PJM Power Providers Group v. FERC

Procedural entryThis page is a short order in PJM Power Providers Group v. FERC. Read the opinion of the Court — 88 F.4th 250
Court of Appeals for the Third Circuit·Decided January 24, 2024·No. 21-3068·Published

Opinion

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 21-3068, 21-3205 & 21-3243

PJM POWER PROVISERS GROUP, Petitioner in 21-3068 v.

FEDERAL ENERGY REGULATORY COMMISSION

ELECTRIC POWER SUPPLY ASSOCIATION, Petitioner in 21-3205

PENNSYLVANIA PUBLIC UTILITY COMMISSION; PUBLIC UTILITIES COMMISSION OF OHIO, Petitioners in 21-3243

(Agency No. ER21-2582-000)

To: Clerk

Motion by Intervenor Respondent Buckeye Power Inc to Amend Opinion dated December 1, 2023.

_________________________________ORDER________________________________ The foregoing motion is granted at the direction of the Court. The opinion will be amended contemporaneously with this order. As the changes to the opinion are clerical in nature, the judgment is unaffected and remains as originally filed.

For the Court,

Patricia S. Dodszuweit, Clerk

Dated: January 24, 2024

kr/cc: All Counsel of Record

Free access — add to your briefcase to read the full text and ask questions with AI

PJM Power Providers Group v. FERC, (3d Cir. 2024).

PJM Power Providers Group v. FERC (PJM Power Providers Group v. FERC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.