Pomeranz v. McDonald's Corp.

821 P.2d 843, 1991 WL 85456
CourtColorado Court of Appeals
DecidedJanuary 6, 1992
Docket89CA2086
StatusPublished
Cited by5 cases

This text of 821 P.2d 843 (Pomeranz v. McDonald's Corp.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pomeranz v. McDonald's Corp., 821 P.2d 843, 1991 WL 85456 (Colo. Ct. App. 1992).

Opinion

Opinion by

Judge JONES.

Defendant, McDonald’s Corporation, appeals from a judgment entered by the trial court holding that it improperly terminated its lease with plaintiffs, the co-owners of the subject premises. Plaintiffs cross-appeal the portion of the trial court’s judgment reducing plaintiffs’ award by the present value of the reasonable rental value of the premises. We affirm the portion *845 of the judgment holding that McDonald’s improperly terminated the lease but reverse as to the amount of damages awarded.

Plaintiffs own a shopping center in Grand Junction, Colorado. On January 16, 1963, plaintiffs’ predecessor in interest and McDonald’s entered into a lease for a retail location in the shopping center.

In May 1974, the parties amended the lease to require that McDonald’s pay rent, taxes, insurance, and all maintenance costs.

As early as 1973, McDonald’s had been advised by the Colorado Department of Health that uranium mill tailings were present on the leased premises. However, both in 1973 and in 1980, the health department advised McDonald’s that there was “no reason for undue concern ... about the radiation levels.”

In February 1984, the Department of Energy (DOE) notified McDonald’s that the property was sufficiently contaminated that it would eventually require remedial action.

After an unsuccessful attempt to negotiate an extension of the lease term, McDonald’s, in February 1986, ceased operation at the leased premises, moved to a different location, and retained a real estate broker to help locate a subtenant. It is undisputed that McDonald’s vacated the premises because it was unable to renegotiate a longer term lease and not because of the mill tailings on the property.

On May 23, 1986, DOE contacted plaintiffs and advised them that extensive excavation would be necessary to remove the tailings. Plaintiffs were further advised that the work could be accomplished at the government’s expense if plaintiffs would agree to participate in the remedial action plan.

On June 5, 1986, plaintiffs signed an agreement to have the removal work performed. Later that month, they forwarded a copy of the removal plan to McDonald’s which had vacated the premises at that time, but was still subject to the lease. McDonald’s consented to the removal program but, m so doing, expressly reserved all of its rights under the lease.

Subsequently, a real estate agent retained by McDonald’s for the purpose of finding a subtenant for the property, informed McDonald’s that, in his opinion, the property could not be subleased until the removal work had been completed.

In September 1986, McDonald’s notified plaintiffs that it would cease making payments pursuant to the lease provision titled “Damage to or Destruction of Improvements” which provides as follows:

“If the building on said premises shall be rendered untenantable by fire or other casualty, the Lessor will, within ninety (90) days from the date of said damage or destruction, repair or replace said building so that Lessee may continue in occupancy. It is further agreed, however, that the rent herein required to be paid shall abate during said period of untenantability. It is further agreed that if said building cannot be replaced or repaired in ninety (90) days due to the inability of the Lessor to obtain materials and labor needed therefor, any strikes, or acts of God, or governmental restrictions that would prohibit, limit or delay said construction, then the time for completion of such repair or replacement shall be extended accordingly, provided, however, that, in any event, if the repair or replacement of the building has not been completed within a period of six months from the date of said damage or destruction, Lessee may at its option terminate this lease.”

Plaintiffs gave McDonald’s written notice of default by letter dated October 10, 1986. McDonald’s responded with a letter on October 28, 1986, stating that it considered the lease terminated pursuant to the above provision.

Excavation work began on November 28, 1986, and was completed on April 10, 1987, a period of four months and thirteen days.

Plaintiffs filed a complaint against McDonald’s alleging that it had breached the lease in failing to pay rent and expenses and in failing to maintain the premises, after September 1986.

*846 At the conclusion of a trial to the court in October 1988, the court determined that McDonald’s “did not validly terminate the lease [because] the premises were not un-tenantable for more than six months” and because “the definition of casualty ... [could not] be construed to include the uranium mill tailings found on the property.” The court also concluded, however, that plaintiffs had failed to mitigate damages from November 1986 to August 1988.

On December 22, 1988, the trial court issued amended findings in which it determined that plaintiffs had taken reasonable steps to mitigate damages. On October 31, 1989, judgment was entered against McDonald’s in the amount of $130,856, an amount which, in spite of the court’s latest findings, still reflected a reduction for plaintiffs’ failure to mitigate damages.

I.

McDonald’s first contends that the trial court erred in finding that it improperly terminated the lease. We disagree.

“Untenantability” has been defined as a condition characterized by:

“damage of such a nature that the premises cannot be used for the purpose for which they were rented and cannot be restored to a fit condition by ordinary repairs made without unreasonable interruption of the tenant’s use.” 1 M. Friedman, Friedman on Leases 500 (3d ed. 1990).

The question of whether premises have been rendered “untenantable” is an issue of fact for the trier of fact, here, the trial court. Presbyterian Distribution Service v. Chicago National Bank, 28 Ill.App.2d 147, 171 N.E.2d 86 (1960). And continued occupancy coupled with the carrying on of business may provide proof of tenantability. See Franzo & Resciniti, Inc. v. Duva, 4 Misc.2d 984, 159 N.Y.S.2d 425 (1956).

Here, after McDonald’s was first notified that the mill tailings were contaminated, it continued to operate its restaurant on the premises for some twenty-three months. Moreover, when McDonald’s ultimately decided to vacate the premises, that decision was based upon its inability to renegotiate a longer lease term and was not due to the presence of the mill tailings.

Thus, we conclude that the record contains substantial evidence to support the trial court’s finding that the premises were not untenantable prior to the removal work.

McDonald’s, however, asserts that under the lease, it was entitled to sublease the premises and that such entitlement was a purpose for which the lease was entered into. McDonald’s, therefore, contends that, because the impending removal work made it extremely difficult to secure a subtenant, the premises could not be used for one of its intended purposes under the lease.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
821 P.2d 843, 1991 WL 85456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pomeranz-v-mcdonalds-corp-coloctapp-1992.