Pine QOZB, LLC v. ARCO/Murray National Construction Company, Inc.

CourtDistrict Court, D. Idaho
DecidedMarch 28, 2025
Docket1:24-cv-00295
StatusUnknown

This text of Pine QOZB, LLC v. ARCO/Murray National Construction Company, Inc. (Pine QOZB, LLC v. ARCO/Murray National Construction Company, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pine QOZB, LLC v. ARCO/Murray National Construction Company, Inc., (D. Idaho 2025).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF IDAHO

PINE QOZB, LLC, a Delaware limited liability Case No.: 1:24-cv-00295-BLW-REP company, MEMORANDUM DECISION AND Plaintiff, ORDER RE: PLAINTIFF’S MOTION TO STAY AND DETERMINE vs. ARBITRABILITY (DKT. 4) AND DEFENDANT’S MOTION TO ARCO/MURRAY NATIONAL CONSTRUCTION COMPEL ARBITRATION AND COMPANY, INC., a Delaware corporation, STAY COURT PROCEEDINGS (DKT. 10) Defendant.

Pending before the Court is Plaintiff’s Motion to Stay Arbitration and Determine Arbitrability (Dkt. 4) and Defendant’s Motion to Compel Arbitration and Stay Court Proceedings (Dkt. 10). As discussed below, the Court will deny Plaintiff’s Motion and grant Defendant’s Motion.1 I. BACKGROUND This case involves a construction agreement (Agreement) between Plaintiff Pine QOZB, LLC (Pine) and ARCO/Murray National Construction, Inc. (ARCO), wherein ARCO agreed to build a large apartment complex in Meridian, Idaho. The Agreement contains arbitration and liquidated damages provisions that are the subject of the instant motions. What began as a contractual disagreement over these provisions has evolved into a dispute about payments and damages.

1 “When a district court finds that a lawsuit involves an arbitrable dispute, and a party requests a stay pending arbitration, § 3 of the Federal Arbitration Act compels the court to stay the proceeding.” Smith v. Spizzirri, 601 U.S. 472, 478 (2024). Thus, given that a decision to grant ARCO’s present Motion is not dispositive, the Court issues this Memorandum Decision and Order, rather than a Report and Recommendation. On June 20, 2024, Pine filed a Complaint against ARCO seeking declaratory judgment for alleged liquidated damages wherein it claimed that ARCO failed to timely deliver the Project. (Dkt. 1, p. 4). Approximately one month later, Pine filed its Motion to Stay Arbitration and Determine Arbitrability, arguing that the present dispute is governed by the liquidated damages provision of the Agreement and, therefore, the arbitration provision does not apply. (Dkt. 4).

In its Answer on September 10, 2024, ARCO denied that Pine is entitled to any liquidated damages and that the dispute is subject to the arbitration provision in the Agreement because the fundamental issue is payment obligations. (Dkt. 9). That same day, ARCO filed its Motion to Compel Arbitration and Stay Court Proceedings wherein it emphasized again that it believes Pine has breached its payment obligations which requires arbitration under the relevant provision. (Dkt. 10; Dkt. 11). At the time the Complaint was filed, Pine was undisputedly withholding payment from ARCO based on its claim of liquidated damages. (Dkt. 1, p. 5). Almost five months after filing, however, Pine paid the undisputed amount (“Lien Payoff”). (Dkt. 19). On November 13, 2024,

Pine filed a Supplement in which it explained that the only dispute remaining concerned liquidated damages and committed to continuing its pursuit of them. Id. at 2. On November 9, 2024, ARCO responded and claimed the Lien Payoff confirmed that the dispute involved payment obligations subject to the arbitration provision in the Agreement. (Dkt. 22, p. 3). II. LEGAL STANDARD The Federal Arbitration Act (FAA) applies to arbitration agreements related to interstate commerce. 9 U.S.C. § 2; Southland Corp. v. Keating, 465 U.S. 1, 10-17 (1984); Wattenbarger v. A.G. Edwards & Sons, Inc., 246 P.3d 961, 968 (Idaho 2010). Yet, “where parties have expressly agreed that Idaho law will govern arbitration, the Idaho [Uniform Arbitration Act], not the FAA, applies as the substantive law in arbitration.” Moore v. Omnicare, Inc., 118 P.3d 141, 147 (Idaho 2005) (cleaned up). Under both Idaho law and the FAA, an arbitration provision is “is valid, enforceable and irrevocable, save upon such grounds as exist at law or in equity for the revocation of any contract.” Idaho Code Ann. § 7-901; 9 U.S.C.A. § 2. Additionally, “any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration . . . .” Moses H. Cone Meml. Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24–25 (1983); Shake Out,

