Pittman v. Manion

570 N.E.2d 1169, 212 Ill. App. 3d 342, 156 Ill. Dec. 447, 1991 Ill. App. LEXIS 430
CourtAppellate Court of Illinois
DecidedMarch 22, 1991
Docket5-90-0215
StatusPublished
Cited by5 cases

This text of 570 N.E.2d 1169 (Pittman v. Manion) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittman v. Manion, 570 N.E.2d 1169, 212 Ill. App. 3d 342, 156 Ill. Dec. 447, 1991 Ill. App. LEXIS 430 (Ill. Ct. App. 1991).

Opinion

JUSTICE WELCH

delivered the opinion of the court:

Appellant, Eater Heating & Cooling Service Co. (hereinafter, Eater), appeals from the dismissal with prejudice of its counterclaim by the circuit court of Jefferson County on March 12, 1990. For the reasons which follow, we reverse the order of the circuit court and remand this cause with directions.

The original action was initiated by Phil Pittman on July 27, 1988, with the filing of a complaint to foreclose his subcontractor mechanic’s lien against James Manion and Bobbie Manion (hereinafter, Owners); the general contractor, David Laird; the mortgagees of the owners’ real estate, Boatman’s Bank of Mt. Vernon and the Bank of Illinois in Mt. Vernon; and other possible holders of mechanics’ liens against the real estate. Eater filed its counterclaim in the circuit court on August 15, 1988, against the owners, the above-named mortgagee banks and Phil Pittman, seeking to foreclose its subcontractor mechanic’s lien against the owners’ real estate and a money judgment against the owners or the contractor, David Laird. Eater alleged in the counterclaim that from April 16, 1987, to December 14, 1987, pursuant to its contract with Laird, it had furnished labor and materials for a heating and air conditioning system in the home of the owners and that the amount due for the above labor and materials was $14,891.34. Eater attached as an exhibit to its counterclaim its subcontractor’s 90-day notice served on the owners on March 2, 1988, at the residence where the lienable services and materials were furnished, pursuant to section 24 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1989, ch. 82, par. 24).

The owners filed a motion to dismiss Eater’s counterclaim for the reason that it failed to allege facts showing compliance with the Mechanics’ Liens Act. The owners cited, in particular, sections 5 and 21 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1989, ch. 82, pars. 5, 21), which are essentially identical. Section 5 requires in pertinent part as follows:

“It shall be the duty of each subcontractor who has furnished, or is furnishing, materials or labor for an existing owner-occupied single-family residence, in order to preserve his lien, to notify the occupant either personally or by certified mail, return receipt requested, addressed to the occupant or his agent at the residence within 14 days from his first furnishing materials or labor, that he is supplying materials or labor, provided, however, that any notice given after 14 days by the subcontractor shall preserve his lien, but only to the extent that the owner has not been prejudiced by payments made prior to receipt of the notice.
The notice shall contain the name and address of the subcontractor or material man, the date he started to work or to deliver materials, the type of work done and to be done or the type of materials delivered and to be delivered, and the name of the contractor requesting the work. The notice shall also contain the following warning:
‘NOTICE TO OWNER
Do not pay the Contractor for this work or material delivered unless you have received from the Contractor a waiver of lien by, or other satisfactory evidence of payment to, the Subcontractor or Material Man.’ Such warning shall be in at least 10 point boldface type. For purposes of this section, notice by certified mail is considered served at the time of its mailing.” (Ill. Rev. Stat. 1989, ch. 82, par. 5.)

The owners alleged that David Laird was the contractor with whom they contracted to renovate and reconstruct their home and that the subcontractor Eater had failed to serve this notice on them at any time after the furnishing of materials or labor and so its lien had not been preserved and the suit to foreclose the lien should be dismissed. The court below dismissed Eater’s counterclaim with prejudice on August 25, 1989, finding that it was fatally defective for failure to plead service of a 14-day subcontractor notice on the owners.

Eater filed a motion to reconsider the order of dismissal on September 14, 1989, claiming, as it does in this appeal, that because the owners’ real estate was not an existing owner-occupied single-family residence occupied by the owners at the time it furnished the heating and air conditioning system, the 14-day notice was not required. Eater attached the affidavit of David McCann, one of its partners, which affidavit provided that McCann had personal knowledge that the owners’ premises had been destroyed by fire and was not occupied by the owners or anyone else during the period of time the lien-able services and materials were furnished to the owners’ real estate, and that the residence now located on said real estate was built from the basement up. The owners responded, as they do in this appeal, that if Eater’s position regarding the applicability of section 5 of the Mechanics’ Liens Act to this factual situation is adopted by the court, then the purpose of the Act would be defeated, as families who go on vacation or even leave for the day for school or work would be unprotected by the notice provisions if they could arguably be found not to “occupy” their family home at the moment a subcontractor began work or delivered materials. Bobbie Manion submitted an affidavit which was attached to the owners’ response which provided that the owners occupied the premises during the time Eater furnished the lienable labor and materials because family possessions which were not burned were at all times after the fire stored on the premises in a storage shed and that members of the family were frequently and regularly at the premises during this time period. Eater filed a supplement to its motion to reconsider stating that unlike the section 24 90-day notice on the owner, with which it complied, the section 5 notice is only' required to be given to owner-occupied single-family residents.

On March 1, 1989, Laird filed a voluntary petition in bankruptcy pursuant to chapter 7 of the United States Bankruptcy Code (11 U.S.C.S., ch. 7, §301 et seq. (Supp. 1990)), listing Eater among his creditors, and received his discharge 106 days later on June 15, 1989. Eater also noted in the supplement to its motion that because of Laird’s intervening bankruptcy and discharge it would strike the request for a personal judgment against Laird as requested in its prayer for relief. Eater had not joined or served Laird as a defendant in its counterclaim or proposed counterclaim, however, and maintains on appeal that Laird is not a necessary party in its complaint to foreclose a mechanic’s lien against the owners’ real estate.

The court below denied Eater’s motion to reconsider but allowed Eater leave to file a motion to amend its proposed amended counterclaim to include argument as to the necessity of joining defendant Laird regarding his bankruptcy. Eater contended that because it was not seeking a money judgment against Laird, the contractor was not a necessary party in foreclosure of its mechanic’s lien in a proceeding brought under section 11 of the Mechanics’ Liens Act. Eater cited this pertinent part of section 11 under which it stated it would bring the amended counterclaim:

“The plaintiff shall make all parties interested, of whose interest he is notified or has knowledge, parties defendant, ***.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Anderson
2015 IL App (3d) 140257 (Appellate Court of Illinois, 2015)
Concrete Products, Inc. v. Centex Homes
721 N.E.2d 802 (Appellate Court of Illinois, 1999)
Chicago Whirly, Inc. v. Amp Rite Electric Co., Inc.
710 N.E.2d 45 (Appellate Court of Illinois, 1999)
In Re Petroleum Piping Contractors, Inc.
211 B.R. 290 (N.D. Indiana, 1997)
West Pointe Properties v. Frye
934 S.W.2d 339 (Court of Appeals of Tennessee, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
570 N.E.2d 1169, 212 Ill. App. 3d 342, 156 Ill. Dec. 447, 1991 Ill. App. LEXIS 430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittman-v-manion-illappct-1991.