Porta-Fab Corp. v. Young Sales Corp.

943 S.W.2d 686, 1997 Mo. App. LEXIS 287, 1997 WL 75929
CourtMissouri Court of Appeals
DecidedFebruary 25, 1997
Docket69740
StatusPublished
Cited by8 cases

This text of 943 S.W.2d 686 (Porta-Fab Corp. v. Young Sales Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porta-Fab Corp. v. Young Sales Corp., 943 S.W.2d 686, 1997 Mo. App. LEXIS 287, 1997 WL 75929 (Mo. Ct. App. 1997).

Opinion

RHODES RUSSELL, Presiding Judge.

Defendant, Young Sales Corporation (“Young”) appeals from a judgment of the trial court entered on a $240,000 jury verdict in favor of plaintiff, Porta-Fab Corporation (“Porta-Fab”), for breach of a settlement agreement. Young contends the trial court submitted an erroneous verdict director and failed to grant its directed verdict. We find that the verdict director was erroneous and reverse and remand for a new trial. 1

The following evidence was adduced at trial: In 1987, Porta-Fab purchased office buildings and manufacturing facilities located in Chesterfield. Subsequently, Young was hired to install a new roof over the existing roof of Porta-Fab’s manufacturing facility. Young presented a written proposal outlining the installation specifications. At trial, there was evidence that Young had presented two different installation specification proposals. The parties disputed which specifications were ultimately agreed upon. The contract *688 price for the new roof was approximately $123,000.

Young began installing the new roof in November 1987. After Young completed installation of the roof, Porta-Fab experienced recurring problems with water leaking through the roof.

Acknowledging that Young had not properly installed the new roof, Young and Porta-Fab entered into an agreement entitled “Settlement Agreement, Warranty, and Guarantee” in December 1989. Under the terms of the settlement agreement, Young agreed to repay Porta-Fab $15,000 of the price paid under the original contract and to forgive an additional $15,000 that was due under the original contract. Paragraph three of the settlement agreement further provided:

Young Sales does hereby agree to warrant and guarantee all material and workmanship associated with Young Sales’ performance or nonperformance in installing the roof until March 1, 1998, and to make all repairs necessary to stop leaks or correct other problems with the roof which result from any omission or commission on the part of Young Sales within that period of time. Said repairs shall be commenced within ten (10) days of notification by Por-ta-Fab of any agent of Young Sales.

After the execution of the settlement agreement, Porta-Fab continued to experience problems with the leaking roof. Young responded to approximately forty calls from Porta-Fab concerning the leaking roof between December 1989 and 1993. Despite Young’s attempts to fix the roof, Young never successfully stopped the leaks on a permanent basis.

In an effort to resolve the problem, Porta-Fab hired a roofing consultant to perform an inspection and analysis of the roof. The roofing consultant determined that Young had not installed the roof in accordance with the specifications, and that Young’s attempted repairs since the execution of the settlement agreement had not corrected the problems with the roof. The roofing consultant concluded that the roof needed to be replaced.

Porta-Fab eventually hired Werner Brothers Roofing Company (“Werner Brothers”) to repair the leaking portions of the roof. Although the repairs performed by Werner Brothers were effective, Werner Brothers also recommended that the entire roof needed to be replaced. Werner Brothers offered to replace the roof for $301,269.

Porta-Fab subsequently filed suit against Young in December 1993 for breach of contract, seeking damages for the replacement of the roof and attorney fees incurred in enforcing the settlement agreement.

Trial began in the Circuit Court of St. Louis County on October 2, 1995. Porta-Fab’s position at trial was that under the terms of the settlement agreement, it was entitled to have the roof replaced. Porta-Fab maintained that Young’s agreement to warrant and guarantee meant that if Young could not permanently fix the roof, then Young was obligated to construct a new roof. Young’s position at trial was that Porta-Fab was not entitled to a new roof. According to Young, the settlement agreement was a maintenance contract in which it was required to repair the roof when it leaked.

Young’s motion for a directed verdict at the close of the evidence was denied. The trial court then submitted, over Young’s objection, Porta-Fab’s verdict director, Instruction Number 7. Instruction Number 7 provided:

Your verdict must be for the plaintiff if you believe:

First, defendant agreed to warrant and guarantee all performance and workmanship associated with defendant’s performance or nonperformance in installing the roof until March 1, 1998, and to make all repairs necessary to stop leaks or correct other problems with the roof which result from any omission or commission on the part of defendant within that period of time, and
Second, defendant did not fulfill its agreement to warrant and guarantee all materials and workmanship associated with defendant’s performance or nonperformance in installing the roof, or
*689 defendant failed to make all repairs necessary to stop leaks, or
defendant failed to correct other problems with the roof which resulted from any omission or commission on the part of defendant, and
Third, plaintiff was thereby damaged,
unless you believe that plaintiff is not entitled to recover by reason of Instruction Number 9.
MAI 26.02 [1980 Revision] Modified Submitted by Plaintiff

Young’s attorney objected to the submission of Instruction Number 7 because it was based upon MAI 26.02. Young contended that the proper verdict director for Porta-Fab’s cause of action should be based upon MAI 26.06. Young also argued that the instruction was argumentative and unduly emphasized certain evidentiary facts. Finally, Young objected to the submission of the instruction because the second paragraph of the verdict director provided the jury with a roving commission.

After a six day trial, the jury returned a verdict in favor of Porta-Fab, awarding damages in the amount of $240,000 and $99,000 in attorney fees. Young filed a motion for judgment notwithstanding the verdict or in the alternative, a motion for a new trial. The trial court denied Young’s motion for j.n.o.v. and new trial. The trial court entered judgment in accordance with the jury’s verdict. This appeal follows.

In its first two points, Young contends the trial court erred in submitting Instruction Number 7. Since we find merit in Young’s second point that the trial court erred in submitting Instruction Number 7 because it was patterned after MAI 26.02 rather than MAI 26.06, we do not discuss Young’s first point.

In its second point, Young contends the trial court erred in submitting Instruction Number 7 because it was patterned after MAI 26.02. Young argues that Instruction Number 7 should have been patterned after MAI 26.06 rather 'than MAI 26.02 because the terms of the settlement agreement were disputed.

MAI 26.02 is to be used only where there is no dispute concerning the terms of the agreement and the sole question for the jury to decide is whether the defendant has breached the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stephen A. Oliver v. Ford Motor Credit Company, LLC
437 S.W.3d 352 (Missouri Court of Appeals, 2014)
Kline v. City of Kansas City
334 S.W.3d 632 (Missouri Court of Appeals, 2011)
D.R. Sherry Construction, Ltd. v. American Family Mutual Insurance Co.
316 S.W.3d 899 (Supreme Court of Missouri, 2010)
Carroll v. Kelsey
234 S.W.3d 559 (Missouri Court of Appeals, 2007)
Gorman v. Walmart Stores, Inc.
19 S.W.3d 725 (Missouri Court of Appeals, 2000)
Hein v. Oriental Gardens, Inc.
988 S.W.2d 632 (Missouri Court of Appeals, 1999)
A.G. Edwards & Sons, Inc. v. Drew
978 S.W.2d 386 (Missouri Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
943 S.W.2d 686, 1997 Mo. App. LEXIS 287, 1997 WL 75929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/porta-fab-corp-v-young-sales-corp-moctapp-1997.