Pioneer Steel Erectors, Inc. v. Commonwealth

181 N.E.2d 670, 344 Mass. 195, 1962 Mass. LEXIS 718
CourtMassachusetts Supreme Judicial Court
DecidedApril 12, 1962
StatusPublished
Cited by4 cases

This text of 181 N.E.2d 670 (Pioneer Steel Erectors, Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pioneer Steel Erectors, Inc. v. Commonwealth, 181 N.E.2d 670, 344 Mass. 195, 1962 Mass. LEXIS 718 (Mass. 1962).

Opinion

Whittemore, J.

Pioneer Steel Erectors, Inc. (Pioneer), an unpaid subcontractor on a highway project, petitioned under G. L. c. 258, §§ 1 and 2, to establish a claim against the Commonwealth under G. L. c. 30, § 39F.1 It also petitioned for a writ of mandamus to require the Commissioners of Public Works to pay it out of sums payable to the principal contractor. A demurrer of the Commonwealth was sustained. The petition for mandamus was dismissed after hearing. At issue is the construction of the provision in G. L. c. 30, § 39F, which directs that if within ten days after the sixty-fifth day after a subcontractor has fully completed its work it has not received from the general contractor the entire balance due on its subcontract, less specified deductions or retentions, the subcontractor shall give written notice to the awarding authority and the general contractor and that thereupon “the awarding authority shall make, out of sums payable to the general contractor [197]*197on the general contract, direct payment to the subcontractor of the entire balance due on the subcontract less the aforesaid amounts. Such direct payment . . . shall discharge the obligation of the awarding authority to the general contractor to the extent of such payment.”

1. The sole contention in the Commonwealth’s brief in respect of the petition under G. L. c. 258 is that such obligation as exists under G. L. c. 30, § 39F, is not of the kind for which by G. L. c. 258 the Commonwealth has consented to be sued.

We disagree. To the extent that § 39F creates an obligation it is for the payment of money for services performed or materials furnished. This is a claim of the sort which “civilized governments have always recognized.” Murdock Parlor Grate Co. v. Commonwealth, 152 Mass. 28, 31. Nash v. Commonwealth, 174 Mass. 335, 338-340. George H. Sampson Co. v. Commonwealth, 202 Mass. 326, 332. Charles I. Hosmer, Inc. v. Commonwealth, 302 Mass. 495, 498. Arthur A. Johnson Corp. v. Commonwealth, 306 Mass. 347, 351. Chilton Club v. Commonwealth, 323 Mass. 543, 545-546. Compare Kennedy v. Commonwealth, 182 Mass. 480; Executive Air Serv. Inc. v. Division of Fisheries & Game, 342 Mass. 356, 359.

The effect of the statute, if obligatory, is to give a subcontractor a direct right such as it would have had under a contract between it and the Commonwealth. See, for a petition under G. L. c. 258 in respect of such a contract, M. DeMatteo Constr. Co. v. Commonwealth, 338 Mass. 568.

So far as the obligation is unlike an obligation under a direct contract between the Commonwealth and Pioneer, the distinction has been considered and disregarded in the Nash case, supra. There the Commonwealth had funds of the contractor which, under Pub. Sts. c. 16, § 64, were security for payment of the subcontractor’s bill.1 The contract provided that the “Commonwealth may keep any [198]*198moneys which would otherwise be payable hereunder, and apply the same to the payment of . . . all claims . . . notice of which . . . shall have been filed ... or may . . . apply such moneys thereto.” (P. 337.) It was held that the Commonwealth held the retained sums, under the provision of the contract and the statute, as trustee for the subcontractor. “The purpose . . . was to secure the . . . claim, and the Commonwealth ... is under an implied obligation to hold . . . [the fund] for that purpose.” (Pp. 337-338.) This court held in a majority opinion that the claim to the fund was within the scope of c. 195, as amended by St. 1887, c. 246, which statute is the forerunner of G. L. c. 258.

We think that § 39F created an obligation. The language is mandatory. The “awarding authority shall make . . . [the payment which] shall [pro tanto] discharge . . . [its obligation] to the general contractor.” We see no basis for assuming that the legislature was making only a suggestion of good practice. The legislative history tends to show the contrary.1

The Commonwealth relies on the circumstance that the specified security for the payment of subcontractors is now only a surety bond under G. L. c. 149, § 29, as appearing in St. 1957, c. 682, § 1, whereas formerly by c. 30, § 39 (now repealed), the security was to be by “bond or otherwise.”2 It seeks to distinguish the Nash case on this ground. That statutory change does not, however, suggest that c. 30, § 39F, was to be meaningless. By the change, rights against retained funds were given only under § 39F, but the language used therein was appropriate to create rights. It is relevant, as the Commonwealth contends, that G. L. c. 30, § 39, provided that c. 258 should apply to petitions to en[199]*199force rights in the security taken thereunder, and that there is no comparable provision in the new statutes. This may show legislative awareness that the primary proceeding under G. L. c. 149, § 29, would always be against the bonding company, and it does suggest that the general court was not giving thought to how the right under G. L. c. 30, § 39F, would be enforced. It does not, however, negative the intent which we find in § 39F that it be effective to assure prompt payment to the subcontractor. The Nash case shows that in the absence of an express reference to G. L. c. 258 (or its forerunner), an intent to provide for payment by a State agency from a retained fund creates an obligation for which the Commonwealth may be sued.

The obligation imposed by the statute is not merely, as the Commonwealth contends, to include the substantive provision in every “contract ... [in respect of certain] public building[s] or public works” as the first sentence of § 39F makes mandatory. The obligation of the awarding authority to make payments stems from the express mandate of the statute; and the inclusion of the provision in the contract assures the contractual assent of all concerned.

The legislative intent to impose an obligation is suggested by the provision for interest in G. L. c. 30, § 39K, inserted by St. 1961, c. 627, § 1. Section 39K applies to contracts for public buildings only and requires payments to contractors after specified elapsed periods and deductions including “retention for direct payments to subcontractors based on demands . . . [under] section thirty-nine F . . ..” “If the awarding authority fails to make payment as herein provided, there shall be added to each such payment daily interest at the rate of five per cent per annum .... The contractor agrees to pay to each subcontractor a portion of any such interest paid in accordance with the amount due each subcontractor.”

There is also a provision in § 39G, as amended through St. 1957, c. 360, for the payment of interest on delayed payments to contractors under contracts for public buildings and specified public works.

[200]*200It would be anomalous to impose an obligation on the awarding authority to make the specified payment, without recognizing an obligation on the Commonwealth to make good on its failure to do so.

2. The petition for writ of mandamus was rightly dismissed in view of the remedy under G. L. c. 258 (point 1, supra).

3. The order for judgment dismissing the petition for a writ of mandamus is affirmed. The order sustaining the demurrer to the petition under Gr. L. c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. Amanti & Sons, Inc. v. Triton Regional School District
14 Mass. L. Rptr. 3 (Massachusetts Superior Court, 2001)
O'Connor v. Deputy Commissioner & Comptroller of Commonwealth
204 N.E.2d 705 (Massachusetts Supreme Judicial Court, 1965)
Long Island Painting Corp. v. Beacon Construction Co.
188 N.E.2d 857 (Massachusetts Supreme Judicial Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
181 N.E.2d 670, 344 Mass. 195, 1962 Mass. LEXIS 718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-steel-erectors-inc-v-commonwealth-mass-1962.