Point Ruston Llc, V. Igor Kunitsa And Lyudmila Kunitsa

CourtCourt of Appeals of Washington
DecidedJanuary 23, 2024
Docket57577-9
StatusUnpublished

This text of Point Ruston Llc, V. Igor Kunitsa And Lyudmila Kunitsa (Point Ruston Llc, V. Igor Kunitsa And Lyudmila Kunitsa) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Point Ruston Llc, V. Igor Kunitsa And Lyudmila Kunitsa, (Wash. Ct. App. 2024).

Opinion

Filed Washington State Court of Appeals Division Two

January 23, 2024

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II POINT RUSTON, LLC; POINT RUSTON No. 57577-9-II PHASE II, LLC; CENTURY CONDOMINIUMS, LLC; COPPERLINE CONDOMINIUM, LLC; and MC REAL ESTATE CONSULTANTS, LLC,

Appellants,

v. UNPUBLISHED OPINION

IGOR KUNITSA, an individual; LYUDMILA KUNITSA, an individual; and the marital community comprised of IGOR KUNITSA and LYUDMILA KUNITSA,

Respondents.

MAXA, J. – Point Ruston, LLC (PR); Point Ruston Phase II, LLC (PR Phase II); Century

Condominiums, LLC (Century); Copperline Condominiums, LLC (Copperline); and MC Real

Estate Consultants, LLC (MC Construction1) (collectively, the Point Ruston companies) appeal

the trial court’s grant of summary judgment in favor of Igor and Lyudmila Kunitsa in the Point

Ruston companies’ lawsuit against them regarding their company’s work on the Point Ruston

real estate development project (Project). The Point Ruston companies also appeal the trial

1 MC Construction is the trade name for MC Real Estate Consultants, LLC. On appeal, they refer to themselves as MC Construction, and so we will refer to them as such. No. 57577-9-II

court’s submission of additional claims to arbitration. Only MC Construction seeks relief on

appeal.

The Point Ruston companies are related entities involved with the Project. The late

Michael Cohen was the manager of the Project. The Kunitsas are owners and employees of

Serpanok Construction, Inc. (Serpanok), a concrete construction company. PR Phase II

subcontracted with Serpanok to perform extensive work on two parts of the Project: Building 1A

and the parking garage. Century later became the party in interest on the Building 1A contract.

After Century and PR Phase II failed to pay for the work, Serpanok sued PR, PR Phase II, and

Century for breach of contract. PR, PR Phase II, and Century asserted counterclaims, alleging

that Serpanok committed fraud and participated in a “kickback” scheme with Larry Hutchinson,

the former construction manager of the Project. Hutchinson was employed by MC Construction.

Pursuant to an arbitration clause in the subcontracts, the case was submitted to

arbitration. The arbitrator ruled in favor of Serpanok on most of its claims, but also ruled that

Serpanok caused Hutchinson to breach his fiduciary duty to PR, PR Phase II, and Century. The

trial court confirmed the arbitration award.

While the arbitration was pending, the Point Ruston companies filed a separate lawsuit

against the Kunitsas in their individual capacities. The Point Ruston companies asserted nearly

identical claims regarding the Building 1A and parking garage subcontracts as the counterclaims

PR, PR Phase II, and Century asserted in the Serpanok lawsuit, including aiding and abetting a

breach of fiduciary duty and participating in common law fraud. The Point Ruston companies

also asserted claims under other subcontracts. The trial court granted summary judgment in

favor of the Kunitsas on the claims regarding the Building 1A and parking garage subcontracts

2 No. 57577-9-II

based on res judicata and collateral estoppel. The court stayed and transferred the remaining

claims to arbitration. But when the arbitration was terminated because the Point Ruston

companies failed to pay the arbitration fees, the trial court dismissed the remaining claims.

We hold that (1) res judicata bars MC Construction’s claims against the Kunitsas

regarding the Building 1A and parking garage subcontracts because MC Construction was in

privity with PR, PR Phase II, and Century; (2) MC Construction is so closely related to the other

Point Ruston entities that it was proper to compel them to arbitrate their remaining claims even

though MC Construction was not a party to the Serpanok subcontracts; and (3) MC Construction

provides no argument why the trial court erred in dismissing the remaining claims.

Accordingly, we affirm the trial court’s grant of summary judgment in favor of the

Kunitsas regarding the Building 1A and parking garage claims, the trial court’s order referring

MC Construction’s remaining claims to arbitration, and the trial court’s dismissal of the

remaining claims.

FACTS

Background

The Point Ruston companies are entities involved with the Project. The Project includes

condominiums, apartments, retail stores, businesses, restaurants, a movie theater, and parking

facilities. Cohen was the manager of the Project. The Kunitsas are owners and employees of

Serpanok, a concrete company, and they acted on behalf of Serpanok.

