D.E. Wright Electric, Inc. v. Henry Ross Construction Co.

538 N.E.2d 1182, 183 Ill. App. 3d 46, 131 Ill. Dec. 626, 1989 Ill. App. LEXIS 552
CourtAppellate Court of Illinois
DecidedApril 28, 1989
Docket5-87-0835
StatusPublished
Cited by7 cases

This text of 538 N.E.2d 1182 (D.E. Wright Electric, Inc. v. Henry Ross Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.E. Wright Electric, Inc. v. Henry Ross Construction Co., 538 N.E.2d 1182, 183 Ill. App. 3d 46, 131 Ill. Dec. 626, 1989 Ill. App. LEXIS 552 (Ill. Ct. App. 1989).

Opinion

PRESIDING JUSTICE WELCH

delivered the opinion of the court:

Plaintiff, D.E. Wright Electric, Inc., appeals from the dismissal with prejudice of its complaint against defendant, Henry Ross Construction Company, Inc., by the circuit court of Jackson County on November 20, 1987. For the reasons which follow, we reverse the order of the circuit court and remand this cause with directions.

Plaintiff filed its complaint in the circuit court of St. Clair County on May 24, 1976. The action was brought under section 28 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1975, ch. 82, par. 28), against the owner of the improved property, First National Bank and Trust Company, as trustee, and the defendant/contractor, Henry Ross Construction Company, Inc.

Section 28 of the Mechanics’ Liens Act provides that a subcontractor may sue the owner and contractor jointly for the amount due under the subcontract, and a personal judgment may be rendered against both. Such an action may be maintained against the owner only when the plaintiff establishes a right to the lien. All suits and actions by subcontractors under this section must be brought against both the contractor and the owner jointly, and all judgments where the lien is established shall be entered against both jointly. However, “this shall not preclude a judgment against the contractor, personally, where the lien is defeated.” Ill. Rev. Stat. 1987, ch. 82, par. 28.

Plaintiff’s complaint alleges that plaintiff entered into a subcontract with defendant, Henry Ross Construction Company, Inc., to perform certain electrical work and supply materials for the construction of a building located on land owned by First National Bank and Trust Company, as trustee; that plaintiff has performed under the contract; that there remains due and owing to plaintiff under the contract the sum of $56,516.68; and that plaintiff has served upon both the contractor and the owner a notice of lien as provided by the Mechanics’ Liens Act. The complaint prays that the court enforce plaintiff’s rights under the Mechanics’ Liens Act and enter judgment jointly against both the contractor and owner.

On July 28, 1976, defendant, Henry Ross Construction Company, Inc., filed a motion to dismiss plaintiff’s complaint for the reason that the subcontract between plaintiff and defendant provides that

“[a]ll claims, disputes, and other matters in question arising out of, or relating to, this Subcontract, or the breach thereof, shall be decided by arbitration ***.”

On August 22, 1978, the court ordered all further proceedings stayed until such time as arbitration is concluded. On December 1, 1978, plaintiff moved the court to set aside the stay order for the reason that the subcontract between plaintiff and defendant also provides that the arbitration clause

“shall not be deemed a limitation on any rights or remedies which the Subcontractor may have under any Federal or State mechanics' lien laws”

and that plaintiff’s action was brought pursuant to the Mechanics’ Liens Act of the State of Illinois. On January 3, 1979, the court vacated its order of August 22, 1978, staying proceedings in this cause. The case was reset on the court’s regular docket.

On March 27, 1979, plaintiff’s complaint was dismissed for technical reasons, and plaintiff was granted leave to amend. Plaintiff filed its amended complaint on May 14, 1980. The complaint contained substantially the same allegations of fact as plaintiff’s original complaint and prayed that the court enter judgment against the contractor and owner in the sum of $56,516.68 plus interest, and that the court enforce plaintiff’s rights under the Mechanics’ Liens Act.

