Pillow v. Bechtel Construction, Inc.

201 F.3d 1348, 2000 U.S. App. LEXIS 1029
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 28, 2000
Docket98-4217
StatusPublished
Cited by8 cases

This text of 201 F.3d 1348 (Pillow v. Bechtel Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pillow v. Bechtel Construction, Inc., 201 F.3d 1348, 2000 U.S. App. LEXIS 1029 (11th Cir. 2000).

Opinion

PER CURIAM:

Plaintiffs filed a complaint seeking interest on the damages which they received from Defendant pursuant to a settlement agreement which was approved by the Secretary of Labor. The district court dismissed the complaint for lack of subject matter jurisdiction. We affirm.

BACKGROUND

Over a decade ago, James Pillow, with the assistance of his attorney Michael Seward, brought an administrative action against Bechtel Construction pursuant to the employee protection (“whistleblower”) provisions of the Energy Reorganization Act of 1974 (“ERA”), 42 U.S.C. § 5851. In 1993, the Secretary of Labor (“Secretary”) found that Bechtel violated the statute’s whistleblower provisions and remanded the action to an administrative law judge (“ALJ”) for a hearing on damages. At the resulting hearing, the parties announced that they had reached a settlement on all remanded issues. The parties did not submit a written settlement agreement, but instead relied upon statements made on the record to encompass the entire agreement.

The parties agreed that Bechtel would pay $25,000 in back pay and interest to Pillow, $25,000 in compensatory damages to Pillow, and $250,000 in attorney’s fees to Seward. And, the parties expressly agreed that the settlement did not cover the issue of liability and would not prejudice Bechtel’s right to appeal that issue to *1350 us. Although noting that the disparity between Pillow’s recovery and Seward’s fee was considerable, the ALJ said that he did not consider the attorney’s fee excessive, particularly given Bechtel’s acceptance of the negotiated amount. The ALJ recommended that the agreement be accepted by the Secretary.

Shortly after the hearing, Pillow submitted a letter to the Secretary of Labor requesting that the Secretary double the amount that he was to receive pursuant to the settlement. Because of the letter, the Secretary wrote “there appears not to be consent of all parties to the settlement terms addressed at the hearing on remand. Accordingly, I will order the parties to submit [within 60 days] a written settlement agreement signed by [Pillow, Seward, and Bechtel].”

The parties submitted a written, signed stipulation that provided for the same terms as outlined at the hearing. In 1994, the Secretary approved and adopted the stipulated amounts of backpay and interest, compensatory damages, costs and attorney’s fees. He used these words:

[A]bsent judicial review or if a reviewing court affirms that Bechtel is liable, it is ordered that:
1. Respondent Bechtel Construction, Inc. will pay Complainant James Carroll Pillow, Jr., back pay and interest in the amount of $25,000, and compensatory damages in the amount of $25,000, for a total sum of $50,000.
2. Respondent will pay attorney Michael R. Seward the sum of $250,000.

We affirmed the Secretary’s determination that Bechtel had violated the ERA. See Bechtel Construction v. Secretary of Labor, 98 F.3d 1351 (11th Cir.1996).

Shortly thereafter, Pillow and Seward filed with the Department of Labor an emergency motion seeking an order compelling Bechtel to pay immediately the $300,000 as partial payment of the award. Bechtel responded that the only reason that it had not paid the $300,000 was that “Pillow has told us he would not accept anything less than $365,000, else he would engage [Bechtel] in additional litigation.” Pillow and Seward claimed that interest had accrued on the $300,000 during the pendency of the appeal and that they were now entitled to $365,000. Bechtel disagreed and believed that the payment of $300,000 would satisfy its obligation.

In 1997, Bechtel was ordered to pay $300,000 then to Pillow and Seward; and the parties were instructed to submit documents relevant to the subject of interest and a brief on the issue. In its brief, Bechtel argued that, because a final order of the Secretary of Labor was at issue, 42 U.S.C. § 5851(e) provided that the United States District Court — and not the Administrative Review Board (“ARB”) — had jurisdiction over the matter. 1 The ARB agreed and stated that, once a final decision has been issued, the ARB lacks jurisdiction over a dispute about the proper interpretation of a settlement agreement.

Plaintiffs then filed a complaint in district court seeking an award of interest from the time that the settlement agreement was announced until the time we affirmed the Secretary’s finding that Bechtel was liable. Bechtel filed a motion to dismiss, claiming that the district court lacked subject matter jurisdiction over the controversy and contending that “Plaintiffs have sued Bechtel pursuant to 42 U.S.C. § 5851, where the jurisdiction of this [c]ourt is limited to the enforcement of orders issued by the Secretary of Labor. Here, the Plaintiffs have sued for something never ordered by the Secretary. Thus, the complaint must be dismissed.” Bechtel said that the order from the Secretary required Bechtel to pay $300,000 and did not mention post-award interest. *1351 As it was not disputed that Bechtel had already paid the $300,000, no enforcement was necessary: the district court did not have jurisdiction. Plaintiffs never responded to Bechtel’s motion to dismiss.

The district court granted Bechtel’s motion, saying that, because Defendant paid the full amount ordered by the Secretary of Labor and “[bjecause the Secretary’s order in this case makes no provision for the post-judgment interest Plaintiffs seek, this Court does not have jurisdiction to hear Plaintiffs’ claim.”

DISCUSSION

We review the dismissal of an action for lack of subject matter jurisdiction de novo. See Parise v. Delta Airlines, Inc., 141 F.3d 1463, 1465 (11th Cir.1998).

On appeal, Plaintiffs raise two arguments. The essence of Plaintiffs’ first argument is that the parties had always “understood” that, during the pendency of any appeal, interest was to accrue on the amount the Secretary ordered that Bechtel pay Plaintiffs. Thus, when the Secretary “approved and adopted” their settlement agreement, the “understanding” about interest became part of the Secretary’s order. Therefore, the district court, according to Plaintiffs, had jurisdiction over the complaint: it was an action to enforce an order of the Secretary.

We reject Plaintiffs’ first argument. After the November 1993 hearing, the Secretary, to ensure that all parties consented to the terms of the settlement, required the parties to submit a written settlement agreement signed by — and binding on— the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Support Working Animals, Inc. v. Governor of Florida
8 F.4th 1198 (Eleventh Circuit, 2021)
Crooked Creek Properties, Inc. v. Richard Ensley
660 F. App'x 719 (Eleventh Circuit, 2016)
David L. Lewis, Ph. D. v. John Walker Ph.D.
438 F. App'x 885 (Eleventh Circuit, 2011)
Jbp Acquisitions, Lp v. United States
224 F.3d 1260 (Eleventh Circuit, 2000)
Clyde Thomas Carter v. Bob Rogers
220 F.3d 1249 (Eleventh Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
201 F.3d 1348, 2000 U.S. App. LEXIS 1029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pillow-v-bechtel-construction-inc-ca11-2000.