Popple Construction, Inc. v. Reilly Assoc., Inc.

CourtSuperior Court of Pennsylvania
DecidedJune 10, 2019
Docket775 MDA 2017
StatusUnpublished

This text of Popple Construction, Inc. v. Reilly Assoc., Inc. (Popple Construction, Inc. v. Reilly Assoc., Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Popple Construction, Inc. v. Reilly Assoc., Inc., (Pa. Ct. App. 2019).

Opinion

J-A06022-19

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

POPPLE CONSTRUCTION, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : REILLY ASSOCIATES, INC. : : Appellant : No. 775 MDA 2017

Appeal from the Order Entered January 24, 2017 In the Court of Common Pleas of Luzerne County Civil Division at No(s): 201204138

BEFORE: OTT, J., NICHOLS, J., and PELLEGRINI, J.*

MEMORANDUM BY NICHOLS, J.: FILED JUNE 10, 2019

Appellant Reilly Associates, Inc., appeals from the order granting in part

and denying in part its preliminary objections in the nature of a demurrer to

the complaint filed by Appellee Popple Construction, Inc. Appellant essentially

contends that a contract between Appellee and the City of Pittston bars

Appellee’s lawsuit. For the reasons that follow, we affirm.

We briefly state the following as background.1 According to Appellee’s

complaint, Pittston hired Appellant to design, prepare bidding documents for,

____________________________________________

* Retired Senior Judge assigned to the Superior Court. 1 “[W]e rely on the facts as alleged in the complaint, including its exhibits.” Khawaja v. RE/MAX Central, 151 A.3d 626, 627 n.1 (Pa. Super. 2016) (citation omitted). J-A06022-19

and construct improvements to a sewer system. R.R. at 9a.2 Appellee

reviewed Appellant’s bidding documents for the sewer improvement project

and submitted its bid. Id. at 9a-10a. Appellee won the bid and executed a

contract with Pittston. Id. at 12a.

Appellee sued Appellant and raised a single claim of negligent

misrepresentation.3 Id. at 20a-22a. Appellee claimed Appellant prepared

flawed bidding documents, and as a result, Appellee suffered financial losses.

Id. at 13a-19a. In relevant part, Appellee initially identified several

obligations and duties owed by Appellant. Id. at 20a. The complaint averred

that Appellant prepared flawed plans that Appellee would rely on:

68. [Appellant] knew or intended that the plans, specifications and other engineering and technical information that they prepared, reviewed and furnished to [Appellee] and others for the Project would be used by [Appellee] in the course of and for guidance in performing its business activities in constructing the Project.

69. The plans, specifications, and other engineering and technical information prepared, reviewed and furnished by [Appellant] to [Appellee] and others for the Project were faulty, containing numerous errors, omissions, discrepancies and ambiguities, and were not otherwise in compliance with construction and design requirements.

2 We cite to the reproduced record for the parties’ convenience. 3 According to Appellant, Appellee also sued Pittston in a separate lawsuit. R.R. at 26a. The status of that lawsuit is unknown, but was active as of January 30, 2018. See generally Popple Const., Inc. v. City of Pittston, 1146 CD 2017 (Pa. Cmwlth. Jan. 30, 2018) (order) (quashing City of Pittston’s appeal as interlocutory).

-2- J-A06022-19

Id. at 21a. Appellee’s complaint detailed specific examples of the negligent

misrepresentations, id. at 21a-22a, and concluded as follows:

74. As a direct and proximate result of the negligent misrepresentations by [Appellant], [Appellee] experienced severe job delays, disruptions, hindrances, interferences and inefficiencies which, inter alia, prevented [Appellee] from performing its work in the time, manner and budget originally contemplated for the Project.

75. In response to the aforementioned violations, [Appellee] was forced to resequence and reschedule significant portions of its work, significantly increase manpower and site support staff, and substantially accelerate and compress the performance and completion of its work on the Project, all of which resulted in diminished efficiency and productivity and greatly increased [Appellee’s] cost of performing the work on the Project.