In 2014, PR Phase II entered into subcontracts with Serpanok to perform work on two

parts of the Project: Building 1A and the parking garage. Both of the subcontracts contained an

3 No. 57577-9-II

arbitration clause. The clause provided that if disputes relating to the subcontract arose, the

parties must resolve the dispute in arbitration.

After Serpanok started work on Building 1A, PR Phase II transferred title of the building

to Century. Serpanok substantially completed its work on Building 1A in November 2015. At

that time, Century owed Serpanok over $850,000, plus interest, for its work on Building 1A. In

addition, PR Phase II owed Serpanok over $2.2 million for its work on the parking garage.

Serpanok filed suit against PR, PR Phase II, Century, and Cohen. Serpanok asserted

several claims, including breach of contract, tortious conversion of some of Serpanok’s

equipment by PR Phase II and Cohen, enforcement of a mechanics lien on Building 1A, and a

claim on promissory notes PR executed related to Building 1A and the parking garage.

PR, PR Phase II, Century, and Cohen asserted counterclaims alleging that Serpanok

perpetuated a fraud with Hutchinson, the former construction manager for the Project. They

claimed that Serpanok made secret payments to Hutchinson in exchange for approving false

invoices, favorable contract terms, and unwarranted change orders to benefit Serpanok and to the

detriment of their companies. They argued that they relied on the fraud and suffered damages.

Finally, they alleged that Serpanok aided and abetted Hutchinson’s breaches of fiduciary duties

owed to them, tortuously interfered with their business expectancy, and violated the Securities

Act of Washington (SAW), chapter 21.20 RCW, by entering into the promissory notes for

Building 1A and the parking garage without prior disclosure of the fraud. In the alternative, PR,

PR Phase II, Century, and Cohen argued that Serpanok breached the subcontracts at issue.

4 No. 57577-9-II

The parties litigated the validity of the arbitration clauses and the arbitrability of their

claims before the trial court. The trial court ruled that the arbitration clauses were valid and that

all of Serpanok’s claims were arbitrable.

Brewer Arbitration

In March 2019, the parties selected Thomas Brewer to serve as their arbitrator. After the

preliminary arbitration hearing, Serpanok argued that MC Construction and Copperline, along

with other related nonparties, should not be able to assert claims or counterclaims in the

arbitration. Brewer stated in his arbitration award that no claims or counterclaims by nonparties,

including MC Construction and Copperline, had been asserted in the arbitration.

In June 2019, PR, PR Phase II, Century, and Cohen moved in the trial court to allow

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King County v. Central Puget Sound
14 P.3d 133 (Washington Supreme Court, 2000)
Ensley v. Pitcher
222 P.3d 99 (Court of Appeals of Washington, 2009)
SPOKANE RESEARCH FUND v. City of Spokane
117 P.3d 1117 (Washington Supreme Court, 2005)
Feature Realty, Inc. v. KIRKPATRICK & LOCKHART PRESTON GATES ELLIS
164 P.3d 500 (Washington Supreme Court, 2007)
Jennifer Wiese, Resps. v. Square Two Financial Corp., App.
189 Wash. App. 466 (Court of Appeals of Washington, 2015)
Stephen Kerr Eugster v. Washington State Bar Association
397 P.3d 131 (Court of Appeals of Washington, 2017)
Lawrence Shandola v. Paula Henry
396 P.3d 395 (Court of Appeals of Washington, 2017)
Raven Offshore Yacht Shipping, Llc & Richard Gladych v. F.t. Holdings, Llc.
199 Wash. App. 534 (Court of Appeals of Washington, 2017)
Afoa v. Port of Seattle
421 P.3d 903 (Washington Supreme Court, 2018)
Weaver v. City of Everett
450 P.3d 177 (Washington Supreme Court, 2019)
King County v. Central Puget Sound Growth Management Hearings Board
142 Wash. 2d 543 (Washington Supreme Court, 2000)
Spokane Research & Defense Fund v. City of Spokane
117 P.3d 1117 (Washington Supreme Court, 2005)
Feature Realty, Inc. v. Kirkpatrick & Lockhart Preston Gates Ellis, LLP
161 Wash. 2d 214 (Washington Supreme Court, 2007)
In re Recall of Fortney
503 P.3d 556 (Washington Supreme Court, 2022)
Virgil J. Mihaila, V. Ronald E. Troth
505 P.3d 163 (Court of Appeals of Washington, 2022)
East Fork Hills Rural Ass'n v. Clark County
965 P.2d 650 (Court of Appeals of Washington, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Point Ruston Llc, V. Igor Kunitsa And Lyudmila Kunitsa, Counsel Stack Legal Research, https://law.counselstack.com/opinion/point-ruston-llc-v-igor-kunitsa-and-lyudmila-kunitsa-washctapp-2024.