Police Jury of Parish of Vernon v. Johnson

35 So. 550, 111 La. 279, 1903 La. LEXIS 529
CourtSupreme Court of Louisiana
DecidedJune 22, 1903
DocketNo. 14,816
StatusPublished
Cited by13 cases

This text of 35 So. 550 (Police Jury of Parish of Vernon v. Johnson) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Police Jury of Parish of Vernon v. Johnson, 35 So. 550, 111 La. 279, 1903 La. LEXIS 529 (La. 1903).

Opinion

BREAUX, J.

Plaintiff seeks to recover the sum of $5,000 from the defendant, as surety on a builder’s bond executed by the builder in favor of plaintiff, for security of the due performance of the contract.

The charge of plaintiff is that the conditions of the bond were broken, because the builder erected plaintiff’s courthouse of bad materials and in an unworkmanlike manner; that he did not follow the specifications. The defendant interposed by way of exceptions the pleas of nonjoinder, no cause of action, and filed- an answer on the merits denying all liability.

The plea of nonjoinder grows out of the fact that plaintiff made the surety only party defendant, and did not sue the principal on the bond.

The plea of no cause of action seems to be mainly grounded on the plea of estoppel which this defendant sets up, and which was referred- to the merits.

The record discloses that plaintiff’s courthouse ivas finished, delivered, and that defendant had paid the price, about two years [281]*281before the suit was brought. The work was performed under the directions of an architect selected by plaintiff, in accordance with the conditions of the contract.

The testimony is conflicting. It remains that, after the building had been received by plaintiff, there was serious cracking of the wall in several places, the jack arches and brickwork over square head openings had given way in some pla'ces, and were about to fall, when repairs were made by plaintiff. One of the corners of the tower had yielded, and the tower was out of plumb, and slightly twisted toward the east.

The whole trouble, an expert reported, was due to a faulty foundation. There were other defects pointed out by him—a number of them.

The work was performed in the presence of the parish officers, who were chafged with the same authority in the premises, and executed with the approval of the architect.

The contract contains an article numbered 16, which we will copy in extenso, because it has direct bearing upon the issues of the ■case, viz.:

“That the contractor shall at any time when required by the supervising architect, within one year- from and after the completion and acceptance of the work herein contracted,'make good any and all latent defects not discernible at the final examination and occupation thereof; such as evidence of the use of improper materials or labor in any branch of the work, causing the same to be imperfect and defective in construction or finish, and if such defects are not promptly made good when ordered by the supervising architect, he shall have the right to employ ■other parties to execute his orders, and charge the cost of same to the second party.”

The last payment under the contract was to be made on the entire work when it had been entirely completed and accepted.

We have seen that the work had been entirely completed and accepted. From the fact that the committee representing plaintiff and the plaintiff accepted the building, we infer that there were no patent defects at the time.

The parties adopted conditions by which they are to be governed, and, whatever may be the right remaining as between the principal and plaintiff, the surety is not bound further than expressed in the contract. A surety is not bound for objects not in contemplation of the parties when the contract was signed. In case of defects, he held himself bound that they would repair, or that he could be held therefor. That was the extent of his liability, so far as the necessity for repair arose from the use of bad materials or labor.

It is true that the contract in question provides that payments shall not be considered as an acceptance of the “work executed, or a waiver of any rights or claims of the parties of the first part.”

Is not this clause to be construed so as to protect the surety to the extent stated in the clause—within the 12 months, as stipulated by article 16? This clause further stipulates that no payment or acceptance was to do away with the right set forth in the article, in so far as the plaintiff was concerned.

The decision to which our attention is invited by learned counsel did not have to interpret the meaning of an article in the contract, such as article 16 of the contract before us for interpretation, and for that reason it was held that acceptance, when the owner could not do otherwise, did not bar him from recovering damages for defective work.

Here the parties laid down to some extent their own conditions, and allowed the time to elapse without making the least claim; and, furthermore, they limited the time, by article 16 of the contract, within which plaintiff was to find the latent defects for which the contractor and builder was to be held liable. They have to some extent, at least, changed the legal to a conventional liability, of which, at least, the surety can avail himself to the extent that the defective work is covered by the language of article 16.

It does not occur to us that the article before cited covers all the defects. There are vices of construction that may not be included within its grasp, if the vice does not arise from bad material or labor mentioned in the article.

There are vices of construction to which the articles (2762 and 3545, Civ. Code) cited by plaintiff have application.

It would be difficult in this case to determine with satisfactory certainty the extent the damages claimed may be due to bad material (for which, under no circumstances, the surety can be held) or to the vice of construe[283]*283tion. The testimony has not pointed out a clear line or separation between the two. There is testimony going to prove that there was bad material used, which defendant sought to meet with counter testimony. There is testimony going to prove that there was vice in the construction. We have already said, as relates to the materials, we think that they are covered by article 16 of the contract.

With reference to the asserted vice of construction, there is testimony to the effect that whatever defect there was in this was due to defectiveness of the plans and specifications prepared by the architect An architect of great experience testified that the plans and specifications were defective, that the foundation as laid down in these plans and specifications was not sufficient for the building, and that the footings of the wall were not broad enough.

Furthermore, the work was done in the presence of, and consented to by, the architect and, part of the time, the president of the police jury, and the building committee gave it their attention.

Returning to the law upon the subject, we find authority, not binding, it is true, but, in considering these articles, containing far-reaching conditions, that the interpretation of their meaning should be restrictive. 4 Fuzier-Hermann, p. 427, No. 1.

Under the resfrie” ve interpretation, the surety of the contractor, when the contractor has followed the direction of the architect and others concerned, can scarcely be held, under the cited article, about two years after the work has been accepted.

The language of these two cited articles does not bring this case within their terms. They are to be construed together, and not, in case “the building should fall to ruin either in whole or in part on account of the badness of the workmanship,” that the architect or contractor shall bear the loss. Civ. Code, art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Guste v. Simoni, Heck & Associates
314 So. 2d 477 (Louisiana Court of Appeal, 1975)
Orleans Parish School Board v. Pittman Construction Co.
260 So. 2d 661 (Supreme Court of Louisiana, 1972)
Orleans Parish School Board v. Pittman Construction Co.
244 So. 2d 641 (Louisiana Court of Appeal, 1971)
Hooter v. Farrar
116 So. 2d 723 (Louisiana Court of Appeal, 1959)
Hunter v. Mayfield
106 So. 2d 330 (Louisiana Court of Appeal, 1958)
Breaux v. Laird
88 So. 2d 33 (Supreme Court of Louisiana, 1956)
Michel v. Efferson
65 So. 2d 115 (Supreme Court of Louisiana, 1953)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
Barraque v. Neff
11 So. 2d 697 (Supreme Court of Louisiana, 1942)
Di Franco v. Ascani
127 So. 76 (Louisiana Court of Appeal, 1930)
Matthews v. Rudy
4 La. App. 226 (Louisiana Court of Appeal, 1926)
Harry Borrosky v. Hill, Harris & Co.
1 La. App. 431 (Louisiana Court of Appeal, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
35 So. 550, 111 La. 279, 1903 La. LEXIS 529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/police-jury-of-parish-of-vernon-v-johnson-la-1903.