Pinnacle Port Community Association, Inc. v. Charles Orenstein

952 F.2d 375, 1992 U.S. App. LEXIS 1071
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 30, 1992
Docket90-4003
StatusPublished
Cited by3 cases

This text of 952 F.2d 375 (Pinnacle Port Community Association, Inc. v. Charles Orenstein) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinnacle Port Community Association, Inc. v. Charles Orenstein, 952 F.2d 375, 1992 U.S. App. LEXIS 1071 (11th Cir. 1992).

Opinion

952 F.2d 375

PINNACLE PORT COMMUNITY ASSOCIATION, INC., Plaintiff-Appellee,
v.
Charles ORENSTEIN, a Canadian individual, d/b/a Pinnacle
Port Developers, Defendant-Appellant,
Southmark Corporation, a Georgia Corporation, Defendant.

No. 90-4003.

United States Court of Appeals,
Eleventh Circuit.

Jan. 30, 1992.

Donald H. Partington, Clark, Partington, Hart, Larry, Bond, Stackhouse & Stone, Pensacola, Fla., for NA Mortg.

Edmund D. Quintana, Burke & Blue, P.A., Panama City, Fla., for Orenstein.

Jennifer W. Fletcher, Griffin, Cochrane, Marshall & Elger, Atlanta, Ga., for plaintiff-appellee.

Appeals from the United States District Court for the Northern District of Florida.

Before JOHNSON*, MORGAN and SMITH**, Senior Circuit Judges.

JOHNSON, Senior Circuit Judge:

This case arises on appeal following the denial of motions for judgment notwithstanding the verdict (JNOV) and for a new trial after a jury awarded plaintiff nearly two million dollars in compensatory damages against defendant because defendant failed to make contracted repairs to a condominium development.

I. STATEMENT OF THE CASE

A. Background Facts

Defendant Orenstein in 1974 assumed a second mortgage for a condominium project in lieu of the project's foreclosure. When in April of 1979 the project was substantially completed and most of its units were sold, the Pinnacle Port Community Association (Association) reported various problems including the fact that the stucco walls leaked. Orenstein subsequently agreed to make repairs and to post $200,000 as security for the repairs. The North American Mortgage Investors (NAMI), who had provided some of the financing for the project, eventually initiated the repairs in July of 1979. Dissatisfied with the repairs, the Association sued Orenstein in state court. In settlement of the suit the Association released Orenstein from all claims that had been or could have been made against him in return for Orenstein's agreement to complete the repairs in progress within 180 days. While Orenstein did little or nothing pursuant to the stipulation, NAMI continued to pay for the repair work. The repairs were supposedly finished in December of 1979. The walls again leaked, however, during the first rainstorm in January of 1980.

NAMI stopped financing the repairs in August of 1981. The Association subsequently hired its own experts, who recommended entirely new walls and supports. The Association ultimately paid four million dollars for the changes.

B. Procedural History

On September 12, 1984, the Association filed suit against Orenstein and NAMI alleging breach of contract and negligence. The defendants moved for summary judgment on both claims. The district court granted summary judgment on all claims except the breach of contract claim against Orenstein. The Association appealed and this Court reversed and remanded the cause of action. Pinnacle Port Community Ass'n v. Orenstein, 872 F.2d 1536 (11th Cir.1989). The Association subsequently dropped its negligence claims. On remand the jury returned a verdict against each of the defendants for $1.9 million. The district court denied defendants' motions for judgment notwithstanding the verdict (JNOV) and for a new trial. Orenstein now brings this appeal.1

II. ANALYSIS

A. Statute of Limitations

Orenstein argues that the action was barred by the statute of limitations. The district court ruled and the parties on appeal agree that the four-year statute of limitations for actions relating to improvements applies:

(3) WITHIN FOUR YEARS

....

(c) An action founded on the design, planning, or construction of an improvement to real property, with the time running from the date of actual possession by the owner, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his employer; except that, when the action involves a latent defect, the time runs from the time the defect is discovered or should have been discovered with the exercise of due diligence....2

We reject the district court's decision to apply this statute. The district court's choice of the applicable statute of limitations is a question of law that this Court may review de novo. Wheeler v. City of Pleasant Grove, 896 F.2d 1347, 1350 (11th Cir.1990); Lumber & Wood Products, Inc. v. New Hampshire Ins. Co., 807 F.2d 916, 918 (11th Cir.1987). The parties' failure to raise this issue on appeal does not preclude our review. Olson v. Superior Pontiac-GMC, Inc., 776 F.2d 265, 267 (11th Cir.1985).

The four-year statute does not appear to encompass contracts for mere repairs. The statute is directed only to "[a]n action founded on the design, planning, or construction of an improvement...." Fla.Stat.Ann. § 95.11(3)(c) (West 1979) (emphasis added). When reenacting this statute in 1980, moreover, the Florida legislature in an unusual preamble employed only the term "improvement" to denote the type of work affected.3 Although the statute does not define "improvement," the Florida Supreme Court in a different context has defined an improvement as " '[a] valuable addition made to property (usually real estate) or an amelioration in its condition, amounting to more than merely repairs or replacement of waste, costing labor or capital, and intended to enhance its value, beauty or utility or to adapt it for new or further purposes.' " Hillsboro Island House Condominium Apartments, Inc. v. Town of Hillsboro Beach, 263 So.2d 209, 213 (Fla.1972) (quoting Black's Law Dictionary 890 (4th ed. 1969)) (emphasis added).

The stipulated repairs were intended not to enhance the assumed value of the property but to restore the walls to their original watertight state.4 The contracted work, then, was in the nature of repairs. See Black's Law Dictionary 1167 (5th ed. 1979) ("The word 'repair' contemplates an existing structure or thing which has become imperfect, and means to supply in the original structure that which is lost or destroyed, and thereby restore it to the condition in which it originally existed, as near as may be.").5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Companion Property & Casualty Group v. Built Tops Building Services, Inc.
218 So. 3d 989 (District Court of Appeal of Florida, 2017)
Ryan & Jessica Dominguez v. Hayward Industries
201 So. 3d 100 (District Court of Appeal of Florida, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
952 F.2d 375, 1992 U.S. App. LEXIS 1071, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinnacle-port-community-association-inc-v-charles-orenstein-ca11-1992.