Plum Bayou Levee District v. Pocket Cypress Drainage District No. 1

265 S.W. 87, 165 Ark. 576, 1924 Ark. LEXIS 547
Supreme Court of Arkansas·Decided October 20, 1924·Published·Cited by 1 cases

Opinion

McCulloch, C. J.

Under authority of a special statute enacted by the General Assembly in' the year 1905, Plum Bayou Levee District, created by that statute, constructed a levee along the east bank of the Arkansas River in Pulaski, Lonoke and Jefferson counties, to protect the adjacent lands from flood waters of the river. The levee begins at a point near Old River, in Pulaski County, and extends southeasterly along the bank of the river for a distance of about forty-three miles, ending at a point south of Rob Roy, and it protects an area of about 377,000 acres, the levee being maintained by the district.

The General Assembly of 1923 enacted a statute (Special Acts 1923, p. 1745) creating a drainage district known as Pocket Cypress Drainage District No. 1 of Pulaski and Jefferson counties, and it embraced an area of about 12,000 acres within the boundaries of the levee district for the purpose of draining that area. A section of the statute creating the drainage district reads as follows:

‘ ‘ Section 12. The commissioners are hereby granted the privilegie to pass through Plum Bayou at a point near the mile-post between miles 18 and 19, in section three (3), township three (3) south, range ten (10) west, Jefferson County. However, all plans, specifications and installation of the necessary floodgates to be installed through said levee shall be approved by the chief engineer of the Plum Bayou Levee District. ”

Plans and surveys were made by the drainage district, at considerable cost, to carry out the work of constructing the drainage canal or ditch, and also plans and specifications were made by the engineer of the drainage district for passing the drainage canal through the levee at the point designated in the statute and for the installation of neeessary floodgates. These plans were presented to the chief engineer of the levee district, who. declined to approve them, and this action was instituted in the chancery court by the drainage district against the levee district to obtain a mandatory injunction compelling the levee district to permit the passage of the ditch through the levee, and to enjoin the levee district from interfering with the prosecution of that work. ' An answer was filed by the levee district alleging that the plans and specifications for the passage of the drainage ditch through the levee and the installation of floodgates were inadequate to protect the levee, and that the engineer of the levee district had properly declined to approve them. The answer also attacked the validity of the statute creating the drainage district on the ground that it was an attempt to take property without compensation and without due process of law.

There was a trial before the chancery court on oral testimony of the respective engineers for the two districts, and other engineers, and also upon all of the maps showing the character of the area and the proposed plans and specifications for the work of passing the ditch through the levee and installing the floodgates. There were several sittings of the court and examinations and reexaminations of the engineers. In the beginning of the trial there were many points of difference between the opinions of the several engineers, but these differences were, to a considerable extent, eliminated .as the trial progressed, and there was an exchange of views as to the plans for this work. The issues of fact finally settled down to the question as to the place for cutting through the levee and the proper safeguards to be adopted for temporarily protecting the levee while the work of constructing a floodgate .and spillway was in progress. The main contention of the levee district and its engineer was that the point designated in the statute was not an appropriate one, for the reason that there was danger of the levee caving at that place on .account of the encroachment of the river. The chancery court rendered a decree granting the relief prayed for by the drainage district.

The appeal to this court was not perfected for nearly six months after the rendition of the decree, and the appellee moved to dismiss on the ground that the statute creating the drainage district provides that, in all cases “involving the validity of this district, or the assessments of benefits, and all suits to foreclose the lien of taxes, *** all appeals therefrom must be taken and perfected within thirty days. ’ ’ Appellant has abandoned the attack on the validity of the statute by failing to insist upon it here, and that strips the case of any of the characteristics which are embraced within the statute which shortens the time for appeal. The case, as it now stands, does not involve the validity of the district, or the assessments of benefits, and it is not a suit to foreclose the lien for taxes, hence the appeal may be prosecuted within the time specified by the general statute fixing six months as the time for appeal to this court. Davis v. Cook, 155 Ark. 613.

Free access — add to your briefcase to read the full text and ask questions with AI

Plum Bayou Levee District v. Pocket Cypress Drainage District No. 1, 265 S.W. 87, 165 Ark. 576, 1924 Ark. LEXIS 547 (Ark. 1924).

265 S.W. 87 (Plum Bayou Levee District v. Pocket Cypress Drainage District No. 1) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mashburn v. North Arkansas Highway Improvement District No. 3
266 S.W. 964 (Supreme Court of Arkansas, 1924)