Pierson v. Willets Point Contracting Corp.

899 F. Supp. 1033, 1995 U.S. Dist. LEXIS 13883, 1995 WL 561874
CourtDistrict Court, E.D. New York
DecidedSeptember 19, 1995
Docket1:88-mj-00743
StatusPublished
Cited by3 cases

This text of 899 F. Supp. 1033 (Pierson v. Willets Point Contracting Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierson v. Willets Point Contracting Corp., 899 F. Supp. 1033, 1995 U.S. Dist. LEXIS 13883, 1995 WL 561874 (E.D.N.Y. 1995).

Opinion

FINDINGS AND FACTS AND CONCLUSIONS OF LAW

HURLEY, District Judge.

INTRODUCTION

By complaint dated March 10, 1988, plaintiffs commenced a diversity action against the corporate defendants for monies allegedly due under a contract dated February 10, 1986.

In its answer, defendant Willets Point Contracting Corporation (‘Willets”), inter alia, counterclaimed for $75,000 it paid to plaintiffs pursuant to what it claims were anticipated “consulting agreements” which never materialized.

The answer of defendant Haulage Enterprises Corporation 1 contains a series of denials, coupled with references to “all the terms and conditions” of the February 10, 1986 Agreement, and of the “contract between defendants and the Town of Oyster Bay” *1035 (Answer ¶¶2-3.) In addition, Haulage Enterprises has asserted an indemnification cross claim against Willets for any sums it, Haulage Enterprises, may be called upon to pay to plaintiffs. That cross claim is based on the Release Agreement between defendants dated August 19, 1987.

The ease was tried non jury before the undersigned in June of 1994.

FINDINGS OF FACTS

Initially, the largely undisputed facts in the ease will be presented by way of background. That will be followed by a synopsis of the trial testimony of each witness, as well as the Court’s finding of fact regarding the contested matters.

1.Factual Background.

In early 1986, a group consisting of (1) Pasquale DiMatteo, who was the President of defendant Haulage Enterprises, (2) John Cameron, (3) Joseph Longo, (4) plaintiff J.J. Pierson and, (5) plaintiff Louis J. DeGange (collectively, the “Haulage Group”), began preparing a bid for a waste disposal contract with the Town of Oyster Bay, Nassau County, New York. The Haulage Group had made arrangements for O’Hara Construction to obtain the multi-million bond needed to submit the bid proposal. However, at the last moment, O’Hara withdrew from the venture. In an effort to remedy that situation, the Haulage Group contacted defendant Wil-lets, an established contractor with considerable experience in major municipal construction projects, although devoid of experience in the waste disposal field. The Haulage Group needed Willets to obtain the bond, and Willets — after some discussion with various members of the Haulage Group — became interested in the Oyster Bay project. As a result, the February 10,1986 Agreement was executed. (Pis.’ Ex. 1.)

The Agreement — which is the focal point of the present dispute — was prepared by plaintiff Pierson and unfortunately is not a model of clarity. Its essential provisions are as follows:

1. Willets and Haulage Enterprises would jointly prepare the bid to the Town of Oyster Bay, which bid would be submitted solely in Willets’s name;

2. Willets was required to secure all bonds needed to bid on the project;

3. Haulage Enterprises was to supply disposal locations, ie. landfills for the solid waste;

4. If Willets was successful in obtaining the Oyster Bay contract:

a) it would name Haulage Enterprises as the subcontractor to perform the contractual obligations with Oyster Bay;
b) Willets would secure all bonds called for under the Oyster Bay contract. However, Haulage Enterprises was required to “secure and execute a performance and payment bond in and for the amount of one-half of the performance bond required under the [Oyster Bay] contract.” That bond was to be delivered by Haulage Enterprises to Willets after the awarding of the contract, and was to “set forth assurances to Willets that Haulage would assume one-half ($) of Willets’s liability to perform the contract.” (Id. at 2, (First) ¶ 6.);
c) pursuant to the second paragraph 6 of the Agreement, the parties were to be paid as follows:
Willets and Haulage [Enterprises] shall divide net profits (and losses) on an equal basis after the following professional fees are paid:
******
c. To J.J. Pierson, Esq., [ ] One Dollar ($1.00) per ton of solid waste transferred, hauled and disposed during the duration of the Contract. This shall represent payment for Legal Services. Payment shall be made in accordance with payments made by the Town to Willets.
d. To Louis J. DeGange [ ], One Dollar ($1.00) per ton of solid waste transferred, hauled and disposed of during the duration of the Contract. This shall represent Transportation Consultant Services. Payment shall be made in accordance with payments made by the Town to Willets.

*1036 In April of 1986, Willets was awarded the Oyster Bay contract. Haulage Enterprises thereafter performed a portion of the work, for which it was paid by Willets the following sums: $100,000 on June 10, 1986; $4,800 on June 20, 1986; $135,000 on June 24, 1986; $15,353.17 on June 26, 1986; and $150,000 in November 1986. In addition, Willets paid the following sums to Pierson: $15,000 on July 16, 1986; $10,000 on August 8, 1986; $5,000 on August 14, 1986; $15,000 on September 19, 1986; $15,000 on November 6, 1986; and $15,000 on November 14, 1986. (Pre-Trial Order ¶ (8)-(9).)

On August 19, 1987, Willets and Haulage Enterprises executed an agreement entitled “Release Agreement.” (Haulage Ex. A.) In that instrument, the parties agreed “to declare ... [the] pre-bid agreement [of February 10, 1986] null and void,” and for Willets to pay $655,025 to Haulage Enterprises as a return of capital invested, and also to identify Haulage Enterprises “for any claims by parties 2 to the [February 10, 1986] agreement.” In addition, Willets made arrangements to acquire the three balers that Haulage Enterprises had purchased as the subcontractor for the Oyster Bay project.

In any event, Willets — initially with Haulage Enterprises, and after August 19, 1987 alone — transferred, hauled and disposed of 610,268.81 tons of solid waste for Oyster Bay from April 8,1986 to August 31,1988. (PreTrial Order ¶ C, C(7).)

The scenario thus far recited rests either on the stipulation of the parties, (Pre-Trial Order ¶ C), or on evidence that was largely undisputed during the trial. Against that backdrop, attention will now be directed to contested matters, including, inter alia, what transpired between the time the Oyster Bay contract was awarded in April of 1986 and August 19, 1987, i.e. the date Willets and Haulage Enterprises parted company via the execution of the Release Agreement.

2. Synopsis of Trial Testimony.

The following witnesses were called by plaintiffs:

a. Kenneth Tully.

The first witness called by plaintiffs was Kenneth Tully, the president of Willets, as well as a 50% shareholder of the corporation. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commissioners of State Insurance Fund v. Photocircuits Corp.
20 A.D.3d 173 (Appellate Division of the Supreme Court of New York, 2005)
Evergreen Marine Corp. v. Welgrow International Inc.
942 F. Supp. 201 (S.D. New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
899 F. Supp. 1033, 1995 U.S. Dist. LEXIS 13883, 1995 WL 561874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierson-v-willets-point-contracting-corp-nyed-1995.