HAROLD BROTHERS MECHANICAL CONTRACTORS, INC. v. TOWN OF BRAINTREE; SHAWMUT WOODWORKING AND SUPPLY, INC., Third-Party

CourtMassachusetts Superior Court
DecidedJanuary 7, 2022
Docket2021-00505
StatusPublished

This text of HAROLD BROTHERS MECHANICAL CONTRACTORS, INC. v. TOWN OF BRAINTREE; SHAWMUT WOODWORKING AND SUPPLY, INC., Third-Party (HAROLD BROTHERS MECHANICAL CONTRACTORS, INC. v. TOWN OF BRAINTREE; SHAWMUT WOODWORKING AND SUPPLY, INC., Third-Party) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HAROLD BROTHERS MECHANICAL CONTRACTORS, INC. v. TOWN OF BRAINTREE; SHAWMUT WOODWORKING AND SUPPLY, INC., Third-Party, (Mass. Ct. App. 2022).

Opinion

SUPERIOR COURT

HAROLD BROTHERS MECHANICAL CONTRACTORS, INC. vs. TOWN OF BRAINTREE; SHAWMUT WOODWORKING AND SUPPLY, INC.[1], third-party defendant

Docket: 2021-00505
Dates: December 16, 2021
Present: Paul D. Wilson Justice of the Superior Court
County: NORFOLK, ss.
Keywords: MEMORANDUM OF DECISION AND ORDER ON PLAINTIFF’S MOTION FOR JUDGMENT ON THE PLEADINGS

            In July 2018, Defendant Town of Braintree (“Braintree”) entered into a construction contract with Third-Party Defendant Shawmut Design and Construction (“Shawmut”) for Shawmut to act as the general contractor on a project to renovate the Braintree East Middle School (the “Project”). Shawmut then subcontracted with Plaintiff Harold Brothers Mechanical Contractors, Inc. (“Harold Brothers”) to perform certain heating, ventilation, and air conditioning work on the Project. Shawmut made several payments to Harold Brothers under the subcontract, but Harold Brothers claims that after it completed its work on the Project, Shawmut refused to pay $393,201.00 it owed to Harold Brothers. Harold Brothers then demanded payment from Braintree pursuant to M.G.L. c. 30, § 39F.  Braintree failed to remit payment in the time specified by the statute, and this lawsuit ensued.

            The Complaint consists of one count, claiming that Braintree failed to comply with M.G.L. c. 30, § 39F and seeking payment of the balance due under the subcontract. Harold

-------------------------------------

            [1] d/b/a Shawmut Design and Construction

                                                            -1-

Brothers has moved for judgment on the pleadings, which Braintree and Shawmut oppose.[2] I heard argument on November 3, 2021. For the reasons set out below, I will allow Harold Brothers’ motion.

Analysis

            Under Massachusetts Rule of Civil Procedure 12(c), any party may move for judgment on the pleadings after the pleadings are closed. Mass. R. Civ. P. 12(c). A court may issue judgment on the pleadings only when the text of the pleadings produces no dispute about material facts. Clarke v. Metropolitan Dist. Comm’n, 11 Mass. App. Ct. 955, 955 (1981). “In deciding a rule 12(c) motion, all facts pleaded by the nonmoving party must be accepted as true.” Jarosz v. Palmer, 436 Mass. 526, 529-530 (2002), citing Minaya v. Massachusetts Credit Union Share Ins. Corp., 392 Mass. 904, 905 (1984). Judgment on the pleadings is not appropriate if the non-moving party pleads by denial or by an affirmative defense that puts in question a material allegation of the complaint. Tanner v. Board of App. of Belmont, 27 Mass. App. Ct. 1181, 1182 (1989). In presenting a Rule 12(c) motion, the moving party is deemed to have admitted as true the opposing party’s assertions of fact. Minaya, 392 Mass. at 905.

            The test for Rule 12(b)(6) motions governs a motion brought under Mass. R. Civ. P. 12(c). See Welch v. Sudbury Youth Soccer Assoc., 453 Mass. 352, 353 (2009). Accordingly, “the court may consider documents referenced in the plaintiff’s complaint without converting the motion to dismiss into a motion for summary judgment.” Johnston v. Box, 453 Mass. 569, 581-582 n. 19 (2009) (citation omitted); see Mullins v. Corcoran, 488 Mass. 275 (2021).