On June 23, 1980, owner filed a motion to transfer venue from St. Clair County to Jackson County for the reason that section 9 of the Mechanics’ Liens Act provides that venue is proper thereunder in the county where the property is located, and the property involved herein is located in Jackson County. (Ill. Rev. Stat. 1987, ch. 82, par. 9.) This motion was granted by order of court dated August 11, 1980, and the cause was ordered transferred to Jackson County.

On January 7, 1981, plaintiff and owner filed a stipulation for dismissal, alleging that a settlement of all issues had been reached between plaintiff and owner, First National Bank and Trust Company, and asking the court to dismiss with prejudice the cause as to First National Bank and Trust Company. On that same date, the court approved the stipulation and dismissed with prejudice plaintiff’s claim against First National Bank and Trust Company. This left only plaintiff’s claim against defendant/contractor, Henry Ross Construction Company, Inc.

On July 27, 1987, defendant filed a counterclaim against plaintiff alleging that plaintiff had breached the subcontract by refusing and neglecting to employ a sufficient number of skilled laborers to complete its work in an expeditious manner, thereby delaying, hindering and obstructing completion of the project. As a result of plaintiff’s breach of the subcontract, the counterclaim alleges, defendant has suffered damages in an amount in excess of $15,000.

On August 10, 1987, in response to defendant’s notice to produce, plaintiff filed an affidavit of compliance in which it stated that it would not produce certain documents relating to its mechanic’s lien because,

“[sjince the complaint against the owner has been settled and since this matter is brought as a suit for money judgment under Section 28 of the Mechanics’ Liens Act by Plaintiff subcontractor against Defendant contractor, this is no longer a suit for mechanic’s lien but rather a suit on the contract and contract documents between Plaintiff and Defendant.”

In response to this statement by plaintiff, defendant filed a motion to dismiss the complaint alleging that since the action against the owner had been settled, there was no longer any lien on the property, and therefore, there can be no action under section 28 of the Mechanics’ Liens Act; that plaintiff is now attempting to assert a common law claim for money damages for breach of contract; that this claim is barred by the subcontract, which requires that any such claims be submitted to arbitration; that plaintiff’s complaint cannot be amended to state a cause of action for breach of contract or for collection on a written contract as any such claim is barred by the statute of limitations; and that plaintiff cannot at this late date assert a right to arbitration.

Hearing was held on the motion on September 17, 1987. Plaintiff responded to defendant’s motion in part by arguing that it seeks to proceed on its amended complaint under the contract; that arbitration is no longer appropriate because defendant has waived his right to arbitration by filing a counterclaim on the contract, but that if the court feels arbitration is appropriate, it should stay any further proceedings in the circuit court and submit the cause to arbitration, rather than dismiss it. Finally, plaintiff asked that, if the court determines that its complaint does not state a good cause of action for breach of contract, that it be granted leave to amend its complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TSP-Hope, Inc. v. Home Innovators of Illinois, LLC
890 N.E.2d 1220 (Appellate Court of Illinois, 2008)
TSP-Hope v. Home Innovators of Illinois
Appellate Court of Illinois, 2008
Yandell v. Church Mutual Insurance
654 N.E.2d 1388 (Appellate Court of Illinois, 1995)
Yandell v. Church Mut. Ins. Co.
654 N.E.2d 1388 (Appellate Court of Illinois, 1995)
Jacob v. C & M VIDEO, INC.
618 N.E.2d 1267 (Appellate Court of Illinois, 1993)
Burnett v. Safeco Ins. Co. of Illinois
590 N.E.2d 1032 (Appellate Court of Illinois, 1992)
Pittman v. Manion
570 N.E.2d 1169 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
538 N.E.2d 1182, 183 Ill. App. 3d 46, 131 Ill. Dec. 626, 1989 Ill. App. LEXIS 552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-wright-electric-inc-v-henry-ross-construction-co-illappct-1989.