Pittman v. Hunt Construction Group

564 F. Supp. 2d 531, 2008 U.S. Dist. LEXIS 49234, 2008 WL 2566568
CourtDistrict Court, E.D. North Carolina
DecidedJune 26, 2008
Docket5:07-mj-00001
StatusPublished
Cited by3 cases

This text of 564 F. Supp. 2d 531 (Pittman v. Hunt Construction Group) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittman v. Hunt Construction Group, 564 F. Supp. 2d 531, 2008 U.S. Dist. LEXIS 49234, 2008 WL 2566568 (E.D.N.C. 2008).

Opinion

ORDER

JAMES C. DEVER III, District Judge.

On January 8, 2007, Plaintiff Eddie LaReece Pittman (“Pittman” or “plaintiff’) filed this Title VII action against defendants Hunt Construction Group (“Hunt Construction”), Billy Stewart (“Stewart”), and Chris Armstrong (“Armstrong”) (collectively, “defendants”). On June 18, 2007, the court entered an order [D.E. 22] granting defendants’ motion to dismiss Stewart and Armstrong as defendants. Consequently, only Hunt Construction remained as a defendant in this case.

On March 28, 2008, Hunt Construction moved for summary judgment. Plaintiff responded on May 21, 2008, and Hunt Construction replied on June 9, 2008. For the reasons discussed below, Hunt Construction’s motion for summary judgment is granted.

I.

The court considers the facts in the light most favorable to Pittman, the non-moving party. See, e.g., United States v. Diebold, Inc., 369 U.S. 654, 655, 82 S.Ct. 993, 8 L.Ed.2d 176 (1962) (per curiam). In the fall of 2006, Pittman was employed by TradeStaff, a temporary employment agency. See Compl. 2. Hunt Construction was the general contractor for the new Genetics Medicine Building at the Univer *533 sity of North Carolina in Chapel Hill (“the project”). See, e.g., Armstrong Aff. ¶2. Armstrong was the manager of the project, and Stewart was the superintendent of the project. Id.; Stewart Aff. ¶ 2. Stewart was Armstrong’s subordinate. Stewart Aff. ¶2.

During the fall of 2006, Hunt Construction needed approximately 15 temporary laborers for the project, and it engaged TradeStaff to provide these temporary laborers. E.g., Armstrong Aff. ¶ 3. The need for temporary laborers at large construction sites like the project waxes and wanes. See, e.g., Pittman Dep. 127:20-128:2. When Hunt Construction’s need for temporary laborers decreased, Armstrong would decide how many temporary laborer positions were no longer necessary, and would instruct Stewart to reduce the staff by determining which temporary laborers to retain and which temporary laborers to terminate. See Armstrong Aff. ¶ 4; Stewart Aff. ¶¶ 4-5.

TradeStaff assigned Pittman to the project in early September 2006. Compl. 2. TradeStaff manager Miles Johnson (“Johnson”) told Pittman that, if Pittman adequately performed his duties, then his assignment to the project would be long-term. Id. Plaintiff adequately performed his duties at the project. Id.

On October 3, 2006, while working at the project site, Pittman sat down to eat lunch. Id. At that time, a man named Kelvin Wood (“Wood”) sat down across from Pittman. Id. Kelvin Wood is nicknamed “KT.” See id.; Stewart Aff. ¶ 9. Wood was not a Hunt Construction employee or a TradeS-taff employee. See Stewart Aff. ¶ 9. Rather, he was the foreman for a steelwork subcontracting firm called National Rebar. Id.

After Wood sat down next to Pittman, Wood asked Pittman if he was alright. Compl. 2. Wood stated that Pittman was too quiet, and that there must be something wrong with him. Id. Wood then began a conversation with other individuals who were eating lunch nearby, stating, “You gotta watch quiet people ... they might be ready to snap at any time and kill someone.” Id. at 2-3.

Pittman felt insulted and believed that Wood had stereotyped Pittman due to Pittman’s race and “the way [Pittman] carried himself.” Id. at 3. Pittman called Johnson to complain about what Pittman believed was Wood’s racially-discriminatory comment. See id. Johnson told Pittman to type up a complaint and send it to the TrádeStaff office. See id. Pittman typed up a complaint and mailed it to TradeStaff that day. Id.

On October 5, 2006, Johnson called Pittman to notify Pittman that Johnson had received the complaint. Id. Johnson stated that he would immediately start investigating by contacting Stewart. Id. However, Johnson did not speak to Stewart or anyone else at Hunt Construction regarding Pittman’s complaint. Johnson Aff. ¶ 9. Instead, Johnson told his supervisor at TradeStaff, Greg Bunn (“Bunn”), that Pittman had filed a complaint. Id. ¶ 6.

Sometime during the week that included October 6, 2006, Armstrong decided to reduce the TradeStaff temporary labor force by three persons, and instructed Stewart to choose which three laborers should be terminated. Armstrong Aff. ¶ 4. Pittman was among the three temporary laborers that Stewart decided to terminate. Stewart Aff. ¶ 6; Bunn Aff. ¶ 6. On October 6, 2006, Stewart called Bunn to inform Tra-deStaff that Hunt Construction no longer needed three temporary laborers, including Pittman. Stewart Aff. ¶ 6; Bunn Aff. ¶ 6. Bunn then asked Stewart if Stewart had heard any complaints from any Tra-deStaff employees. Bunn Aff. ¶ 7. Stewart *534 said that he had not. Id. Bunn did not inform Stewart about Pittman’s complaint. Id.

Later that same day, Bunn told Johnson that Hunt Construction no longer needed Pittman and the other two temporary laborers whom Stewart had decided to terminate. Id. ¶ 8. Bunn instructed Johnson to reassign these three individuals. Id. Johnson then called Pittman and informed him that Hunt Construction no longer needed his services. Pittman Dep. 188:5-188:10.

At some point a few days after Pittman was no longer working for Trade Staff on the project, Armstrong received Pittman’s complaint through the Equal Employment Opportunity Commission (“EEOC”). Armstrong Aff. ¶ 5. This was the first time that anyone at Hunt Construction learned of Pittman’s complaint about Wood’s allegedly racially-discriminatory comment. See id. On October 20, 2008, Bunn met with Armstrong. Bunn Aff. ¶ 11. During this meeting, Armstrong told Bunn that he had received Pittman’s EEOC complaint. Id. This was the first time that anyone at TradeStaff had spoken to anyone at Hunt Construction about Pittman’s complaint. See id.

Pittman was one of nine TradeStaff temporary laborers whose assignment at the project ended in October 2006. See Bunn Aff. ¶¶ 8-9, 12. The assignments ended because Hunt Construction no longer needed their services at the project. Armstrong Aff. ¶7. To Hunt Construction’s knowledge, none of the TradeStaff employees who were terminated had ever made a complaint of any kind. See id.

After the EEOC issued a right-to-sue letter, Pittman filed suit in this court. Pittman argues that Hunt Construction terminated his employment in retaliation for his complaining about Wood’s allegedly racially-discriminatory remark, and that Hunt Construction thereby violated Title VII of the Civil Rights Act of 1964.

II.

Under Title VII of the Civil Rights Act of 1964, it is unlawful for an employer “to discriminate against any of [its] employees ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shepherd v. Coastal Community Action, Inc.
602 F. Supp. 2d 686 (E.D. North Carolina, 2009)
Pittman v. Hunt Construction Group
308 F. App'x 672 (Fourth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
564 F. Supp. 2d 531, 2008 U.S. Dist. LEXIS 49234, 2008 WL 2566568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittman-v-hunt-construction-group-nced-2008.