Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Wilson

91 N.E. 725, 46 Ind. App. 444, 1910 Ind. App. LEXIS 117
CourtIndiana Court of Appeals
DecidedApril 27, 1910
DocketNo. 6,719
StatusPublished
Cited by6 cases

This text of 91 N.E. 725 (Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Wilson) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Wilson, 91 N.E. 725, 46 Ind. App. 444, 1910 Ind. App. LEXIS 117 (Ind. Ct. App. 1910).

Opinion

Myers, C. J.

Appellees brought this action against appellant to recover damages for the destruction of a farm crossing over appellant’s right of way and railroad tracks, in violation of a provision in a certain deed, giving appellant a paper title to such right of way.

Many of the matters suggested by counsel for appellant at this time were sufficiently discussed in the opinion on the former appeal. That opinion also shows the facts substantially as they appeared in evidence upon the previous trial. Pittsburgh, etc., R. Co. v. Wilson (1904), 34 Ind. App. 324.

On the return of this cause to the court below, the pleadings were reformed by the filing of two amended paragraphs of complaint and. a third paragraph. A demurrer to each of these paragraphs for want of facts was overruled. When the ease was here before, as now, each paragraph was based upon a deed of conveyauce of the right of way, which contained a covenant on the part of the railroad'company, grantee, “to make, for the grantors one farm crossing; together with all legal and equitable rights, claims and demands therein and thereto.” •

The first paragraph of the complaint, after showing that appellees were the owners of the land on- each side of appellant’s right of way, and the change of grade of the railroad tracks in 1901, whereby the crossing at grade which existed at that time, and at the time of the conveyance, and for many years thereafter, was, by appellant, without the consent of appellees or either of them, wrongfully and without [447]*447right destroyed by the erection and construction of an embankment over said crossing, alleged that appellant, ever since the constructing of the embankment, had wholly neglected, failed and refused to construct or maintain, or permit to be constructed or maintained, any other crossing in lieu thereof, and that appellees have been wholly deprived of a crossing. After showing that the embankment at its highest point was more than twenty feet high, and at its lowest point eight feet high, its average height being fourteen feet, it was alleged from the break on each side it was almost perpendicular and of such height, and the contour of the land adjoining was of such a character, as to render it impossible and impracticable to construct a crossing over and across appellant’s right of way, grade and embankment, with proper or sufficient approaches thereto to permit appellees or the occupants of the land to use it as a farm crossing with any degree of safety.

In the second paragraph it was shown that in 1902 appellant, as a partial compliance with its contract, constructed a crossing over the tracks of its railroad on the top of the embankment, at a point some rods east of the place where the destroyed crossing Avas located, and at a point AAdiere the embankment and tracks were ten feet above the surrounding surface, by placing planks suitable for a crossing between the rails and at the sides of its tracks, but that it wholly failed, neglected and refused to construct the approaches thereto so that it could be used by appellees as a crossing, or Avas suitable for the use and benefit of the occupants of said lands; that before appellees could use it as a farm crossing it Avould be necessary to build and construct approaches thereto; that by reason of the sloping condition of the surface of the land at that point it would be necessary to extend the approaches for a long distance onto appellees’ land on either side of appellant’s right of Avay, to the great and irreparable damage of the land; that in order for appellées to construct, and complete said approaches it will be necessary for them [448]*448to expend a large sum of money. Other damages also were stated.

The third paragraph was substantially like the second, except that it stated that a practicable crossing could be constructed, with approaches suitable for a farm crossing, at a point 150 feet east of the place where the appellant attempted to build a crossing, by grading and constructing. approaches upon the right of way, and extending them out'over the lands of appellees on each side of the right of way, and that by reason of the high grade and embankments, and the condition of the land adjacent, there was no other place where an overgrade crossing could be constructed as easily or as cheaply.

1. 2. While it is true that the railroad company had the right to raise the grade of its tracks, yet it had received its right of way under a contract to make a farm crossing, “together with all legal and equitable rights, claims and demands therein and thereto.” If it chose to raise its grade, as described in the complaint, and failed to provide an undergrade crossing, and it was impossible to make a practicable overgrade crossing wholly on its right of way, and it was occupying the right of way under a contract requiring it to provide one crossing, it cannot be pretended that the law is so impotent as not to furnish any remedy, by way of damages, for such an injury to the farm, as to make it practically impossible to enjoy the use of one-half thereof with safety and reasonable convenience. Therefore, the first paragraph of the complaint was sufficient.

3. The second and third paragraphs show that appellant recognized its obligation to provide a crossing, and constructed one without proper approaches thereto. The second paragraph shows that the crossing so made was impracticable, but that it might be made practicable by extending approaches beyond the right of way, and the third paragraph shows that a passable crossing could not be made at the place so selected by the appellant, but might be [449]*449made at another designated point, by extending the approaches over the land of appellees.

Appellant having failed to make an undergrade crossing, and it being practicable to make an overgrade one, and it being bound by its contract to make a crossing at its own expense, and not having done so, it would be liable in damages. The second and third paragraphs each shows a cause of action.

Appellant’s motion for a new trial was overruled.

4. Upon the trial the cause proceeded upon the theory set forth in the second paragraph of complaint. It is insisted that appellees should not have been permitted to prove by parol their ownership of the farm divided by the right of way into nearly equal portions, and that they should have been required to prove title by the production of deeds of conveyance.

Abram Wilson was the owner and occupant of the land in question at the time of the construction of the railroad. Delia Wilson was the widow of Abram Wilson, and with Prances M. Crumley, one of the two appellees herein, and Nancy Shrack, their husbands joining, in 1883 executed the deed for the right of way containing the covenant upon which this action is predicated. At the time the deed was made, Delia Wilson’s interest in the land was that received by her as widow of Abram Wilson, and the interest of her two daughters in the land came to them by inheritance from their father. Abram Wilson died in 1874, and his widow, mother of appellees, Prances M. Crumley and James W. Wilson, died in 1887. In 1888 James W. Wilson purchased the interest from his sister, Nancy P. Shrack, and he lived on the farm from that time until after the destruction of the crossing and the commencement of this action. It was upon his demand that the imperfect crossing was made.

The contract in suit was one by virtue of which appel[450]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Countrywide Home Loans, Inc. v. Robert Holland
993 N.E.2d 184 (Indiana Court of Appeals, 2013)
Guido v. Baldwin
360 N.E.2d 842 (Indiana Court of Appeals, 1977)
Chicago, Indianapolis & Louisville Railway Co. v. Beisel
106 N.E.2d 117 (Indiana Court of Appeals, 1952)
Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Arnott
135 N.E. 365 (Indiana Court of Appeals, 1922)
Pittsburgh, Cincinnati, Chicago & St. Louis Railway Co. v. Kearns
108 N.E. 873 (Indiana Court of Appeals, 1915)
Friendly v. Ruff
120 P. 745 (Oregon Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
91 N.E. 725, 46 Ind. App. 444, 1910 Ind. App. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburgh-cincinnati-chicago-st-louis-railway-co-v-wilson-indctapp-1910.