LLC v. Clearwater Constr., LLC, 535 P.3d 598, 604 (Idaho 2023) (stating the Idaho Uniform Arbitration Act (IUAA) parallels the FAA). Whether a dispute is subject to an arbitration agreement is a matter of law for the Court to decide. Lewis v. CEDU Educ. Serv., Inc., 135 Idaho 139, 142 (Idaho 2000). Substantial arbitrability is the gateway question a court must answer to determine whether a party agreed to arbitrate the type of dispute before it. Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84 (2002). To do this, courts must determine whether there is a valid and enforceable contract and if the arbitration provision covers the current dispute within its scope. Id. at 84. III. DISCUSSION

A. Arbitration The parties do not dispute the validity of their Agreement or its inclusion of a valid and enforceable arbitration provision. Therefore, the only question before this Court is whether the present dispute falls within the scope of that valid arbitration provision. Pine believes that the present dispute need not be submitted to arbitration because it is fundamentally about liquidated damages which falls under a different provision of the Agreement. Pine argues that the application and calculation of liquidated damages is subject to Section 8 of the Agreement which provides: Contractor acknowledges that Owner will suffer significant financial damages if Contractor does not achieve Substantial Completion of any portion of the Work by the Substantial Completion Deadline for that portion of the Work. Contractor further acknowledges that the actual damages that would likely be incurred by Owner would be expensive and burdensome to dispute. Therefore, in-lieu-of engaging in an expensive and burdensome dispute about actual damages, Owner and Contractor agree that, subject to the terms hereof, if Contractor does not achieve Substantial Completion of any portion of the Work by the Substantial Completion Deadline for that Work, then Contractor will pay Owner, liquidated damages as set forth in the Liquidated Damages Schedule for each day thereafter until Substantial Completion of the applicable Work is achieved. Contractor and Owner agree that the liquidated damages represent a reasonable estimate of the actual damages that would likely be incurred by Owner due to Contractor’s failure to achieve Substantial Completion of the applicable Work by the Substantial Completion Deadline. The liquidated damages provided in the Substantial Completion Schedule are in-lieu-of, and replace, and so Owner hereby waives any loss of use consequential damages incurred by Owner arising from Contractor’s failure to achieve Substantial Completion of the applicable Work by the Substantial Completion Deadline for the applicable Work. (Dkt. 1, Ex. A, § 8.81). Pine maintains that this Section controls because “liquidated damages” is so distinct from “payment obligations” contemplated under the arbitration provision that the arbitration provision does not apply. (Dkt. 4, p. 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southland Corp. v. Keating
465 U.S. 1 (Supreme Court, 1984)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Wattenbarger v. A.G. Edwards & Sons, Inc.
246 P.3d 961 (Idaho Supreme Court, 2010)
Mortensen v. Stewart Title Guaranty Co.
235 P.3d 387 (Idaho Supreme Court, 2010)
Zenner v. Holcomb
210 P.3d 552 (Idaho Supreme Court, 2009)
Lewis v. CEDU Educational Services, Inc.
15 P.3d 1147 (Idaho Supreme Court, 2000)
Moore v. Omnicare, Inc.
118 P.3d 141 (Idaho Supreme Court, 2005)
Lamprecht v. JORDAN, LLC
75 P.3d 743 (Idaho Supreme Court, 2003)
Bakker v. Thunder Spring-Wareham, LLC
108 P.3d 332 (Idaho Supreme Court, 2005)
Smith v. Spizzirri
601 U.S. 472 (Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Pine QOZB, LLC v. ARCO/Murray National Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pine-qozb-llc-v-arcomurray-national-construction-company-inc-idd-2025.