Porter-Constructors v. Dixon Motor Service Co.

172 S.E. 419, 171 S.C. 396, 1934 S.C. LEXIS 11
CourtSupreme Court of South Carolina
DecidedJanuary 3, 1934
Docket13745
StatusPublished

This text of 172 S.E. 419 (Porter-Constructors v. Dixon Motor Service Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porter-Constructors v. Dixon Motor Service Co., 172 S.E. 419, 171 S.C. 396, 1934 S.C. LEXIS 11 (S.C. 1934).

Opinion

The opinion of the Court was delivered by

Mr. Justice Bonham.

The respondents, in November, 1926, entered into a contract with the State Highway Department for the construe *399 tion of a section of a highway in Aiken County, extending from Clearwater to Savannah River, a distance of approximately four miles. They also entered into a contract with appellant for hauling and placing the excavated earth, constructing embankments, and shaping and maintaining roadbed. It was stipulated in the contract between plaintiff and defendant that the work should be done as by the requirements of the State Highway engineers. It was mutually agreed that plans, proposal sheets, and standard specifications and contract by the State Highway Commission should become part of the contract between respondents and appellant. The job was to be completed in 250 working days.

It was further mutually agreed that it would be necessary to remove 1,000 yards each working day; that the contractors (the respondents) would not require a bond of appellant, but in lieu thereof the appellant agreed that, if it did not furnish sufficient equipment to handle the material to the capacity of the shovel, the contractors might put on additional equipment and charge the expense to appellant, to be paid out of any money then due or to become due them, and that appellant would not move any men or equipment off the job if the contractors needed them in the work.

It .appears that appellant never from the start moved the 1,000 yards required of him by his contract. The contractors did not, during the short days and bad weather of the winter, especially urge 'appellant to comply with this condition, but as the spring passed and the'summer came on and the appellant continued to fall below the required number of yards, the record shows that respondents continually urged that the appellant catch up with the standard, and at last themselves put on extra trucks and hands. From the June estimate of the amount then due appellant for work done, respondents deducted the sum of $650.00 as pay for the extra trucks they had put on, and mailed to appellant a check for $933.39, the balance due on this estimate. It appears that when appel *400 lant ascertained that $650.00 had been withheld by respondents, it threw up the job and moved its equipment across the river to Augusta, Ga. Respondents, thereupon, stopped the payment of the check for $933.39, and instituted this suit, and issued an attachment against the equipment of appellant, but found only one truck on this side of the river.

It may be pertinent to say that respondent is a partnership composed of John M. and E. E. Porter, and the appellant is a corporation under the laws of North Carolina. Both parties have their principal places of business at Charlotte, N. C.

Appellant answered the complaint, and procured the attachment of respondent’s outfit, which was released upon respondents giving a replevin bond in the sum of $10,000.00. The complaint claimed damages in the sum of $11,300.00 for the alleged breach of the contract by appellant. The answer admitted the execution of the contract, and denied all allegations not specifically admitted; for further defense and by way of counterclaim, it alleged that the work was progressing within the schedule; that delays were due to the inefficient manner in which the trucks were loaded by plaintiffs’ agents and employees; that on July 15, 1927, plaintiffs made up the estimate as of June 20th, of the amount due appellant and from it withheld money in excess of $1,000.00, and stopped the payment of a check which had been mailed to defendant; that without cause they attached one of defendant’s trucks and caused some of defendant’s creditors to bear down on them for amount due; that plaintiffs breached the contract; and that by reason of such breach defendant was damaged in the sum of $10,860.00, for which sum defendant asks judgment against the plaintiffs.

The case came on for trial before Hon. C. J. Ramage, special Judge, and a jury, at the November, 1928, term for Aiken County and resulted in the jury finding simply for defendant. That is to say, neither party was awarded any *401 damages. A motion for new trial was duly made by the defendant on the minutes of the Court on the ground that the verdict was against the evidence and not supported by it. The motion was overruled. This appeal followed.

There are 21 exceptions. In considering them, we shall group them as they are pertinent to special issues.

Exceptions 1, 3 and 4 relate to the exclusion of certain testimony which appellant’s counsel sought to evoke from plaintiffs on cross-examination, relating to the financial standing of the plaintiffs.

These exceptions do not cite the Court to any folio or page of the record where the rulings complained of were made, but leave it to the Court to plow through some three hundred pages of testimony to find them. However, they are without merit. Defendant did not in its counterclaim ask punitive damages against plaintiffs, but asked for a fixed and definite sum, $6,745.09, of which, less a credit of $700.-00, was for service performed under the contract, and which plaintiffs held and refused to pay to defendant, and $4,-815.00 as damages “directly and primarily caused by plaintiff’s breach of their contract.” It appears that when counsel for defendant asked E. E. Porter: “What is your real estate holdings?” and plaintiffs’ counsel objected and the objection was sustained by the Court, defendant’s counsel said: “If they don’t want to give it, I will leáve it with them.” No exception was taken to the ruling. It is late now to make exception.

Defendant’s counsel asked of J. M. Porter: “Are you bankrupt?” Objection thereto was sustained. The witness said: “Can I answer that question?” The Court: “If you want to.” The witness : “I have been.” Thus defendant got the benefit of his question, despite the ruling of the Court. Moreover, defendant was amply protected in his business relations with plaintiffs by the conditions of the bond for approximately $40,000.00, which plaintiffs had *402 given the Highway Department, and by the replevin bond for $10,000.00 given by plaintiffs to defendant.

After defendant had left the job, plaintiff contracted with one McFadden to do the work which defendant had left undone. The counsel for defendant asked of E. E. Porter: “Did you put a claim like that in against Mr. McFadden?” (referring to underproduction). Objection to the question was sustained, but not before the witness had answered: “No, sir.” Therefore defendant suffered no harm from the ruling. We may say, too, that the ruling was proper.

Exceptions 5, 6, 7, 8, 9, 10, and 11 set forth alleged errors in the charge of the presiding Judge. The counsel for defendant presented no written requests to charge, but presented to the Court Guerini Stone Co. v. Carlin Const. Co., 248 U. S., 334, 39 S. Ct., 102, 106, 63 L. Ed., 275, and certain sections of 6 R. C. L. The presiding Judge read the syllabus of the case of Guerini Stone Company v. Carlin Const. Co. from the United States Reporter, and certain sections of R. C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guerini Stone Co. v. P. J. Carlin Construction Co.
248 U.S. 334 (Supreme Court, 1919)
Daly v. Jefferson Hotel Co.
82 S.E. 412 (Supreme Court of South Carolina, 1914)
Morrison v. Mutual Benevolent Ass'n
59 S.E. 27 (Supreme Court of South Carolina, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
172 S.E. 419, 171 S.C. 396, 1934 S.C. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/porter-constructors-v-dixon-motor-service-co-sc-1934.