Point Contracting, LLC v. Urban Investment Research Corp. and West Roswell NM, LLC

CourtDistrict Court, D. New Mexico
DecidedMarch 31, 2026
Docket2:24-cv-00562
StatusUnknown

This text of Point Contracting, LLC v. Urban Investment Research Corp. and West Roswell NM, LLC (Point Contracting, LLC v. Urban Investment Research Corp. and West Roswell NM, LLC) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Point Contracting, LLC v. Urban Investment Research Corp. and West Roswell NM, LLC, (D.N.M. 2026).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW MEXICO

POINT CONTRACTING, LLC,

Plaintiff,

v. No. 2:24-cv-00562-SMD-KRS

URBAN INVESTMENT RESEARCH CORP. and WEST ROSWELL NM, LLC,

Defendants.

ORDER DENYING PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT THIS MATTER is before the Court on Plaintiff’s motion for summary judgment. Doc. 61 (“Pl.’s Mot. for SJ”). Defendants filed their response and Plaintiff replied. Doc. 63 (“Defs.’ Resp.”); Doc. 66 (“Pl.’s Reply”). Upon careful consideration of the record, relevant law, and the parties’ briefing, the Court DENIES Plaintiff’s motion. BACKGROUND The present dispute arises from a construction project in Roswell, New Mexico. In the spring of 2022, Defendants Urban Investment Research Corporation (“UIRC”) and West Roswell NM LLC (collectively “Defendants”) hired Point Contracting (“Plaintiff”) to perform a variety of improvements on a building the Bureau of Land Management (“BLM”) leases. Relations between the parties began to deteriorate beginning in 2023; Defendants were dissatisfied with Plaintiff’s work, Plaintiff was upset over Defendants’ failure to pay for the work it had performed, and so on. This cycle of rebuked payment requests followed by punch lists of corrections never reached a resolution. Instead, Defendants retained over $80,000, asserting that they were forced to spend more than that to correct Plaintiff’s purported shoddy work, and Plaintiff sued, alleging that Defendants breached their contract and New Mexico state law. Plaintiff filed suit on July 25, 2023, in the Fifth Judicial District Court, County of Chaves, State of New Mexico. Doc. 1, Ex. 2 at 3. Plaintiff asserts four claims—breach of the New Mexico Prompt Payment Act, breach of contract as to the tenant improvement (“TI”) Project, breach of contract as to the shell project, and failure to uphold the implied covenant of good faith and fair dealing. Id. at 7–8. Defendants removed the case to federal court and counterclaimed for breach

of contract, alleging that Plaintiff “walked off the project without completing all of the many defective and incomplete construction work set forth in the GSA’s final punch list.” Doc. 1; Doc. 17 ¶ 7. The parties proceeded through discovery. Plaintiff now moves for summary judgment on the New Mexico Prompt Payment Act Claim, Defendants’ counterclaim, and the breach of contract claims. See Pl.’s Mot. for SJ at 16, 18, and 23. STATEMENT OF MATERIAL FACTS I. The Contract Defendant West Roswell owns 2909 W. 2nd Street, Roswell, NM 88201 (the “Space”). Pl.’s Mot. for SJ ¶¶ 1, 7. The United States General Services Administration (“GSA”) leases the

Space for the United States Bureau of Land Management’s (“BLM’s”) use. Id. ¶ 3. Defendants hired Plaintiff to perform construction services on the Space. Id. ¶¶ 3–4. On April 7, 2022, the parties executed two work agreements (the “Contracts”), memorializing their contractual obligations and defining Plaintiff’s scope of work. Id. ¶ 7. One contract was for shell improvements—installing door hardware, adding insulation, updating the plumbing space, and performing electrical work—and one contract was for TI—adding security features, fire suppression, and updating the lighting. Id. ¶ 5. Under the Contracts, the Owner must pay Plaintiff the fixed amount specified in the attached “Description of Work.” Doc. 61, Ex. 2 at 92. The fixed amount for the shell improvements was $1,666,566.46 and the fixed amount for the tenant improvements was $1,837,189.34. Id. at 14, 24. The terms and conditions section specify that Defendants must pay Plaintiff undisputed amounts within 30 days of receiving an invoice, but may “withhold amounts that Owner disputes are payable, pending resolution of the dispute.” Id. at 10. The Contracts further provide that Plaintiff may continue performing corrections for up to “one year after completion of the Work.” Pl.’s Mot. for SJ ¶ 14; Doc. 61, Ex. 2 at 4. The Contracts

do not define “completion.” However, the attached Schedule of Work lists the “final milestone” as “Substantial Completion/Acceptance.” Pl.’s Mot. for SJ ¶ 11; Doc. 61, Ex. 2 at 9; Defs.’ Resp. ¶ D. Work that is performed after completion is called “warranty work.” Doc. 61, Ex. 1 (“Warden Dep.”) 110:15–112:1. If the owner notifies the contractor of a defect and the contractor must repair its work within five days of receiving notice. Doc. 61, Ex. 2 at 11. If the contractor fails to do so, the Owner has the right to “arrange for another contractor to perform the repair, and the Contractor shall pay amounts due to the separate contractor.” Id. The parties also attached the lease agreement between GSA and Defendants. The lease states that the Government “shall accept the space only if the building shell and TI conforming to

