P.J. Gear & Son, Inc. v. City of Medford

16 Mass. L. Rptr. 173
CourtMassachusetts Superior Court
DecidedApril 29, 2003
DocketNo. 0203408
StatusPublished

This text of 16 Mass. L. Rptr. 173 (P.J. Gear & Son, Inc. v. City of Medford) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P.J. Gear & Son, Inc. v. City of Medford, 16 Mass. L. Rptr. 173 (Mass. Ct. App. 2003).

Opinion

Brassard, J.

The plaintiff, P.J. Gear & Son, Inc. (“Gear”) has brought suit against the defendants, City

of Medford, acting through the Medford Housing Authority (“MHA”), andB. Goba Associates, Inc. (“Goba”), alleging breach of contract (Count I), delay damages (Count II), misrepresentation and unfair or deceptive acts or practices in the conduct of any trade or commerce under G.L.c. 93A, §11 (Count III). Goba has moved for summary judgment on all counts in Gear’s amended complaint and Gear has filed a cross motion for summary judgment on all counts in its amended complaint as they relate to Goba.3 For the reasons set forth below, Goba’s motion for summary judgment on Counts I-III is ALLOWED and Gear’s cross motion for summary judgment on Counts I-III, as they relate to Goba, is DENIED.

BACKGROUND

The summary judgment record contains the following material facts.

On January 2, 2001, Gear entered into a contract with MHA to serve as the general contractor on a project to renovate a lobby in the Saltonstall Building at 121 Riverside Avenue (“the Project”). Goba entered into a separate contract with MHA to serve as the architect on the Project and act as the administrator of the construction contract. Under the terms of its contract with MHA, Goba had to review, approve and submit all of Gear’s requests for payment. The contract further required Goba to negotiate, prepare cost or price analyses for and countersign change orders and to prepare written punch lists, certificates of completion and other necessary construction close out documents.

At some time prior to February 15, 2001, Gear began experiencing delays on the Project. On August 2, 2001, Gear submitted Change Order #1 seeking a 175-day extension on the time of the contract and $25,740.99 for extra work performed. It also submitted Requisition for Payment #6 in the amount of $128,721.99 for contract work due to Gear and its subcontractors and Requisition for Payment #7 in the amount of $36,932 for retainage due to Gear and its subcontractors. On September 25, 2001, Gear resubmitted all of the above along with Change Order #2. Change Order #2 sought a five-day extension and $928.40 for additional work performed.

On October 17, 2001, Gear received its “first” non-monetarized punch list from Goba containing forty-seven items, which Goba believed were not complete. Gear returned the punch list on December 7, 2001, stating that most, if not all, of the work had been completed by November 14, 2001, if not before. Gem received two additional punch lists, one on January 14, 2002 and one monetarized on February 8, 2002, containing items from the October 17, 2001 punch list that Goba believed were still incomplete. Gear submitted these lists to its subcontractors, who Gear claims responded that most, if not all, of the work had already been completed. On February 19, 2002, MHA notified Gear that because of its failure to complete the work [174]*174and pay its subcontractors, MHA was invoking liquidated damages and would not make any further payments.

DISCUSSION

Summary judgment is appropriate when there are no genuine issues of material fact and the summary judgment record entitles the moving party to judgment as a matter of law. See Mass.R.Civ.P. 56(c); Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983). The facts must be viewed “in the light most favorable to [the nonmoving party], taking all the facts set forth in its supporting affidavits as true.’’4 G.S. Enterprises. Inc. v. Falmouth Marine, Inc., 410 Mass. 262, 263 (1991). The moving party bears the burden of demonstrating that no genuine issue of material fact exists on every relevant issue. See Pederson v. Time, Inc., 404 Mass. 14, 17 (1989). Amovingparty who does not bear the burden of proof at trial may demonstrate the absence of a triable issue either by submitting affirmative evidence negating an essential element of the nonmoving party’s case or by showing that the nonmoving party has no reasonable expectation of proving an essential element of its case at trial. See Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). The nonmoving party is required to oppose the summary judgment motion by setting forth “specific facts showing that there is a genuine issue for trial.” Mass.R.Civ.P. 56(e); Kourouvacilis, 410 Mass. at 716. Vague or general allegations of expected proof or mere assertions or inferences made by the opposing party are insufficient to defeat a motion for summary judgment. See First National Bank of Boston v. Slade, 379 Mass. 243, 246 (1979).

