Porter v. R. J. Boyd Paving & Construction Co.

112 S.W. 235, 214 Mo. 1, 1908 Mo. LEXIS 208
CourtSupreme Court of Missouri
DecidedJuly 14, 1908
StatusPublished
Cited by30 cases

This text of 112 S.W. 235 (Porter v. R. J. Boyd Paving & Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porter v. R. J. Boyd Paving & Construction Co., 112 S.W. 235, 214 Mo. 1, 1908 Mo. LEXIS 208 (Mo. 1908).

Opinion

GANTT, J.

This is an action in equity against the defendants as owners and holders of certain tax-bills, issued against the appellant’s property, some eighty-three lots in J. L. Porter’s second subdivision and addition to Kansas City, by which it is sought to have said bills canceled by the decree of the court and the apparent lien of said taxhills removed from the title to said lots.

To the defendant Construction Company had been let a contract for the construction of a sewer in sewer district number 227, which was confirmed by an ordinance of the council of Kansas City, on the 13th of May, 1901; and it proceeded with the execution of the work provided for in said contract, and the ordinance under which it was let, and claimed to have completed the same in accordance with its said contract on the 14th of September, 1901, on which date the city issued and delivered to the company the taxhills which are the subject of complaint, and thereupon the plaintiff [6]*6brought this action for the cancellation of said bills against the said property, on September 10, 1902.

The grounds as set forth in the petition on which the said bills are assailed were:.

First, that the ordinance No. 16521, which provided for the construction of the sewer and the letting of the contract for that purpose, and No. 16915 confirming the contract with the defendant company, were not enacted pursuant to the charter provisions in that behalf, in that, while purporting to have received the signature and approval of the mayor of the city, they, in fact, had not been signed by the mayor, but were signed and approved by his private secretary.

Second, that the notice of the letting of the contract was not published ten successive days within the twenty days next preceding the time for opening the bids, in' that said publication was omitted from the newspapers during the period of publication on the 7th and 14th of April, which were Sundays.

Third, that the defendant company never completed the construction of said sewer prior to the issuance of the bills in question, and such completion of said work has never been done, and the particulars in which it is claimed that the contractor failed in completing the sewer are as follows: “ (a) That the contract required the construction of seventeen catch basins, and the contractor only constructed thirteen, (b) That the contract provided that where any part of the sewer was to be built on or above the surface, and any other foundation is required than embankment, such construction and sewer built thereon shall be covered with an earth embankment carried to a height of not less than one foot above the top of the sewer and the top width of such embankment shall not be less than the greatest external diameter of the sewer, and that the contractor had failed to cover with an embankment, as required, a portion of about 1,000 [7]*7feet in length of said sewer, which portion was required to be laid on a wall of rubble masonry.”