this lease and the approved [design intent drawings (“DIDs”)], if applicable, is substantially complete.” Doc. 63, Ex. 1 at 29. The Space is substantially completed “only if the Space may be used for its intended purpose, and completion of remaining work will not interfere with the Government’s enjoyment of the Space.” Id. at 30. Once the Government accepts the Space, that acceptance is “final and binding . . . with respect to conformance of the completed TIs to the approved DIDs with the exception of items identified on a punch list generated as a result of the inspection[.]” Id. II. The Project Plaintiff began working on the project in spring of 2022. In January of 2023, GSA performed an inspection and provided Plaintiff with a punch list of items that needed to be completed. Pl.’s Mot. for SJ ¶ 17. GSA completed a second inspection on February 22, 2023, and sent another punch list to Plaintiff. Id. ¶ 18. Plaintiff claims that it completed both punch lists.

Id. ¶¶ 17–18. Defendants assert that Plaintiff failed to complete work from either punch list and that “Plaintiff was not even present in New Mexico” in February or March of 2023. Defs.’ Resp. ¶ 18. On February 28, 2023, five days after receiving the second GSA punch list, Nicole Brown, Plaintiff’s operations manager, sent Joe Vadenbrink, Defendant UIRC’s project manager, a final invoice for $145,972.27 (“Draw 7”).1 Id. ¶ 19; Defs.’ Resp. ¶¶ 19, O. The invoice states that it is for all services related to the Shell and TI Final, with $10,000 reserved for warranty work. Doc. 61, Ex. 2 at 101. Kevin Ellis, general manager at Point Contracting, confirmed that the February 28th invoice sought “full payout,” meaning a “hundred percent of the change orders and contract

amounts.” Doc 61, Ex. 4 (“Second Ellis Dep.”) 193:7–13. On March 1, 2023, Vandenbrink emailed Plaintiff with a list of incomplete items from the January inspection. Defs.’ Resp. ¶ 21. On March 3, 2023, Bryan Crot, senior project manager at GSA, sent an updated version of the February punch list. Id. The email noted that for Phase 1 acceptance Plaintiff needed to address the sewer odor in the engine bay, the exhaust fans in the shower areas not turning on, and missing electrical drops in the office area. Pl.’s Mot. for SJ ¶ 26;

1 The exhibits attached to Plaintiff’s motions include two invoices—one for the TI work ($64,226.39) and one for the Shell Work ($145,972,27)—which total $210.198.66. Doc. 61, Ex, 2 at 101–02. Both are dated February 28, 2023. Id. It appears that Brown sent both invoices to Vandenbrink, but is unclear why Plaintiff only refers to the shell final in its UMF. Doc. 63, Ex. 6 at 2. The attached inspection report identified itself as a “progress inspection” and noted that “additional inspections” were required. Id. On April 7, 2023, Vandenbrink emailed a few individuals from GSA about the status of the project. Vandenbrink attached a list of items that needed to be completed “to reach a level of completion agreed to by all parties and to be inspected on 4/19/2023 and 04/20/2023 by BLM and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reed v. Bennett
312 F.3d 1190 (Tenth Circuit, 2002)
Serna v. Colorado Department of Corrections
455 F.3d 1146 (Tenth Circuit, 2006)
Miller v. New Mexico Department of Transportation
741 P.2d 1374 (New Mexico Supreme Court, 1987)
Continental Potash, Inc. v. Freeport-McMoran, Inc.
858 P.2d 66 (New Mexico Supreme Court, 1993)
Jaynes v. Strong-Thorne Mortuary, Inc.
1998 NMSC 004 (New Mexico Supreme Court, 1997)
Crow v. Capitol Bankers Life Insurance
891 P.2d 1206 (New Mexico Supreme Court, 1995)
Kreischer v. Armijo
884 P.2d 827 (New Mexico Court of Appeals, 1994)
Paiz v. State Farm Fire & Casualty Co.
880 P.2d 300 (New Mexico Supreme Court, 1994)
J.R. Hale Contracting Co. v. Union Pacific Railroad
2008 NMCA 037 (New Mexico Court of Appeals, 2007)
State v. Baca
2005 NMCA 001 (New Mexico Court of Appeals, 2004)
Ballou v. Walker
2017 MT 197 (Montana Supreme Court, 2017)
State v. Adams
2022 NMSC 008 (New Mexico Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Point Contracting, LLC v. Urban Investment Research Corp. and West Roswell NM, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/point-contracting-llc-v-urban-investment-research-corp-and-west-roswell-nmd-2026.