PJM Power Providers Group v. FERC
Opinion
UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT
No. 21-3068, 21-3205 & 21-3243
PJM POWER PROVISERS GROUP, Petitioner in 21-3068 v.
FEDERAL ENERGY REGULATORY COMMISSION
ELECTRIC POWER SUPPLY ASSOCIATION, Petitioner in 21-3205
PENNSYLVANIA PUBLIC UTILITY COMMISSION; PUBLIC UTILITIES COMMISSION OF OHIO, Petitioners in 21-3243
(Agency No. ER21-2582-000)
Present: JORDAN, PHIPPS and ROTH, Circuit Judges
Motion by Respondent FERC to Correct the Opinion dated December 1, 2023.
Respectfully, Clerk/kr
_________________________________ORDER________________________________ The foregoing motion is GRANTED. The clerk is directed to amend the opinion to include the correct address of counsel Jared B. Fish. As the change to the opinion is clerical in nature, the judgment is not affected and remains as originally filed.
By the Court,
s/ Jane R. Roth Circuit Judge
Dated: January 4, 2024 kr/cc: All Counsel of Record