shall find that a substantial issue is raised as to the making of the agreement or provision, it shall summarily hear and determine the issue and, according to its determination, shall grant or deny the application." (emphasis supplied).

Thus, the role of the court in deciding, ab initio, whether arbitration may be compelled is limited to determining whether an enforceable arbitration clause exists. See Comment, The Uniform Arbitration Act in Missouri, 46 Mo.L.Rev. 627, 634 (1981). See generally Annot., Violation or Repudiation of Contract as Affecting Right to Enforce Arbitration Clause Therein, 32 A.L.R.3d 377 (1970); compare Annot., 3 A.L.R.2d 383 (1959) (discussing earlier contrary rule and noting trend toward present rule). There being no challenge by Fairways to the making of the contract, much less the making of the included provision for arbitration, the unchallenged arbitration clause is valid,[2],[3]*874 regardless of the "justiciable character of the controversy."[4] It follows that an alleged breach of a valid contract does not forfeit the included agreement to arbitrate, but rather makes the question of breach one to be decided in arbitration. Gersh v. Concept House, Inc., 291 So.2d 258 (Fla.3d DCA 1974); Merkle v. Rice Construction Company, 271 So.2d 220 (Fla. 2d DCA 1973).

"[The] circuit court may not enjoin or stay an arbitration proceeding upon the ground that the contract providing for arbitration is not in force and effect, because of factual matters which have occurred since the making of the contract. Such an issue is for the arbitrators." Gersh v. Concept House, Inc., supra, at 259.

Second, though it is true that if the arbitration clause of the contract calls for arbitration to take place in a foreign jurisdiction, Florida courts cannot, over objection, compel arbitration, § 682.02, Fla. Stat. (1981); Damora v. Stresscon International, Inc., 324 So.2d 80 (Fla. 1975); Romar Transports Limited, Inc. v. Iron & Steel Company of Trinidad, 386 So.2d 572, 573 (Fla. 4th DCA 1980); see Murphey v. Dean Witter & Co., Inc., 392 So.2d 286 (Fla. 4th DCA 1980); Knight v. H.S. Equities, 280 So.2d 456 (Fla. 4th DCA 1973); the arbitration clause found in the contract between Fairways and Commercial,[5] which provides that arbitration shall be conducted under the rules of the American Arbitration Association, is considered one which merely expresses the method to be followed, not a choice to arbitrate in a foreign jurisdiction or a stipulation that the Florida Arbitration Code shall not apply. Hall v. Nationwide Mutual Insurance Co., 189 So.2d 224 (Fla. 4th DCA 1966). See Travelers Insurance Co. v. Luckett, 279 So.2d 885 n. 1 (Fla. 3d DCA 1973).

Having concluded that the arbitration clause is valid and enforceable, we now address Fairways' contention that Commercial waived its right to demand arbitration. The waiver, says Fairways, arises from Commercial's failure to bind its subcontractors to arbitration pursuant to its agreement with Fairways.[6] If Commercial's alleged failure is simply a breach of its contract with Fairways, then, as we have said, that breach does not affect Commercial's right to compel arbitration, but itself will be submitted to arbitration. Therefore, for Fairways to prevail on its contention, it must show that the alleged breach is an act inconsistent with Commercial's right to arbitration. See, e.g., Lapidus v. Arlen Beach Condominium Association, Inc., 394 So.2d 1102 (Fla. 3d DCA 1981). But even if, arguendo, Commercial elected not to arbitrate with its subcontractors, see n. 6, supra, that election is in no way inconsistent with Commercial's insistence on its right to arbitrate with Fairways. For an act to be inconsistent with the right to arbitrate and thus constitute a waiver of that right, it must repudiate the right of the party who does the act. See Lapidus v. Arlen Beach Condominium Association, Inc., supra, and cases collected therein. The most that can be said about Commercial's failure to bind its subcontractors to arbitration is that it might impinge *875 upon Fairways' ability to include these subcontractors in an arbitration proceeding, not upon Commercial's right to arbitrate with Fairways.

We reject as well Fairways' remaining arguments in defense of the trial court's ruling. Commercial's right to compel arbitration is unaffected by the fact that Fairways' complaint alleges fraud, Vic Potamkin Chevrolet, Inc. v. Bloom, 386 So.2d 286 (Fla. 3d DCA 1980); Raymond, James and Associates, Inc. v. Maves, 384 So.2d 716 (Fla. 2d DCA 1980); seeks equitable relief,[7]Collier Land Corporation v. Royal Palm Realty, Inc., 338 So.2d 859 (Fla. 3d DCA 1976); and concerns a complex construction industry dispute, William Passalacqua Builders, Inc. v. Mayfair House Association, Inc., 395 So.2d 1171 (Fla. 4th DCA 1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles Boyd Const. v. Vacation Beach
959 So. 2d 1227 (District Court of Appeal of Florida, 2007)
Oz v. Warter
943 So. 2d 287 (District Court of Appeal of Florida, 2006)
Kel Homes, LLC v. Burris
933 So. 2d 699 (District Court of Appeal of Florida, 2006)
The Hillier Group, Inc. v. Torcon, Inc.
932 So. 2d 449 (District Court of Appeal of Florida, 2006)
American Intern. Group, Inc. v. Cornerstone Bus., Inc.
872 So. 2d 333 (District Court of Appeal of Florida, 2004)
Rewards Hotel Man. Co., LLC v. Elite Gen. Contr., Inc.
860 So. 2d 1011 (District Court of Appeal of Florida, 2003)
Northport Health Services v. Estate of Raidoja
851 So. 2d 234 (District Court of Appeal of Florida, 2003)
Kinder Mobile Home Sales, Inc. v. Clemens
794 So. 2d 677 (District Court of Appeal of Florida, 2001)
CUNINGHAM HAMILTON QUITER v. BL of Miami, Inc.
776 So. 2d 940 (District Court of Appeal of Florida, 2000)
Grosseibl v. J. Chris Howard Builders
739 So. 2d 1255 (District Court of Appeal of Florida, 1999)
PCA Health Plans v. Proxymed, Inc.
682 So. 2d 224 (District Court of Appeal of Florida, 1996)
Sun City Diner v. CENTURY FIN. ADV.
662 So. 2d 967 (District Court of Appeal of Florida, 1995)
Chemstar Corp. v. Stark
634 So. 2d 794 (District Court of Appeal of Florida, 1994)
Morex Consolidators Corp. v. Industry Shipping & Commerce, Inc.
626 So. 2d 989 (District Court of Appeal of Florida, 1993)
Motyczka v. Kerce
616 So. 2d 549 (District Court of Appeal of Florida, 1993)
MODERN HEALTH CARE SERV., INC. v. Puglisi
597 So. 2d 930 (District Court of Appeal of Florida, 1992)
C & M VENTURES, INC. v. Wolf
587 So. 2d 512 (District Court of Appeal of Florida, 1991)
Steinberg/W.F.I. Foods, Inc. v. D.C.M. & Associates, W.F.I.
522 So. 2d 512 (District Court of Appeal of Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
412 So. 2d 871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/post-tensioned-engg-corp-v-fairways-plaza-assoc-fladistctapp-1982.