Place St. Charles, a Louisiana Partnership v. J.A. Jones Construction Co.

823 F.2d 120
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 26, 1987
Docket86-3842
StatusPublished
Cited by13 cases

This text of 823 F.2d 120 (Place St. Charles, a Louisiana Partnership v. J.A. Jones Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Place St. Charles, a Louisiana Partnership v. J.A. Jones Construction Co., 823 F.2d 120 (5th Cir. 1987).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

Place St. Charles appeals the grant of J.A. Jones Construction Co.’s motion to stay pending arbitration and the corresponding denial of Place St. Charles’s motion for an injunction against arbitration. Place St. Charles also appeals the denial of its motion to transfer to another district court. We affirm.

I

In October 1982, Place St. Charles, a Louisiana partnership, contracted with Jones Construction, a North Carolina general contractor, for the construction of the Place St. Charles Building. There were many disputes during construction. When the parties were unable to resolve their differences, Place St. Charles sued Jones Construction, seeking damages for delay and defective construction. Jones Construction moved to stay the suit and to compel Place St. Charles to arbitrate pursuant to the arbitration provision in the contract. The district court granted the stay without an evidentiary hearing.

Place St. Charles, wary of the stay order’s appealability, petitioned for leave to appeal under 28 U.S.C. § 1292(b). A panel of this Court, noting that Place St. Charles could appeal the district court’s order as a matter of right under 28 U.S.C. § 1291, treated Place St. Charles’s petition as a notice of appeal and transmitted it to the district court.

*122 II

Place St. Charles argues that there was no agreement to arbitrate this dispute; that the language of the contract does not support the order to arbitrate. Place St. Charles contends that the arbitration clause did not permit Jones Construction to compel Place St. Charles to arbitrate, but only provided a mechanism in the event both parties agreed to arbitrate. To the extent the arbitration agreement clause did constitute a binding agreement, Place St. Charles argues it was only an agreement to arbitrate pre-“substantial completion” disputes. In addition, because the provision does not provide for arbitration for “all disputes,” Place St. Charles argues the provision is not entitled to a presumption of arbitration. Finally, Place St. Charles contends that the parties did not provide for judicial enforcement of arbitration awards and that, accordingly, the arbitration clause is unenforceable or at least provided for only pre-completion disputes. We first set out the relevant provisions of the contract and then treat in turn Place St. Charles’s contentions.

A '

While the “contract” consists of several “Contract Documents,” including the Construction Contract, the General Conditions of the Contract, and Plans and Specifications, three provisions shape the issues here.

General Condition 7, entitled “Disputes,” provides in part:

7.1 Differences between the parties to the Contract as to the interpretation, application or administration of this Contract or any failure to agree where agreement between the parties is called for, herein collectively called disputes, which are not resolved in the first instance by decision of the Architect where applicable, shall be settled in accordance with the requirements of this General Condition.
7.6 In the event of a dispute or difference between Owner and Contractor, which Owner’s Contractor and Owner’s Architect cannot effectively satisfy, Owner or Contractor may invoke arbitration, and each agrees to be bound by the result of said arbitration. To invoke arbitration, either party shall notify the other, in writing, setting forth:
(a) The issue to be arbitrated; and
(b) That arbitration is demanded]; and
(c) Name the person who shall serve as the arbitrator on behalf of that party demanding arbitration.
It shall be the obligation of the other party within five (5) working days after receipt of this notice, to name its arbitrator, and the two arbitrators so named shall, within ten (10) days after the naming of the second arbitrator, agree upon a third arbitrator, and the three arbitrators shall set an arbitration hearing not more than fifteen (15) days after the third arbitrator shall have been selected. The arbitrator shall have the right to call upon either party to produce papers, documents and instruments, witnesses or other information which the arbitrators, acting by a majority of them, may require, in their sole discretion, reasonably to determine the issue. After such hearing it shall be the obligation of the arbitrators, within three (3) working days to render their findings in writing, sending a copy thereof to Owner and Contractor.

Article A-5 of the Construction Contract states:

The duties and obligations imposed by the Contract Documents, and the rights and remedies available thereunder, shall be in addition to and not a limitation upon any duties, obligations, rights and remedies otherwise imposed or available by law.

Finally, General Condition 1.5(e) states that in the event of conflict, “the Construction Contract shall govern over all Contract Documents.”

Place St. Charles argues that General Condition 7, the arbitration provision, conflicts with the reservation of rights in Article A-5 of the Construction Contract, and thus General Condition 1.5(e) requires *123 that the reservation of rights govern over the arbitration provision.

Place St. Charles contends that the district court’s arbitration order pursuant to General Condition 7 violated the reservation of rights provision by limiting Place St. Charles’s available legal remedies, presumably because Place St. Charles lost its opportunity to try the case in district court. Although the case might ultimately return to the district court after arbitration, “review of arbitration awards is quite limited.” Amalgamated Meat Cutters v. Great Western Food Co., 712 F.2d 122, 124 (5th Cir.1983).

We are unpersuaded. Place St. Charles’s interpretation of General Condition 7 ignores the strong federal policy in favor of arbitration. As the Supreme Court explained in Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1, 24-25, 103 S.Ct. 927, 942, 74 L.Ed.2d 765 (1983):

The Arbitration Act establishes that, as a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability (footnote omitted).

The agreement is loosely worded, but General Condition 7 and Article A-5 are not necessarily inconsistent. Article A-5 provides only that the contractual obligations shall not be a limitation on rights “otherwise imposed or available by law” (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
823 F.2d 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/place-st-charles-a-louisiana-partnership-v-ja-jones-construction-co-ca5-1987.