Fourth (a) that said contract provided that the excavation shall be done by open cut from the surface except where tunneling is expressly permitted or directed by the city engineer, and that no tunneling was in any manner permitted or directed by the city engineer; but notwithstanding, the contractor, in all parts of the work which was done in earth excavation, adopted the method of tunneling by alternating a section of tunnel with open excavation, instead of doing said work by open cut from the surface as required; and that by reason of such manner of doing said work, it was impossible to fill said trenches and tunnels in a compact manner, as required, and the same was not, in fact, done, (b) That when a trench is in rock formation, the filling required by the contract was that the same be filled with clay to a point two feet above the top of the sewer, provided that the rock from the trench might be used with an equal amount of earth; but no stones of greater dimensions than six inches should be used, and that the filling was required to rammed and tamped; and that 3,258 feet of said sewer was laid in trenches and excavated through rock, in which the contractor did not use earth or clay, as required, but, on the contrary, the rock taken from the trench was dumped into the trench as filling- material, (c) That said contract further provided that all surplus materials from the trenches should be hauled away to such places within a distance of six hundred feet as might be designated by the engineer, and deposited according to his directions; and if no such place was designated, the contractor should be bound to remove the surplus at his own risk and cost; and said contractor, in violation of said requirement, failed to remove the surplus material, but left large quantities thereof dumped upon plaintiff’s lands, situated in the [8]*8neighborhood of said sewer work, (d) That the contractor further failed to complete said contract in this: That manholes were required to be built in the line of said sewer at designated heights, and that the outside of all manholes should be thoroughly plastered with cement mortar; that twenty-nine of such manholes were provided to be built by said contract and ordinance, and the contractor omitted to finish and complete any of them, in that none of these manholes were plastered outside, as required, (e) That it was required that rubble masonry in the construction of said sewer should be built of the best quality of limestone, laid in cement mortar, the stone to be of uniform size, generally not less than two feet square in area and six feet in thickness; that each stone should be laid on its natural bed, with its face down, and should have uniform bearing and be well bedded in mortar, the work to be so laid as to secure a thorough bond throughout. And the charge is that, no such rubble masonry was constructed at all; no such stone or quality of stone as required was used; it was omitted to lay it in cement mortar. All that was done was to use mortar on the outside; and that all of such part of said work was wholly inferior and in every respect failed to comply with the contract in that regard, (f) That said contract required, in joining the sections of sewer pipe, that the joints should be filled with mortar, one part Portland cement, two parts sand, and the joint all thoroughly cleaned on the inside and plastered externally, at least three inches beyond the rim of the socket; and that, in fact, the contractor wholly failed to complete said work in this particular, in that the plastering of each joint was never completed, but for about a fourth of the rim or circumferance of each socket at the bottom of the pipe was entirely without any mortar, and the work in that regard was left wholly incomplete.

[9]*9Briefly stated, the above are the propositions on which relief by cancellation of the bills is asked.

The defendant’s answer denies generally and specially all of the foregoing charges, and concludes with an allegation that, “In all things in the execution of said contract, it acted in good faith and under the direction of the city engineer or the inspector from his office; that, if in any material matter, an error has been made and the plaintiff has been damaged thereby, these defendants would surrender and cancel the said taxbills for the payment of such sum as the court may find the plaintiff should justly pay.”

Upon a trial in the circuit court, the plaintiff’s bill was dismissed and from that judgment the plaintiff has appealed to this court in due form of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No. 88-77 (1977)
Missouri Attorney General Reports, 1977
State v. Burns
172 S.W.2d 259 (Supreme Court of Missouri, 1943)
School District No. 3 of Adams v. Callahan
297 N.W. 407 (Wisconsin Supreme Court, 1941)
Powers v. Kansas City, Mo.
18 S.W.2d 545 (Missouri Court of Appeals, 1929)
City of Grant City Ex Rel. O'Neil v. Salmon
288 S.W. 88 (Missouri Court of Appeals, 1926)
Haeussler Investment Company v. Bates
267 S.W. 632 (Supreme Court of Missouri, 1924)
State Ex Rel. Clayton v. Bland
256 S.W. 757 (Supreme Court of Missouri, 1923)
Hinerman v. Williams
224 S.W. 1017 (Missouri Court of Appeals, 1920)
The Parker-Washington Co. v. Field
214 S.W. 402 (Missouri Court of Appeals, 1919)
Holmes v. Webb City Building & Loan Ass'n
174 S.W. 122 (Missouri Court of Appeals, 1915)
City of Poplar Bluff v. Meadows
173 S.W. 11 (Missouri Court of Appeals, 1915)
Coatsworth Lumber Co. v. Owen
172 S.W. 436 (Missouri Court of Appeals, 1915)
Witham v. Delano
171 S.W. 990 (Missouri Court of Appeals, 1914)
City of Maryville v. Cox
167 S.W. 1166 (Missouri Court of Appeals, 1914)
R. J. Waddell Investment Co. v. Hall
164 S.W. 541 (Supreme Court of Missouri, 1914)
Battles v. United Railways Co. of St Louis
161 S.W. 614 (Missouri Court of Appeals, 1913)
Whiteaker v. Chicago, Rock Island & Pacific Railway Co.
160 S.W. 1009 (Supreme Court of Missouri, 1913)
Rollison v. Wabash Railroad
160 S.W. 994 (Supreme Court of Missouri, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
112 S.W. 235, 214 Mo. 1, 1908 Mo. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/porter-v-r-j-boyd-paving-construction-co-mo-1908.