A. Breach of Contract and Delay Damages

Gear asserts that Goba breached a contractual obligation to Gear by failing to act on Gear’s requests for payment. There is no contract, however, between Gear and Goba. Gear had a contract with MHA and Goba had its own contract with MHA, but Gear and Goba did not have a contract with each other. Without an agreement, oral or written, expressed or implied, Gear cannot sustain a claim for breach of contract. See Singarella v. Boston, 342 Mass. 385, 387 (1961) (to prove a breach of contract, the plaintiff must prove (1) an agreement (2) supported by consideration, (3) that the plaintiff was ready to perform, (4) breach prevented it from performing, and (5) damages). To the extent that Gear’s delay claim arises out of an alleged breach of contract between Gear and Goba, since there was no contract between them, Goba is not responsible for any delay damages arising out of an alleged contract with Gear or Goba’s contract with MHA.

B. Misrepresentation

Gear claims that Goba’s submission of the punch lists to Gear and recommendations to MHA to deny payment because work was not completed amounted to fraud or negligent misrepresentation. In analyzing a claim for negligent misrepresentation, the court must begin by determining whether, in the absence of a contract, Gear can bring a claim of negligent misrepresentation against Goba. The duty of a professional to persons with whom the professional is not in privity extends to a plaintiff who can establish actual knowledge on behalf of the professional of the limited, named or unnamed, group of people who might reasonably be expected to receive this information and act in reliance upon it, as well as actual knowledge of the purpose of the information. See Nycal Corp. v. KPMG Peat Marwick, LLP., 426 Mass. 491, 496-97 (1998). Since Goba knew that it was required to administer the construction contract and that MHA would use Goba’s recommendations to determine whether to pay Gear or to direct Gear to do additional work, Gear can bring a negligent misrepresentation claim against Goba, despite the absence of a contract.

Next, the court must determine whether Gear has a reasonable expectation of proving the essential elements of a negligent misrepresentation claim. See Kourouvacilis, 410 Mass. at 716; Nota Construction Corp. v. Keyes Associates, Inc., 45 Mass.App.Ct. 15, 19-20 (1998).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Craig v. Everett M. Brooks Co.
222 N.E.2d 752 (Massachusetts Supreme Judicial Court, 1967)
PMP Associates, Inc. v. Globe Newspaper Co.
321 N.E.2d 915 (Massachusetts Supreme Judicial Court, 1975)
Nei v. Boston Survey Consultants, Inc.
446 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1983)
Singarella v. City of Boston
173 N.E.2d 290 (Massachusetts Supreme Judicial Court, 1961)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Mongeau v. Boutelle
407 N.E.2d 352 (Massachusetts Appeals Court, 1980)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Zimmerman v. Kent
575 N.E.2d 70 (Massachusetts Appeals Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
G.S. Enterprises, Inc. v. Falmouth Marine, Inc.
571 N.E.2d 1363 (Massachusetts Supreme Judicial Court, 1991)
Glickman v. Brown
486 N.E.2d 737 (Massachusetts Appeals Court, 1985)
First National Bank v. Slade
399 N.E.2d 1047 (Massachusetts Supreme Judicial Court, 1979)
Nycal Corp. v. KPMG Peat Marwick LLP
688 N.E.2d 1368 (Massachusetts Supreme Judicial Court, 1998)
Standard Register Co. v. Bolton-Emerson, Inc.
649 N.E.2d 791 (Massachusetts Appeals Court, 1995)
Fox v. F & J Gattozzi Corp.
672 N.E.2d 547 (Massachusetts Appeals Court, 1996)
Nota Construction Corp. v. Keyes Associates, Inc.
694 N.E.2d 401 (Massachusetts Appeals Court, 1998)
Reisman v. KPMG Peat Marwick LLP
787 N.E.2d 1060 (Massachusetts Appeals Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
16 Mass. L. Rptr. 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pj-gear-son-inc-v-city-of-medford-masssuperct-2003.