            Harold Brothers asserts that it is entitled to judgment on the pleadings because the facts established in the pleadings show that Braintree has failed to comply with M.G.L. c. 30, § 39F.

[2] The sole argument in Shawmut’s Opposition is also made by Braintree in its Opposition. Therefore, while I have not specifically noted Shawmut’s Opposition, I have addressed it in this decision.

                                                            -2-

Section 39F permits subcontractors to obtain direct payment from the awarding governmental authority, if the general contractor does not pay them promptly. Its purpose “is to ensure prompt payment to subcontractors on public works projects.” See E. Amanti & Sons, Inc. v. Triton Reg’l Sch. Dist., 14 Mass. L. Rptr. 3, 4 (Mass. Super. 2001) (Lowy, J).

            The statutory language of “Section 39F . . . is not unusually complicated.” American Manufacturers Mut. Ins. Co. v. N. Brookfield, 2006 WL 8458636, at *9 (D. Mass. 2006). If a subcontractor has “substantially completed” work and has not received from the general contractor “the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor, less any amount retained by the awarding authority as the estimated cost of completing the incomplete and unsatisfactory items of work, the subcontractor may demand direct payment of that balance from the awarding authority.” M.G.L. c. 30, § 39F(d). Section 39F(d) requires that the demand “be by a sworn statement delivered to or sent by certified mail to the awarding authority,” with a copy also delivered to or sent by certified mail to the general contractor. “The demand shall contain a detailed breakdown of the balance due under the subcontract and also a statement of the status of completion of the subcontract work.” Id.

            Sections 39F(d) and (e) set forth the timing requirements for the response to the demand. Specifically, they provide:

(d) . . . Within ten days after the subcontractor has delivered or so mailed the demand to the awarding authority and delivered or so mailed a copy to the general contractor, the general contractor may reply to the demand. The reply shall be by a sworn statement delivered to or sent by certified mail to the awarding authority and a copy shall be delivered to or sent by certified mail to the subcontractor at the same time. The reply shall contain a detailed breakdown of the balance due under the subcontract including any amount due for extra labor and materials furnished to the general

                                                            -3-

contractor and of the amount due for each claim made by the general contractor against the subcontractor.

(e) Within fifteen days after receipt of the demand by the awarding authority, but in no event prior to the seventieth day after substantial completion of the subcontract work, the awarding authority shall make direct payment to the subcontractor of the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor, less any amount (i) retained by the awarding authority as the estimated cost of completing the incomplete or unsatisfactory items of work,

. . . or (iii) disputed by the general contractor in the sworn reply; provided, that the awarding authority shall not deduct from a direct payment any amount as provided in part (iii) if the reply is not sworn to, or for which the sworn reply does not contain the detailed breakdown required by subparagraph (d). . . .

            The undisputed facts, alleged in the Complaint and confirmed by Braintree and Shawmut in their written oppositions and at oral argument, establish that on April 20, 2021, Braintree’s Mayor received a certified letter from Harold Brothers demanding direct payment under M.G.L. c. 30, § 39F(d).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minaya v. Massachusetts Credit Union Share Ins. Corp.
467 N.E.2d 874 (Massachusetts Supreme Judicial Court, 1984)
Pioneer Steel Erectors, Inc. v. Commonwealth
181 N.E.2d 670 (Massachusetts Supreme Judicial Court, 1962)
Jarosz v. Palmer
766 N.E.2d 482 (Massachusetts Supreme Judicial Court, 2002)
Welch v. Sudbury Youth Soccer Ass'n
901 N.E.2d 1222 (Massachusetts Supreme Judicial Court, 2009)
Johnston v. Box
903 N.E.2d 1115 (Massachusetts Supreme Judicial Court, 2009)
Clarke v. Metropolitan District Commission
417 N.E.2d 47 (Massachusetts Appeals Court, 1981)
Tanner v. Board of Appeals
541 N.E.2d 576 (Massachusetts Appeals Court, 1989)
Revoli Construction Co. v. Town of Andover
10 Mass. L. Rptr. 688 (Massachusetts Superior Court, 1999)
E. Amanti & Sons, Inc. v. Triton Regional School District
14 Mass. L. Rptr. 3 (Massachusetts Superior Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
HAROLD BROTHERS MECHANICAL CONTRACTORS, INC. v. TOWN OF BRAINTREE; SHAWMUT WOODWORKING AND SUPPLY, INC., Third-Party, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harold-brothers-mechanical-contractors-inc-v-town-of-braintree-shawmut-masssuperct-2022.