Id. at 22a. We note that Appellee’s complaint did not attach any exhibits,

such as the contract between Appellee and Pittston.

Appellant raised twelve preliminary objections. Appellant’s first three

preliminary objections rely on the contract between Appellee and Pittston. Id.

at 28a-36a. Specifically, the first preliminary objection was that the contract

precluded Appellee from suing Appellant. Id. at 28a. The second and third

preliminary objections were that the contract contained no misrepresentations

and, therefore, Appellee’s negligent misrepresentation claim was legally

insufficient. Id. at 29a-37a.

Appellant’s fourth and fifth preliminary objections were that Appellee’s

claim is barred by the economic loss doctrine or a lack of contractual privity.

Id. at 37a-39a. Appellant’s sixth, seventh, eighth, ninth, and tenth

preliminary objections sought to strike various paragraphs as impertinent or

-3- J-A06022-19

vague. Id. at 39a-44a. Appellant’s eleventh preliminary objection claimed

that Appellee failed to timely invoke the dispute resolution procedure set forth

in the contract between Appellee and Pittston. Id. at 44a-49a. Appellant’s

twelfth and last preliminary objection was a motion to strike Appellee’s request

for costs and counsel fees. Id. at 49a-50a. Appellant’s preliminary objections

attached five exhibits, including excerpts from a contract between Appellee

and Pittston. Id. at 27a, 82a. In sum, all of Appellant’s preliminary objections

at issue were based on the contract between Appellee and Pittston.

Appellee filed preliminary objections to Appellant’s preliminary

objections. Id. at 80a. Appellee sought to strike four of Appellant’s

preliminary objections as “impermissible ‘speaking demurrers.’”4 Id. at 83a.

The trial court overruled Appellee’s preliminary objections to Appellant’s

preliminary objections and ordered Appellee to file a response to Appellant’s

preliminary objections. Id. at 145a.

4 This Court defined “speaking demurrer” as follows:

A “speaking demurrer” is defined as “one which, in order to sustain itself, requires the aid of a fact not appearing on the face of the pleading objected to, or, in other words, which alleges or assumes the existence of a fact not already pleaded, and which constitutes the ground of objection and is condemned both by the common law and the code system of pleading.” A “speaking demurrer” cannot be considered in sustaining a preliminary objection.

Regal Indus. Corp. v. Crum & Forster, Inc., 890 A.2d 395, 398 (Pa. Super. 2005) (citation omitted).

-4- J-A06022-19

On January 24, 2017, the trial court sustained in part and overruled in

part Appellant’s preliminary objections as follows.

(a) [Appellant’s] Preliminary Objections I, II, and III (Demurrer pursuant to Pa. R.C.P. 1028(a)(4) are OVERRULED and DENIED See 68 P.S. ¶ 491, Restatement (Second) of Torts ¶ 552, and Bilt-Rite Contractors, Inc. v. Architectural Studio[,] 866 A.2d 270 (Pa. 2005));

(b) [Appellant’s] Preliminary Objections IV and V are OVERRULED and DENIED. SEE [sic] Bilt-Rite Contractors, Inc. (supra).

(c) [Appellant’s] Preliminary Objections VI, VII, VIII, IX and X are GRANTED and SUSTAINED and paragraphs 43, 46, 53, 54, 56, 58, 60, 61, 62, 63, 64, 72, and 76 are STRICKEN;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bilt-Rite Contractors, Inc. v. Architectural Studio
866 A.2d 270 (Supreme Court of Pennsylvania, 2005)
Regal Industrial Corp. v. Crum & Forster, Inc.
890 A.2d 395 (Superior Court of Pennsylvania, 2005)
Hall v. Goodman Co.
456 A.2d 1029 (Superior Court of Pennsylvania, 1983)
Prieto Corp. v. Gambone Construction Co.
100 A.3d 602 (Superior Court of Pennsylvania, 2014)
Khawaja, H. v. Re/Max Central
151 A.3d 626 (Superior Court of Pennsylvania, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Popple Construction, Inc. v. Reilly Assoc., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/popple-construction-inc-v-reilly-assoc-inc-pasuperct-2019.